Letter Sequence Other |
---|
|
|
MONTHYEARRS-09-041, Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC2009-03-31031 March 2009 Submittal of Exelon Generation Company, LLC, Report on Status of Decommissioning Funding for Reactors Owned by EGC Project stage: Request ML0916003362009-06-18018 June 2009 Company, Llc'S Status of Decommissioning Funding Assurance Project stage: Other ML0916005302009-06-18018 June 2009 Company, Llc'S Status of Decommissioning Funding Assurance Project stage: Other ML0916004962009-06-18018 June 2009 Company, Llc'S Status of Decommissioning Funding Assurance Project stage: Other ML0916005482009-06-18018 June 2009 Company, Llc'S Status of Decommissioning Funding Assurance Project stage: Other ML0916003562009-06-18018 June 2009 Company, Llc'S Status of Decommissioning Funding Assurance Project stage: Other ML0916001942009-06-18018 June 2009 Company, Llc'S Status of Decommissioning Funding Assurance Project stage: Other ML0916002402009-06-18018 June 2009 Company, Llc'S Status of Decommissioning Funding Assurance Project stage: Other ML0918700662009-07-0707 July 2009 Summary of July 1, 2009, Conference Call with Exelon Generation Company, LLC, on Decommission Funding Assurance Project stage: Other RS-09-095, Decommissioning Funding Assurance Plan2009-07-29029 July 2009 Decommissioning Funding Assurance Plan Project stage: Request RS-09-114, Site-Specific Safstor Decommissioning Cost Estimate2009-08-27027 August 2009 Site-Specific Safstor Decommissioning Cost Estimate Project stage: Request RS-09-111, Submittal of Clinton Power Station Site-Specific Safstor Decommissioning Cost Estimate2009-08-27027 August 2009 Submittal of Clinton Power Station Site-Specific Safstor Decommissioning Cost Estimate Project stage: Request ML0920400182009-09-25025 September 2009 Review of Biennial Decommissioning Funding Report and Plan for Projected Shortfall Project stage: Approval ML0927304962009-10-0202 October 2009 RAI Decommissioning Financial Assurance Plans Project stage: RAI RS-09-145, Units 1 & 2 - Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans2009-10-27027 October 2009 Units 1 & 2 - Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans Project stage: Response to RAI RS-09-157, Submittal of Site-Specific Safstor Decommissioning Cost Estimate2009-11-16016 November 2009 Submittal of Site-Specific Safstor Decommissioning Cost Estimate Project stage: Request ML0933706802009-12-10010 December 2009 Correction Letter Regarding Review of Biennial Decommissioning Funding Report and Plan for Projected Shortfall Project stage: Approval ML0933706902009-12-10010 December 2009 Status of Decommissioning Funding Assurance Project stage: Other ML0933805902009-12-17017 December 2009 Status of Decommission Funding Assurance Project stage: Other ML0933806182009-12-17017 December 2009 Status of Decommissioning Funding Assurance Project stage: Other ML1000601672010-01-0707 January 2010 Request for Additional Information Decommissioning Financial Assurance Plans Project stage: RAI ML1001202412010-01-11011 January 2010 Submittal of Braidwood Station Site-Specific Safstor Decommissioning Cost Estimate Project stage: Request ML1001207712010-01-13013 January 2010 Correction - Braidwood Station, Units 1 and 2; Byron Station, Unit Nos. 1 and 2 - Request for Additional Information Decommissioning Financial Assurance Plans Project stage: RAI RS-10-034, Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans2010-02-15015 February 2010 Response to Request for Additional Information Regarding Decommissioning Financial Assurance Plans Project stage: Response to RAI RS-10-051, Submittal of Decommissioning Funding Assurance Calculations2010-03-10010 March 2010 Submittal of Decommissioning Funding Assurance Calculations Project stage: Request ML1011003382010-04-20020 April 2010 Request for Additional Information Regarding to Decommissioning Financial Assurance Plans (Tac Nos. ME0489, ME0490, ME0496, and ME0497) Project stage: RAI ML1014403232010-05-26026 May 2010 Request for Additional Information Regarding the Decommissioning Financial Assurance Plans Project stage: RAI ML1016803572010-06-28028 June 2010 June 2, 2010, Summary of a Telephone Conference Held with Exelon Generation Company, LLC, Regarding Decommissioning Funding Shortfalls Project stage: Other ML14126A3782014-06-30030 June 2014 Issuance of License Amendment Nos. 250 and 254 Regarding Change to Technical Specification 5.6.5, Reactor Coolant System Pressure and Temperature Limits Report Project stage: Approval 2009-08-27
[Table View] |
Summary of July 1, 2009, Conference Call with Exelon Generation Company, LLC, on Decommission Funding AssuranceML091870066 |
Person / Time |
---|
Site: |
Byron, Braidwood, Clinton, LaSalle |
---|
Issue date: |
07/07/2009 |
---|
From: |
Gratton C Plant Licensing Branch III |
---|
To: |
Pardee C Exelon Nuclear |
---|
Gratton C, NRR/DORL/LPL3-2, 415-1055 |
References |
---|
