MONTHYEARML0916003362009-06-18018 June 2009 Company, Llc'S Status of Decommissioning Funding Assurance Project stage: Other ML0916001942009-06-18018 June 2009 Company, Llc'S Status of Decommissioning Funding Assurance Project stage: Other ML0916002402009-06-18018 June 2009 Company, Llc'S Status of Decommissioning Funding Assurance Project stage: Other ML0918700662009-07-0707 July 2009 Summary of July 1, 2009, Conference Call with Exelon Generation Company, LLC, on Decommission Funding Assurance Project stage: Other RS-09-095, Decommissioning Funding Assurance Plan2009-07-29029 July 2009 Decommissioning Funding Assurance Plan Project stage: Request RS-09-111, Submittal of Clinton Power Station Site-Specific Safstor Decommissioning Cost Estimate2009-08-27027 August 2009 Submittal of Clinton Power Station Site-Specific Safstor Decommissioning Cost Estimate Project stage: Request ML0927304962009-10-0202 October 2009 RAI Decommissioning Financial Assurance Plans Project stage: RAI RS-09-145, Units 1 & 2 - Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans2009-10-27027 October 2009 Units 1 & 2 - Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans Project stage: Response to RAI RS-09-157, Submittal of Site-Specific Safstor Decommissioning Cost Estimate2009-11-16016 November 2009 Submittal of Site-Specific Safstor Decommissioning Cost Estimate Project stage: Request ML1000601672010-01-0707 January 2010 Request for Additional Information Decommissioning Financial Assurance Plans Project stage: RAI ML1001202412010-01-11011 January 2010 Submittal of Braidwood Station Site-Specific Safstor Decommissioning Cost Estimate Project stage: Request ML1001207712010-01-13013 January 2010 Correction - Braidwood Station, Units 1 and 2; Byron Station, Unit Nos. 1 and 2 - Request for Additional Information Decommissioning Financial Assurance Plans Project stage: RAI RS-10-034, Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans2010-02-15015 February 2010 Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans Project stage: Response to RAI RS-10-051, Submittal of Decommissioning Funding Assurance Calculations2010-03-10010 March 2010 Submittal of Decommissioning Funding Assurance Calculations Project stage: Request ML1011003382010-04-20020 April 2010 Request for Additional Information Regarding to Decommissioning Financial Assurance Plans (Tac Nos. ME0489, ME0490, ME0496, and ME0497) Project stage: RAI ML1014403232010-05-26026 May 2010 Request for Additional Information Regarding the Decommissioning Financial Assurance Plans Project stage: RAI ML1016803572010-06-28028 June 2010 June 2, 2010, Summary of a Telephone Conference Held with Exelon Generation Company, LLC, Regarding Decommissioning Funding Shortfalls Project stage: Other 2010-01-11
[Table View] |
|
---|
Category:Letter type:RS
MONTHYEARRS-24-064, Nuclear Radiological Emergency Plan Document Revisions2024-06-28028 June 2024 Nuclear Radiological Emergency Plan Document Revisions RS-24-066, Inservice Testing Interval Extension for Essential Service Water Valves Due to Required Use of Containment Chiller2024-06-25025 June 2024 Inservice Testing Interval Extension for Essential Service Water Valves Due to Required Use of Containment Chiller RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations RS-24-057, License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink2024-06-0404 June 2024 License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink RS-24-044, License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed2024-05-28028 May 2024 License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed RS-24-043, Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications2024-05-24024 May 2024 Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-026, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR)2024-04-25025 April 2024 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR) RS-24-034, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-04-10010 April 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-24-004, Proposed Alternative to the Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators2024-01-11011 January 2024 Proposed Alternative to the Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators RS-23-118, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information RS-23-117, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information RS-23-114, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2023-11-0101 November 2023 Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds RS-23-100, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections RS-23-093, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel.2023-09-29029 September 2023 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel. RS-23-094, Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 752023-09-29029 September 2023 Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 75 RS-23-091, Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals2023-09-26026 September 2023 Relief Request I4R-25, Alternative Requirements for Reactor Pressure Vessel Inservice Inspection Intervals RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-074, Supplement to Application for License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink2023-06-0909 June 2023 Supplement to Application for License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink RS-23-075, Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process2023-06-0707 June 2023 Application for Technical Specification Improvement to Extend the Completion Time for Condition B of Technical Specification 3.5.1, Accumulators, Using the Consolidated Line Item Improvement Process RS-23-050, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube.2023-05-22022 May 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube. RS-23-056, Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 