5-14-2014 | On March 17, 2014, at 12:02 Central Daylight Time ( CDT), a turbine trip and subsequent reactor trip occurred while operating at nominal 100 percent power. Maintenance was in progress on the main generator stator cooling system when system inventory was lost resulting in an automatic turbine trip due to low system pressure.
Immediate response by operations personnel included implementing procedure emergency operating procedure (EOP) -00, Standard Post Trip Actions, and subsequent entry into procedure EOP-01, Reactor Trip Recovery.
Based on plant system response this is considered an uncomplicated trip.
The station determined that the root cause of the plant trip was that operational risk was not effectively identified or mitigated by individuals throughout the organization.
The leak was isolated shortly after the trip by fully removing the probe and closing the isolation valve. Fort Calhoun Station will be implementing the Exelon risk management procedure, WC-AA-104, Integrated Risk Management. This procedure provides direction consistent with industry best practices, and requires individual review of each category of risk identification and mitigation. |
---|
Reported lessons learned are incorporated into the licensing process and fed back to industry.
Send comments regarding burden estimate to the FOIA, Pnvacy and Information Collections Branch (T-5 F53). U.S Nuclear Regulatory Commission, Washington, DC 20555-0001 or by internet e-mail to Infocollects.Resource@nrcigov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB 10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. a means ,,sec to impose an information collection does not display a currently valid CMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the informatior collection
BACKGROUND
Fort Calhoun Station (FCS) is a two-loop reactor coolant system of Combustion Engineering design.
EVENT DESCRIPTION
On March 17, 2014, at 12:02 Central Daylight Time (CDT), a turbine trip and subsequent reactor trip occurred while operating at nominal 100 percent power. Maintenance was in progress on the main generator stator water cooling system when system inventory was lost resulting in an automatic turbine trip due to low system pressure. Immediate response by operations personnel included implementing procedure EOP-00, Standard Post Trip Actions, and subsequent entry into procedure EOP-01, Reactor Trip Recovery. Based on plant system response this is considered an uncomplicated trip.
The loss of stator water cooling system inventory occurred during the removal of generator stator water cooling conductivity electrode number CE-5043-1 for calibration. The installed safety knob did not prevent the probe from being removed from the system causing a stator water cooling leak. The technicians were unable to isolate the leak in time to prevent a turbine trip. The leak was isolated shortly after the trip by fully removing the probe and closing the isolation valve.
At 1455 Central Daylight Time (CDT), the Headquarter Operations Officer (H00) was informed of the event per 10 CFR 50.72(b)(2)(iv)(B) (RPS Actuation) and 50.72(b)(3)(iv)(A) (Specified System Actuation (RPS)). This report is being submitted pursuant to 10 CFR 50.73(a)(2)(iv)(A), Specified System Actuation (RPS).
CONCLUSION
Fort Calhoun Station's (FCS's) risk management processes and individual behaviors/mindsets were investigated to determine the root and contributing causes of this event. The RCA team reviewed FCS procedures, standards, and expectations regarding operational risk assessment. Interviews were then conducted to determine if individual behaviors/mindsets and station culture was in line with established expectations.
The investigation concluded that there were shortfalls in individuals' mindsets and in the level of detail in the Station's risk management procedures. Mindsets and accountability contributed to the cause of this event, and current Station procedures and guidelines are not sufficiently detailed to ensure workers are not in a knowledge based performance mode when assessing risk just prior to job execution. Individual behaviors, mindset, and knowledge levels, as well as Station procedures and processes need to be at a level to ensure risk identification and mitigation actions are adequately evaluated prior to the job scheduled start time.
The Station determined that the root cause of the plant trip was that operational risk was not effectively identified or mitigated by individuals throughout the organization.
Fort Calhoun Station Reported lessons learned are incorporated into the licensing process and fed back to industry Send comments regarding burden estimate to the FOIA, Pnvacy and Information Collections Branch (T-5 F53), U.S Nuclear Regulatory Commission Washington, DC 20555-0001, or by Internet e-mail to Infocotlects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104) Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not requ'red to respond to, the information collection Fort Calhoun Station
2. DOCKET
YEAH
3 OF
CORRECTIVE ACTIONS
The leak was isolated shortly after the trip by fully removing the probe and closing the isolation valve.
Long Term Corrective Actions To correct the root cause Fort Calhoun Station will be implementing the Exelon risk management procedure, WC-AA-104, Integrated Risk Management. This procedure provides direction consistent with industry best practices, and requires individual review of each category of risk identification and mitigation.