TAC ME0489, TAC ME0490, TAC ME0496, TAC ME0497, TAC ME0503, TAC ME0531, TAC ME0532 |
Download: ML091870066 (4) |
|
|
---|
Category:Letter
MONTHYEARIR 05000461/20240032024-11-0505 November 2024 Integrated Inspection Report 05000461/2024003 RS-24-104, Nuclear Radiological Emergency Plan Document Revision2024-11-0101 November 2024 Nuclear Radiological Emergency Plan Document Revision IR 05000373/20243012024-10-31031 October 2024 Initial License Examination Report 05000373/2024301 05000374/2024301 IR 05000461/20244032024-10-24024 October 2024 – Security Baseline Inspection Report 05000461/2024403 IR 05000461/20244022024-10-24024 October 2024 – Security Baseline Inspection Report 05000461/2024402 ML24285A1452024-10-24024 October 2024 Ltr. to Gail Cheatham, Kickapoo Tribe of Indians of the Kickapoo Reservation in Ks Re CPS Sect 106 Consult ML24285A1472024-10-24024 October 2024 Ltr. to Geoffrey M. Standing Bear, Principal Chief, Osage Nation Re CPS Section 106 Consultation ML24285A1422024-10-24024 October 2024 Ltr. to Darwin Kaskaske, Chairman, Kickapoo Tribe of Oklahoma Re CPS Section 106 Consultation ML24285A1442024-10-24024 October 2024 Ltr. to Estavio Elizondo, Sr., Chairman, Kickapoo Traditional Tribe of Texas Re CPS Section 106 Consultation ML24285A1462024-10-24024 October 2024 Ltr. to Gena Kakkak, Chairwoman, Menominee Indian Tribe of Wisconsin Re CPS Section 106 Consultation ML24285A1482024-10-24024 October 2024 Ltr. to Joseph Rupnick, Chairman, Prairie Band Potawatomi Nation Re CPS Section 106 Consultation ML24283A1642024-10-23023 October 2024 Summary of the 2024 Environmental Audit Related to the Review of the License Renewal Application Environmental Report (EPID Number L-2024-LNE-0000)(Docket Number:50-461) RS-24-098, Units 1 and 2 - Supplement to License Amendment Request to Revise Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel Assembly Storage, 4.3.1, Fuel Storage, Criticality2024-10-23023 October 2024 Units 1 and 2 - Supplement to License Amendment Request to Revise Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel Assembly Storage, 4.3.1, Fuel Storage, Criticality ML24297A2702024-10-23023 October 2024 Notification of NRC Baseline Inspection and Request for Information: Inspection Report 05000455/2025002 IR 05000373/20244042024-10-23023 October 2024 County Station – Security Baseline Inspection Report 05000373/2024404 and 05000374/2024404 ML24285A1432024-10-21021 October 2024 Ltr. to Douglas Lankford, Chief, Miami Tribe of Oklahoma Re CPS Section 106 Consultation ML24285A1412024-10-21021 October 2024 Ltr. to Craig Harper, Chief, Peoria Tribe of Oklahoma Re CPS Section 106 Consultation ML24291A0012024-10-17017 October 2024 Submittal of Core Operating Limits Report, Cycle 25 RS-24-095, Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals2024-10-10010 October 2024 Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000373/LER-2023-001-01, Air Circuit Breaker (Acb) Mechanically Operated Contacts (MOC) Switch Failed to Actuate2024-10-0909 October 2024 Air Circuit Breaker (Acb) Mechanically Operated Contacts (MOC) Switch Failed to Actuate ML24281A1502024-10-0707 October 2024 Request for Information for NRC Commercial Grade Dedication Inspection Report 05000454/2025010 and 05000455/2025010 ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000373/20244012024-09-27027 September 2024 County Station – Security Baseline Inspection Report 05000373/2024401 and 05000374/2024401 ML24215A2932024-09-27027 September 2024 Scoping Summary Letter 05000461/LER-2023-002-01, Reactor Core Isolation Cooling Inoperable Prior to Mode Change2024-09-24024 September 2024 Reactor Core Isolation Cooling Inoperable Prior to Mode Change ML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary BYRON 2024-0046, Cycle 27 Core Operating Limits Report2024-09-19019 September 2024 Cycle 27 Core Operating Limits Report ML24263A2062024-09-19019 September 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for LaSalle County Station - Holtec MPC-68MCBS ML24260A0492024-09-16016 September 2024 Operator Licensing Examination Approval - Lasalle County Station, Unit 1 and 2, September 2024 RS-24-088, Relief Requests Associated with the Fifth Inservice Inspection Interval2024-09-13013 September 2024 Relief Requests Associated with the Fifth Inservice Inspection Interval IR 05000456/20240112024-09-12012 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000456/2024011 and 05000457/2024011 RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24211A2302024-09-11011 September 2024 – Request for Partial Site Release for Facility Operating License No. NPF-62 ML24164A0032024-09-10010 September 2024 Issuance of Amendment Nos. 235 and 235 Revision of Technical Specifications for the Ultimate Heat Sink RS-24-087, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2024-09-0909 September 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station IR 05000461/20240112024-09-0909 September 2024 Commercial Grade