102023-04-20020 April 2023 Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 10 RS-23-055, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2023-04-10010 April 2023 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-23-052, License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink2023-03-24024 March 2023 License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-038, Response to Request for Additional Information for the Byron Proposal to Reinsert an Accident Tolerant Fuel Lead Test Assembly2023-02-27027 February 2023 Response to Request for Additional Information for the Byron Proposal to Reinsert an Accident Tolerant Fuel Lead Test Assembly RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-118, Withdrawal of License Amendment Request to Revise Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink2022-10-31031 October 2022 Withdrawal of License Amendment Request to Revise Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink RS-22-110, Supplemental Information - Proposed Alternatives Related to the Steam Generators and Request.2022-09-20020 September 2022 Supplemental Information - Proposed Alternatives Related to the Steam Generators and Request. RS-22-097, License Amendment Request to Reinsert an Accident Tolerant Fuel Lead Test Assembly2022-08-31031 August 2022 License Amendment Request to Reinsert an Accident Tolerant Fuel Lead Test Assembly RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-086, R. E. Ginna Nuclear Power Plant - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam.2022-08-10010 August 2022 R. E. Ginna Nuclear Power Plant - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam. RS-22-084, Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator .2022-06-17017 June 2022 Response to Request for Additional Information Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator . RS-22-072, Response to Request for Additional Information Regarding License Amendment to Revise Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink2022-06-0606 June 2022 Response to Request for Additional Information Regarding License Amendment to Revise Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink RS-22-075, License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink2022-06-0202 June 2022 License Amendment to Braidwood Station, Units 1 and 2, Technical Specification 3.7.9, Ultimate Heat Sink RS-22-074, Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds .2022-05-20020 May 2022 Response to Request for Additional Information - Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds . RS-22-073, Supplemental Information Regarding License Amendment Request -Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube.2022-05-19019 May 2022 Supplemental Information Regarding License Amendment Request -Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube. RS-22-037, License Amendment Request - Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control2022-04-21021 April 2022 License Amendment Request - Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control RS-22-057, Constellation Radiological Emergency Plan Addendum Revision2022-04-21021 April 2022 Constellation Radiological Emergency Plan Addendum Revision RS-22-051, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-04-12012 April 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-047, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2022-04-0808 April 2022 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors 2024-06-04
[Table view] |
Text
Exelon Nuclear 4300 Winfield Road Nuclear Warrenville, l L 60555 10 CFR 50.75(f)(I)
February 15,2010 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and STN 50-457 Byron Station, Units 1 and 2 Facility Operating License Nos. NPF-37 and NPF-66 NRC Docket Nos. STN 50-454 and STN 50-455
Subject:
Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans
References:
- 1. Letter from Keith R. Jury (Exelon Generation Company, LLC) to U.S. NRC, "Decommissioning Funding Assurance Plan," dated July 29, 2009
- 2. Letter from Patrick R. Simpson (Exelon Generation Company, LLC) to U.S. NRC, "Response to Request for Additional lnformation Regarding Decommissioning Financial Assurance Plans," dated October 27, 2009
- 3. Letter from Christopher Gratton (U.S. NRC) to Charles G. Pardee (Exelon Generation Company, LLC), "Request for Additional lnformation Re: Decommissioning Financial Assurance Plans,"
dated January 7,201 0 In Reference 3, the NRC requested additional information with respect to the decommissioning funding assurance plan, submitted by Exelon Generation Company, LLC (EGC) in Reference I,for Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, and supplemented by the information submitted by EGC in Reference 2.
February 15, 2010 U.S. Nuclear Regulatory Commission Page 2 The requested information is contained in the Attachment to this letter.
There are no new regulatory commitments made in this letter.
If you have any questions about this letter, please contact me at (630) 657-2823.
R w e c f fully, i & ~ & ~ \0 Patrick R. Simpson Manager - ~icensing Exelon Generation Company, LLC
Attachment:
Response to Request for Additional Information cc: Regional Administrator, U.S. NRC Region Ill U.S. NRC Senior Resident Inspector, Braidwood Station U.S. NRC Senior Resident Inspector, Byron Station
ATTACHMENT RESPONSE TO NRC REQUEST FOR ADDITIONAL INFORMATION Braidwood and Byron Question 1 In accordance with Title 10 of the Code of Federal Regulations (10 CFR), Section 50.75(b)(2):
The NRC reserves the right to take the following steps in order to ensure a licensees adequate accumulation of decommissioning funds; and, either independently or in cooperation with the FERC and the licensees State PUC, take additional actions as appropriate on a case-by-case basis, including modification of a licensees schedule for the accumulation of decommissioning funds.
