UNITED STATES NU C LE AR RE G ULATO RY C O M M I S S I O N rch 4, 2009
SUBJECT:
ANNUAL ASSESSMENT LETTER - COLUMBIA GENERATING STATION (REPORT 05000397/2009001)
Dear Mr. Parrish:
On February 10, 2009, the NRC staff completed its performance review of the Columbia Generating Station. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2008.
The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security-Related Information" will include the security cornerstone review and resultant inspection plan.
Overall, Columbia Generating Station operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRC=s Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through June 30, 2010. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Energy Northwest -2-If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (817) 860-8249 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
George D. Replogle, Chief Reactor Projects Branch A Division of Reactor Projects Docket: 50-397 License: NPF-21 Enclosure: Columbia Generating Station Inspection/Activity Plan cc w/Enclosure: Lynn Albin Gregory Cullen Department of Health Energy Northwest Regulatory Programs Office of Radiation Protection P.O. Box 968 P.O. Box 47827 Richland, WA 99352-0968 Olympia, WA 98504-7827 Gary Robertson, Director Mike Hammond Division of Radiation Protection Department of Homeland Security Department of Health FEMA/REP P.O. Box 47827 130 228th Street S.W.
Olympia, WA 98504-7827 Bothell, WA 98021-8627 James R. Beaver The Honorable Thomas Moak Benton County Board of Commissioners Mayor of Kennewick P.O. Box 190 City Hall Prosser, WA 99350 210 West 6th Avenue Kennewick, WA 99336 Chair Board of Franklin County Commissioners Bob Hammond 1016 North 4th Street City of Kennewick Pasco, WA 99301 City Managers Office P.O. Box 6108 Susan Reinertson, Regional Director Kennewick, WA 99336 FEMA Region X 130 228th Street, SW Gary Crutchfield Bothell, WA 98021-8627 Pasco City Manager P.O. Box 293 Pasco, WA 99301
Energy Northwest -3-Cindy Johnson City of Richland Nuclear Safety and Energy Siting Division City Hall Oregon Department of Energy 975 George Washington Way 625 Marion Street NE Richland, WA 99352 Salem, OR 97301-3742 The Honorable Joyce Olson Special Hazards Program Manager Mayor of Pasco Washington Emergency Management P.O. Box 293 Division Pasco, WA 99301 127 W. Clark Street Pasco, WA 99301 Larry Jecha, M.D., M.P.H.
District Health Officer Chairman Benton Franklin District Health Dept. Energy Facility Site Evaluation Council 471 Williams Blvd. P.O. Box 43172 Richland, WA 99354 Olympia, WA 98504-3172 The Honorable Dale Jackson Chairman Mayor of West Richland Benton County Board of Commissioners City Hall P.O. Box 190 3801 West Van Giesen Prosser, WA 99350-0190 West Richland, WA 99353 Matt Steuerwalt The Honorable John Fox Executive Policy Division Mayor, City of Richland Office of the Governor P.O. Box 190 P.O. Box 43113 505 Swift Blvd. Olympia, WA 98504-3113 Richland, WA 99352 Ken Niles Jim Mullen, Director Assistant Director Emergency Management Division Nuclear Safety and Energy Siting Division Military Department Oregon Department of Energy Building 20 (MS TA-20) 625 Marion Street NE Camp Murray, WA 98430-5122 Salem, OR 97301-3737 Chairman Chief, Technological Hazards Branch Energy Facility Site Evaluation Council c/o FEMA Region X P.O. Box 43172 Federal Regional Center Olympia, WA 98504-3172 130 228th Street, SW Bothell, WA 98021-9796 William A. Horin, Esq.