Dedication Inspection Report 05000461/2024011 ML24250A1182024-09-0606 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification 05000454/LER-2024-001, Both Trains of Control Room Ventilation Temperature Control System Inoperable2024-09-0505 September 2024 Both Trains of Control Room Ventilation Temperature Control System Inoperable ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000373/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Lasalle County Station (Report 05000373/2024005; 05000374/2024005) IR 05000456/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2024005 and 05000457/2024005) IR 05000461/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Clinton Power Station (Report 05000461/2024005) ML24227A0522024-08-29029 August 2024 Audit Plan for LAR to Remove ATWS Mtc Limit IR 05000454/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Byron Station, Units 1 and 2 (Report 05000455/2024005 and 05000454/2024005) IR 05000373/20244022024-08-28028 August 2024 County Station - Cyber Security Inspection Report 05000373/2024402 and 05000374/2024402 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24222A3952024-08-23023 August 2024 Regulatory Audit Report to Support the Review of the Amendments to Revise Reactor Water Cleanup Valve Isolation Timing 05000373/LER-2024-004-01, Emergency Diesel Generator Auto-Start and Load Due to Loss of System Auxiliary Transformer2024-08-22022 August 2024 Emergency Diesel Generator Auto-Start and Load Due to Loss of System Auxiliary Transformer 2024-09-09
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 July 7, 2009 Mr. Charles G. Pardee President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
BRAIDWOOD STATION, UNITS 1 AND 2; BYRON STATION, UNITS 1 AND 2; CLINTON POWER STATION, UNIT 1; LASALLE COUNTY STATION, UNITS 1 AND 2 -
SUMMARY
OF JULY 1,2009, CONFERENCE CALL WITH EXELON GENERATION COMPANY, LLC, ON DECOMMISSION FUNDING ASSURANCE (TAC NOS. ME0489, ME0490, ME0496, ME0497, ME0503, ME0531, AND ME0532)
On July 1, 2009, the Nuclear Regulatory Commission (NRC) staff held a conference call with representatives of Exelon Generation Company, LLC (the licensee). The purpose of the call was to clarify the amount of the decommissioning funding assurance shortfall calculated by the NRC staff for the subject units, to clarify the methodology used by the NRC staff to determine decommissioning funding assurance levels, and to establish a schedule for the submittal of a plan to address the shortfall. A list of attendees is provided as an Enclosure.
For each of the subject units, the NRC staff described its calculation of the minimum amount of financial assurance required by Title 10 of the Code of Federal Regulations (10 CFR),
Sections 50.75(c)(1) and (2). The NRC staff identified the amount credited to the licensee's decommissioning funding assurance total due to contributions, if any, and earnings on its decommissioning trust fund balance. The difference between the minimum required amount and the total amount of decommissioning funding assurance provided, including earnings and contributions, as of December 31, 2008, was identified as a potential shortfall if no adjustments are made by the licensee.
For each unit, the licensee agreed that the amounts described by the NRC staff reflect the licensee's decommissioning funding assurance status as of December 31,2008.
The licensee agreed to submit its plan on or before July 31, 2009, in accordance with the provisions of 10 CFR 50.4. The licensee agreed that its plan will contain sufficient detailed numerical information to permit the staff to evaluate its plan. The submittal will include the final agreed-upon values for the required minimum amount, projected total amount of decommissioning funding assurance, and the potential shortfall as of December 31,2008. The NRC staff agreed that (1) the plan could use the actual date of license expiration as the end date for the earnings credit allowed during operation, and (2) realized earnings to date on trust fund balances could be credited to the total amount of decommissioning funding assurance proposed in the plan.
C. Pardee -2 Please direct any inquiries to me at 301-415-1055, or Christopher.Gratton@nrc.gov.
~~
Christopher Gratton, Senior Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. STN 50-456, STN 50-457, STN 50-454, STN 50-455, 50-461,50-373, and 50-374
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv
LIST OF PARTICIPANTS JULY 1,2009, CONFERENCE CALL WITH EXELON GENERATION COMPANY, LLC DECOMMISSION FUNDING ASSURANCE Christopher Gratton Michael Dusaniwskyj Anneliese Simmons Thomas Fredrichs Beth Mizuno Susan Uttal Theodore Quay Shawn Harwell Exelon Generation Company, LLC Darin Benyak Patrick Simpson J. Bradley Fewell Adam Levin Jeff Dunlap Enclosure
' .. ML091870066 OFFICE DORULPL3-2/PM DORULPL3-2/LA DPRlPFPB/BC DORULPL3-21BC NAME CGratton BTuily for THarris RCarlson SCampbell DATE 7/6/09 7/6/09 717109 717109