Provide balances for the respective decommissioning trust funds for Braidwood Unit 1 and Braidwood Unit 2 as of July 31, 2009, August 31, 2009, September 30, 2009 and October 31, 2009.
Provide balances for the respective decommissioning trust funds for Byron Unit 1 and Byron Unit 2 as of July 31, 2009, August 31, 2009, September 30, 2009 and October 31, 2009.
Response to Question 1 The decommissioning trust fund balances for Braidwood Station, Units 1 and 2 and Byron Station, Units 1 and 2 are provided below for the dates requested. Additional information is also provided for November 30, 2009, and December 31, 2009, to show the performance of the trust funds from the time of the submittal of EGCs decommissioning funding assurance plan through the end of 2009, the date EGC will use to calculate any required additional decommissioning funding assurance as described in the Reference.
Braidwood Braidwood Byron Byron Date Unit 1 Unit 2 Unit 1 Unit 2 July 31, 2009 $187.5M $207.1M $210.1M $203.6M August 31, 2009 $193.5M $213.4M $216.4M $209.9M September 30, 2009 $199.3M $219.5M $222.6M $216.0M October 31, 2009 $196.9M $216.9M $220.2M $213.6M November 30, 2009 $203.0M $223.3M $226.7M $219.9M December 31, 2009 $205.2M $225.3M $228.7M $221.9M Braidwood and Byron Question 2 As of November 30, 2009, Exelon has not resolved its shortfall in decommissioning funding assurance for Braidwood Units 1 and 2 and Byron Units 1 and 2 per NRC requirements. Provide additional financial assurance in an amount that will eliminate the decommissioning funding assurance shortfall for 1
Braidwood Units 1 and 2 and Byron Units 1 and 2 prior to December 31, 2009.
Response to Question 2 EGC intends to calculate any shortfall based on the decommissioning trust fund values and the estimated decommissioning costs as of December 31, 2009 as proposed in EGCs decommissioning funding assurance plan submitted in the Reference. Per this plan, EGC also intends to establish this additional financial guarantee by April 1, 2010, in accordance with NRC requirements. The dates set forth in the funding assurance plan were based on the time required to complete updated site-specific estimates for Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, and the time required to obtain the required internal approvals for any required additional financial guarantees, including approval by the Exelon Board of Directors.
Byron and Braidwood Beginning in 1999, provide the year-end balances, dates, and amounts of contributions made by Exelon into each of the decommissioning trust funds associated with Braidwood Units 1 and 2 and Byron Units 1 and 2. The data should be aggregated to show total contributions made.
Response to Byron and Braidwood Request A summary of the year-end balances, and annual contributions made into each of the trust funds for Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2 is given below.
Year-end Balances Braidwood Braidwood Byron Byron Year Unit 1 Unit 2 Unit 1 Unit 2 1999 $154.3M $154.5M $169.7M $156.6M 2000 $153.1M $160.2M $168.2M $161.1M 2001 $145.9M $153.3M $160.0M $153.9M 2002 $133.8M $141.5M $146.5M $141.3M 2003 $155.8M $165.6M $170.6M $164.8M 2004 $169.0M $180.6M $184.9M $179.0M 2005 $179.8M $192.8M $196.7M $190.7M 2006 $204.1M $219.7M $223.0M $216.6M 2007 $217.9M $234.9M $238.3M $231.4M 2008 $165.1M $183.2M $185.8M $180.0M 2009 $205.2M $225.3M $228.7M $221.9M 2
Annual Contributions Braidwood Braidwood Byron Byron Year Unit 1 Unit 2 Unit 1 Unit 2 1999 $474.9K $4,403.4K $2.5K $3,839.8K 2000 $474.9K $4,403.4K $2.5K $3,839.8K 2001 $64.1K $844.8K $9.9K $396.3K 2002 $64.1K $844.8K $9.9K $396.3K 2003 $64.1K $844.8K $9.9K $396.3K 2004 $64.1K $844.8K $9.9K $396.3K 2005 $64.1K $777.8K $9.9K $396.3K 2006 $58.8K $715.9K $9.1K $363.3K 2007 $0 $0 $0 $0 2008 $0 $0 $0 $0 2009 $0 $0 $0 $0
Reference:
Letter from Keith R. Jury (Exelon Generation Company, LLC) to U.S.
NRC, "Decommissioning Funding Assurance Plan," dated July 29, 2009 3