SAFETY SIGNIFICANCE
The loss of stator water cooling pressure caused a turbine trip to protect the main generator as designed. Plant safety systems shutdown the reactor plant and support systems operated as designed. One non-safety bus was wetted and then deenergized as a precautionary measure. No equipment was damaged. The plant trip is considered uncomplicated.
SAFETY SYSTEM FUNCTIONAL FAILURE
This does not represent a safety system functional failure in accordance with NEI 99-02, revision 7.
PREVIOUS EVENTS
None.
|
---|
|
|
| | Reporting criterion |
---|
05000285/LER-2014-001 | Reactor Shutdown due to Sluice Gate Failure | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000285/LER-2014-002 | Reactor Manual Trip due to Control Rod Misalignment | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000285/LER-2014-003 | Reactor Trip Due to Stator Water Cooling Leak During Maintenance | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000285/LER-2014-004 | Unqualified Limit Switches Render Safety Equipment Inoperable | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ix)(A), Prevented Safety Function in Multiple System | 05000285/LER-2014-005 | Technical Specification Violation of Containment Integrity | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000285/LER-2014-006 | ler Omaha Public Power District 444 South 16th Street Mall Omaha, NE 68102-2247 10 CFR 50.73 LIC-14-0123 November 12, 2014 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Fort Calhoun Station, Unit No. 1 Renewed Facility Operating License No. DPR-40 NRC Docket No. 50-285 Subject: Licensee Event Report 2014-006, Revision 0, for the Fort Calhoun Station Please find attached Licensee Event Report 2014-006, Revision 0. This report is being submitted pursuant to 10 CFR 50.73(a)(2)(i)(B). There are no new commitments being made in this letter. If you should have any questions, please contact Terrence W. Simpkin, Manager, Site Regulatory Assurance, at (402) 533-6263. Louis P. Cortopassi Site Vice President and CNO LPC/epm Attachment c: M. L. Dapas, NRC Regional Administrator, Region IV C. F. Lyon, NRC Senior Project Manager S.M. Schneider, NRC Senior Resident Inspector NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION (02-2014) LICENSEE EVENT REPORT (LER) (See Page 2 for required number of digits/characters for each block) APPROVED BY OMB: NO. 3150-0104 EXPIRES: 01/31/2017 Estimated burden per response to comply with this mandatory collection request 80 hou rs. Reported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the FOIA, Privacy a nd Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 205 55-0001, or by intemet e-mail to Infocollects.Resource@nrogov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. 1. FACILITY NAME Fort Calhoun Station 2. DOCKET NUMBER 05000285 3. PAGE 1 OF 3 Inoperability of Radiation Monitors Due to an Error in Technical Specifications | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000285/LER-2014-007 | AMIN& 1111111106 1111111111111 11111111111111111 IlMr111111.11 11111Wil Omaha Parthfic ifitswerOistrid 444 South le Street Mall Omaha, NE 68102-2247 10 CFR 50.73 LIC-15-0001 February 13, 2015 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Fort Calhoun Station, Unit No. 1 Renewed Facility Operating License No. DPR-40 NRC Docket No. 50-285 Subject: Licensee Event Report 2014-007, Revision 0, for the Fort Calhoun Station Please find attached Licensee Event Report 2014-007, Revision 0. This report is being submitted pursuant to 10 CFR 50.73(a)(2)(iv)(A), Specified System Actuation (RPS). There are no new commitments being made in this letter. If you should have any questions, please contact Terrence W. Simpkin, Manager, Site Regulatory Assurance, at (4s2) 533-6263. Lo s P. Cortopassi Site Vice President and CNO LPC/epm Attachment c: M. L. Dapas, NRC Regional Administrator, Region IV C. F. Lyon, NRC Senior Project Manager S.M. Schneider, NRC Senior Resident Inspector NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION (02-2014) LICENSEE EVENT REPORT (LER) (See Page 2 for required number of digits/characters for each block) APPROVED BY OMB: NO. 3160-0104 EXPIRES: 01131/2017 Estimated burden per response to comply with this mandatory collection request 80 hours. Reported lessons learned are incorporated into the licensing process and led back to industry. Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by interne' e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (31500104), Office of Management and Budget, Washington. DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the Information collection. 1. FACILITY NAME Fort Calhoun Station ,2. DOCKET NUMBER 05000285 3. PAGE 1 OF 3 Plant Trip Due to Moisture Intrusion into a Transformer Control Cabinet | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
|