Winston & Strawn 1700 K Street Washington, DC 20006-3817
Energy Northwest -4-Regional Administrator (Elmo.Collins@nrc.gov)
DRP Director (Dwight.Chamberlain@nrc.gov)
DRP Deputy Director (Anton.Vegel@nrc.gov)
DRP Director (Roy.Caniano@nrc.gov)
DRP Deputy Director (Troy.Pruett@nrc.gov)
Senior Resident Inspector (Ron.Cohen@nrc.gov)
Branch Chief, DRP/A (George.Replogle@nrc.gov)
Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Regional State Liaison Officer (Bill.Maier@nrc.gov)
RA Secretary (Lucy.Owen@nrc.gov)
DRA Secretary (Judy.Kilcrease@nrc.gov)
Branch Chief, DRS/EB1 (Thomas.Farnholtz@nrc.gov)
Branch Chief, DRS/EB2 (Neil.OKeefe@nrc.gov)
Branch Chief, DRS/PSB1 (Michael.Shannon@nrc.gov)
Branch Chief, DRS/PSB2 (Greg.Werner@nrc.gov)
Branch Chief, DRS/OB (Bernard.Stapleton@nrc.gov)
OEDO, TRPS (Tamara.Bloomer@nrc.gov)
OEDO, TRPB (Stephen.Campbell@nrc.gov)
Deputy Director, DIRS, NRR (Frederick.Brown@nrc.gov)
Director, DORL, NRR (Joseph Giitter@nrc.gov)
Deputy Director, DORL, NRR (Timothy.McGinty@nrc.gov)
Chief, PLB IV, DORL, NRR (Thomas.Hiltz@nrc.gov)
NRR Project Manager (Fred Lyon@nrc.gov)
RIV OEDO Coordinator, Primary (Shawn.Williams@nrc.gov)
RIV OEDO Coordinator, Backup (Eugene.Guthrie@nrc.gov)
RidsNrrDirslpab Resource@nrc.gov ROPreports.Resource@nrc.gov mortensengk@INPO.org File located: R:\_REACTORS\EOC\EOCAssessmentLetters\2008\CGS.doc SUNSI Rev Compl. 7 Yes No ADAMS 7 Yes No Reviewer Initials GR Publicly Avail 7 Yes No Sensitive Yes 7 No Sens. Type Initials GR C:DRP/ D:DRS D:DRP C:DRP/Signature GReplogle RJCaniano DDChamberlain GReplogle
/RA/ /RA/ /RA/ /RA/
2/18/2009 2/18/2009 2/23/2009 2/23/2009 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
Page 1 of 2 Columbia Generating Stati 02/23/2009 12:40:28 Inspection / Activity Plan Report 22 03/01/2009 - 06/30/2010 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EXAM - INITIAL EXAMINATION 7 2 03/16/2009 03/20/2009 X02376 COLUMBIA GENERATING-INITIAL EXAM (2/2009)
EB1-08 - INSERVICE INSPECTION 2 2 05/11/2009 06/12/2009 IP 7111108G Inservice Inspection Activities - BWR RP-ORS4 - OCCUPATIONAL RADIATION SAFETY - ACCESS 1 2 05/18/2009 05/22/2009 IP 7112101 Access Control to Radiologically Significant Areas 2 05/18/2009 05/22/2009 IP 7112102 ALARA Planning and Controls 2 05/18/2009 05/22/2009 IP 71151 Performance Indicator Verification RPTEAM - RADIATION SAFETY TEAM INSPECTION 4 2 07/20/2009 07/24/2009 IP 2515/173 Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 2 07/20/2009 07/24/2009 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 2 07/20/2009 07/24/2009 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 2 07/20/2009 07/24/2009 IP 7112202 Radioactive Material Processing and Transportation 2 07/20/2009 07/24/2009 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program PSB2-52B - BIENNIAL PI&R INSPECTION 5 2 08/17/2009 08/21/2009 IP 71152B Identification and Resolution of Problems 2 08/31/2009 09/04/2009 IP 71152B Identification and Resolution of Problems EP1 - BIENNIAL EP PROGRAM INSPECTION 1 2 08/07/2009 08/21/2009 IP 7111402 Alert and Notification System Testing 2 08/17/2009 08/17/2009 IP 7111404 Emergency Action Level and Emergency Plan Changes 2 08/17/2009 08/21/2009 IP 7111403 Emergency Response Organization Augmentation Testing 2 08/17/2009 08/21/2009 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 2 08/17/2009 08/21/2009 IP 71151 Performance Indicator Verification EXAM - INITIAL EXAM 3 2 08/24/2009 08/28/2009 X02405 INITIAL EXAM-CGS (10/2009)
2 10/05/2009 10/09/2009 X02405 INITIAL EXAM-CGS (10/2009)
EB2-05T - TRIENNIAL FIRE PROTECTION 4 2 09/21/2009 09/24/2009 IP 7111105T Fire Protection [Triennial]
2 10/05/2009 10/09/2009 IP 7111105T Fire Protection [Triennial]
RP-ORS5 - OCCUPATIONAL RADIATION SAFETY - ALARA 1 2 10/26/2009 10/30/2009 IP 7112101 Access Control to Radiologically Significant Areas 2 10/26/2009 10/30/2009 IP 7112102 ALARA Planning and Controls 2 10/26/2009 10/30/2009 IP 71151 Performance Indicator Verification EB2-07T - TRIENNIAL HEAT SINK PERFORMANCE 1 2 03/01/2010 03/05/2010 IP 7111107T Heat Sink Performance This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Columbia Generating Stati 02/23/2009 12:40:28 Inspection / Activity Plan Report 22 03/01/2009 - 06/30/2010 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EB1-21 - COMPONENT DESIGN BASIS INSPECTION 6 2 05/17/2010 05/21/2010 IP 7111121 Component Design Bases Inspection 2 06/01/2010 06/11/2010 IP 7111121 Component Design Bases Inspection This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.