ML101481076

From kanterella
Revision as of 17:39, 13 November 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Semi-Annual Power Uprate Survey
ML101481076
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 05/27/2010
From: Feintuch K
Plant Licensing Branch III
To: Browning T
NextEra Energy Duane Arnold
Feintuch K, NRR/DORL/LPL3-1, 415-3079
References
Download: ML101481076 (3)


Text

From: F@intucn, Karl Sent: Thursday, May 27, 20102:37 PM To: 'Browning, Tony' Cc;: 'Thomas.Byrne@nexteraenergy.com'

Subject:

Seml*Annual Power Uprate Survey Attachments: June.2010.Survey.doc Importance: High Attached Is a survey, which is conducted semi-annually. lnatructlons for interpreting the requested information are included on the one page survey. We have been asked to submit results internally by June 10, 2010. If you could respond to me by June 8, 2010, I would appreciate it..

Thank you for your assistance with this survey.

Karl Feintuch Project Manager USNRC 301-415-3079 This syrvl;Y has been approved by Joe Giitter.

This survey contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These Information collections were approved by the Office of Management and Budget (OMB), approval number 3150-0011.

E-mail Properties Mail Envelope Properties (26E42474DB238C408C94990815A02F0906DF144DFD)

Subject:

Semi-Annual Power Uprate Survey Sent Date: 5/27/20102:36:41 PM Received Date: 5/27/20102:36:00 PM From: Feintuch, Karl Created By: Karl.Feintuch@nrc.gov Recipients:

Tony.Browning@nexteraenergy.com ('Browning, Tony')

Tracking Status: None Thomas.Byrne@nexteraenergy.com ('Thomas.Byrne@nexteraenergy.com')

Tracking Status: None Post Office:

HQCLSTROl.nrc.gov Files Size Date & Time MESSAGE 47485 5/27/2010 June.20 1a.Survey.doc 37562 Options Expiration Date:

Priority: olImportanceHigh ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received:

SEMI-ANNUAL POWER UPRATE SURVEY (§-MAIL TQ LICENSEES)

(This survey is to be a-mailed to all power reactor licensees, regardless of whether a licensee has received a power uprate in the past or currently has a power uprate under NRC review. If you currently have a power uprate under NRC review, do not complete the survey with respect to that uprate. Instead, complete the survey with respect to any additional, future, power uprate applications that may be planned.)

1. Plant Name (Complete a separate survey for each unit at multi-unit sites.)
2. Unit Number
3. Do you plan to apply for a power uprate in the next 5 years? Yes I No (If answer to number 3 is no. skip 4, 5, and 6 and answer number 7.)
4. What percent increase in power from the current licensed thermal power (CLTP) limit do you plan to apply for?
5. What is the planned increase from the CLPT limit in megawatts thermal?
6. What is the expected schedule for filing the application (month/year)?

(If the month is not known, provide the quarter andlor year.)

7. Can the NRC staff make the above information public? Yes I No*
  • If you select "no" above, the information you provide will be initially withheld from public disclosure. In addition, pursuant to 10 CFR 2.390(b)(1)(ji), the NRC is waiving the affidavit requirements on its own initiative, as the NRC has determined that it is appropriate to do so in this case since responses to the survey that contain business sensitive information, the disclosure of which is likely to cause competitive harm, are considered by the NRC to constitute proprietary information. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information.

In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure. For example, you may be requested to submit an affidavit at that time.

This survey contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 at seq.). These information collections were approved by the Office of Management and Budget (OMB), approval number 3150-0011.

The burden to the public for this voluntary information collection is estimated to be 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> per response. Send comments regarding this burden estimate to the Informetion Services Branch (T-5 F53), U.S. Nuclear Regulatory Commission, WaShington, DC 20555-0001, or by Internet electronic mail to INFOCOLLECTS.Resource@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0011), Office of Management and Budget, Washington, DC 20503.

Public Protection Notification The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid OMB control number.

Enclosure