Letter Sequence Other |
|---|
|
|
MONTHYEARRS-09-041, Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC2009-03-31031 March 2009 Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC Project stage: Request ML0916003362009-06-18018 June 2009 Company, LLCs Status of Decommissioning Funding Assurance Project stage: Other ML0916001942009-06-18018 June 2009 Company, LLCs Status of Decommissioning Funding Assurance Project stage: Other ML0916002402009-06-18018 June 2009 Company, LLCs Status of Decommissioning Funding Assurance Project stage: Other ML0916005302009-06-18018 June 2009 Company, LLCs Status of Decommissioning Funding Assurance Project stage: Other ML0916004962009-06-18018 June 2009 Company, LLCs Status of Decommissioning Funding Assurance Project stage: Other ML0916005482009-06-18018 June 2009 Company, LLCs Status of Decommissioning Funding Assurance Project stage: Other ML0916003562009-06-18018 June 2009 Company, LLCs Status of Decommissioning Funding Assurance Project stage: Other ML0918700662009-07-0707 July 2009 Summary of July 1, 2009, Conference Call with Exelon Generation Company, LLC, on Decommission Funding Assurance Project stage: Other RS-09-095, Decommissioning Funding Assurance Plan2009-07-29029 July 2009 Decommissioning Funding Assurance Plan Project stage: Request RS-09-111, Submittal of Clinton Power Station Site-Specific Safstor Decommissioning Cost Estimate2009-08-27027 August 2009 Submittal of Clinton Power Station Site-Specific Safstor Decommissioning Cost Estimate Project stage: Request RS-09-114, Site-Specific Safstor Decommissioning Cost Estimate2009-08-27027 August 2009 Site-Specific Safstor Decommissioning Cost Estimate Project stage: Request ML0927304962009-10-0202 October 2009 RAI Decommissioning Financial Assurance Plans Project stage: RAI RS-09-145, Units 1 & 2 - Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans2009-10-27027 October 2009 Units 1 & 2 - Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans Project stage: Response to RAI RS-09-157, Submittal of Site-Specific Safstor Decommissioning Cost Estimate2009-11-16016 November 2009 Submittal of Site-Specific Safstor Decommissioning Cost Estimate Project stage: Request ML0933706902009-12-10010 December 2009 Status of Decommissioning Funding Assurance Project stage: Other ML0933806182009-12-17017 December 2009 Status of Decommissioning Funding Assurance Project stage: Other ML0933805902009-12-17017 December 2009 Status of Decommission Funding Assurance Project stage: Other ML1000601672010-01-0707 January 2010 Request for Additional Information Decommissioning Financial Assurance Plans Project stage: RAI ML1001202412010-01-11011 January 2010 Submittal of Braidwood Station Site-Specific Safstor Decommissioning Cost Estimate Project stage: Request ML1001207712010-01-13013 January 2010 Correction - Braidwood Station, Units 1 and 2; Byron Station, Unit Nos. 1 and 2 - Request for Additional Information Decommissioning Financial Assurance Plans Project stage: RAI RS-10-034, Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans2010-02-15015 February 2010 Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans Project stage: Response to RAI RS-10-051, Submittal of Decommissioning Funding Assurance Calculations2010-03-10010 March 2010 Submittal of Decommissioning Funding Assurance Calculations Project stage: Request ML1011003382010-04-20020 April 2010 Request for Additional Information Regarding to Decommissioning Financial Assurance Plans (Tac Nos. ME0489, ME0490, ME0496, and ME0497) Project stage: RAI ML1014403232010-05-26026 May 2010 Request for Additional Information Regarding the Decommissioning Financial Assurance Plans Project stage: RAI ML1016803572010-06-28028 June 2010 June 2, 2010, Summary of a Telephone Conference Held with Exelon Generation Company, LLC, Regarding Decommissioning Funding Shortfalls Project stage: Other NRC 2013-0005, License Amendment Request 252, Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2013-01-15015 January 2013 License Amendment Request 252, Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) Project stage: Request NRC 2013-0022, Supplement to License Amendment Request 252 Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2013-03-0101 March 2013 Supplement to License Amendment Request 252 Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) Project stage: Supplement ML13074A0342013-03-12012 March 2013 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance Review License Amendment Request Associated with TS 5.6.5, RCS PTLR Project stage: Acceptance Review ML13098B0702013-03-27027 March 2013 NRR E-mail Capture - Information Needed for Review Project stage: Other NRC 2013-0036, To License Amendment Request 252 Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report2013-04-18018 April 2013 To License Amendment Request 252 Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report Project stage: Request ML13198A1412013-07-11011 July 2013 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Draft Requests for Additional Information (Evib) Supporting Review of LAR to Implement New PTLR Project stage: Draft RAI NRC 2013-0080, License Amendment Request 252 Technical Specification 5.6.5. Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) Response to Request for Additional Information2013-09-12012 September 2013 License Amendment Request 252 Technical Specification 5.6.5. Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) Response to Request for Additional Information Project stage: Response to RAI NRC 2014-0016, Submittal of License Amendment Request 252 Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)- Response to Request for Additional Information2014-03-11011 March 2014 Submittal of License Amendment Request 252 Technical Specification 5.6.5, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)- Response to Request for Additional Information Project stage: Response to RAI ML14122A1252014-06-20020 June 2014 Request for Withholding of Proprietary Information from Public Disclosure Project stage: Withholding Request Acceptance ML14126A3782014-06-30030 June 2014 Issuance of License Amendment Nos. 250 and 254 Regarding Change to Technical Specification 5.6.5, Reactor Coolant System Pressure and Temperature Limits Report Project stage: Approval ML14213A0032014-08-14014 August 2014 Correction to Technical Specification Page 5.6-5 Associated with Amendment Nos. 250 and 254 Project stage: Other 2010-03-10
[Table View] |
Summary of July 1, 2009, Conference Call with Exelon Generation Company, LLC, on Decommission Funding Assurance| ML091870066 |
| Person / Time |
|---|
| Site: |
Byron, Braidwood, Clinton, LaSalle  |
|---|
| Issue date: |
07/07/2009 |
|---|
| From: |
Gratton C Plant Licensing Branch III |
|---|
| To: |
Pardee C Exelon Nuclear |
|---|
| Gratton C, NRR/DORL/LPL3-2, 415-1055 |
| References |
|---|
| TAC ME0489, TAC ME0490, TAC ME0496, TAC ME0497, TAC ME0503, TAC ME0531, TAC ME0532 |
| Download: ML091870066 (4) |
|
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 July 7, 2009 Mr. Charles G. Pardee President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
BRAIDWOOD STATION, UNITS 1 AND 2; BYRON STATION, UNITS 1 AND 2; CLINTON POWER STATION, UNIT 1; LASALLE COUNTY STATION, UNITS 1 AND 2 -
SUMMARY
OF JULY 1,2009, CONFERENCE CALL WITH EXELON GENERATION COMPANY, LLC, ON DECOMMISSION FUNDING ASSURANCE (TAC NOS. ME0489, ME0490, ME0496, ME0497, ME0503, ME0531, AND ME0532)
On July 1, 2009, the Nuclear Regulatory Commission (NRC) staff held a conference call with representatives of Exelon Generation Company, LLC (the licensee). The purpose of the call was to clarify the amount of the decommissioning funding assurance shortfall calculated by the NRC staff for the subject units, to clarify the methodology used by the NRC staff to determine decommissioning funding assurance levels, and to establish a schedule for the submittal of a plan to address the shortfall. A list of attendees is provided as an Enclosure.
For each of the subject units, the NRC staff described its calculation of the minimum amount of financial assurance required by Title 10 of the Code of Federal Regulations (10 CFR),
Sections 50.75(c)(1) and (2). The NRC staff identified the amount credited to the licensee's decommissioning funding assurance total due to contributions, if any, and earnings on its decommissioning trust fund balance. The difference between the minimum required amount and the total amount of decommissioning funding assurance provided, including earnings and contributions, as of December 31, 2008, was identified as a potential shortfall if no adjustments are made by the licensee.
For each unit, the licensee agreed that the amounts described by the NRC staff reflect the licensee's decommissioning funding assurance status as of December 31,2008.
The licensee agreed to submit its plan on or before July 31, 2009, in accordance with the provisions of 10 CFR 50.4. The licensee agreed that its plan will contain sufficient detailed numerical information to permit the staff to evaluate its plan. The submittal will include the final agreed-upon values for the required minimum amount, projected total amount of decommissioning funding assurance, and the potential shortfall as of December 31,2008. The NRC staff agreed that (1) the plan could use the actual date of license expiration as the end date for the earnings credit allowed during operation, and (2) realized earnings to date on trust fund balances could be credited to the total amount of decommissioning funding assurance proposed in the plan.
C. Pardee
- 2 Please direct any inquiries to me at 301-415-1055, or Christopher.Gratton@nrc.gov.
~~
Christopher Gratton, Senior Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-456, STN 50-457, STN 50-454, STN 50-455, 50-461,50-373, and 50-374
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv
LIST OF PARTICIPANTS JULY 1,2009, CONFERENCE CALL WITH EXELON GENERATION COMPANY, LLC DECOMMISSION FUNDING ASSURANCE Christopher Gratton Michael Dusaniwskyj Anneliese Simmons Thomas Fredrichs Beth Mizuno Susan Uttal Theodore Quay Shawn Harwell Exelon Generation Company, LLC Darin Benyak Patrick Simpson J. Bradley Fewell Adam Levin Jeff Dunlap Enclosure
'.. ML091870066 OFFICE DORULPL3-2/PM DORULPL3-2/LA DPRlPFPB/BC DORULPL3-21BC NAME CGratton BTuily for THarris RCarlson SCampbell DATE 7/6/09 7/6/09 717109 717109