After reaching criticality on January 12, 2014, the control room attempted to reduce power ascension rate while at zero percent power by inserting Group 4 CEAs. All Group 4 CEAs inserted with the exception of control rod RC-10-41, which failed to move. Group 4 was inserted further until a 10 inches deviation existed between RC-10-41 and the remaining Group 4 CEAs. Power continued to slowly rise and the Control Room conservatively decided to manually trip the reactor with the existing deviation.
On January 12, 2014, at 0323 the reactor was manually tripped due to reactor power rising with RC-10- 41 deviation. Control room entered EOP-00, Standard Post Trip Actions, and exited AOP-2. All CEAs inserted into the reactor as expected following the trip.
Troubleshooting determined that the rectifier for RC-10-41 had failed.
The failed CEDM rectifier and associated fuses for RC-10-41 were replaced.
Additional review of the rectifier failure is being performed and any significant findings will be addressed in a supplement to this LER if needed. |
BACKGROUND
Fort Calhoun Station (FCS) is a two-loop reactor coolant system of Combustion Engineering (CE) design.
The Control Element Drive Mechanism (CEDM) functions to raise or lower its respective Control Element Assembly (CEA) in response to signals from the Control Room. The CEDM includes the upper components that drive the movement such as the drive package containing the motor/brake. It also includes lower components such as the drive shaft, bevel gears, and rack and pinion which are contained in the support tube assembly.
EVENT DESCRIPTION
After reaching criticality on January 12, 2014, the control room attempted to reduce power ascension rate, while at zero percent power, by inserting Group 4 CEAs. All Group 4 CEAs inserted with the exception of control rod RC-10-41, which failed to move. Group 4 was inserted further until a 10" deviation existed between RC-10-41 and the remaining Group 4 CEAs. Power continued to rise slowly and the Control Room conservatively decided to manually trip the reactor. On January 12, 2014, at 0323 the reactor was manually tripped due to reactor power rising with RC-10-41 deviation.
The control room entered EOP-00, Standard Post Trip Actions, and exited AOP-2. All CEAs inserted into the reactor as expected following the trip. At 0644 Central Standard Time (CST) NRC Headquarter Operations Office (H00) was notified of the reactor trip per 10 CFR 50.72(b)(2)(iv)(B) and (b)(3)(iv). This event is reportable per 50.73(a)(2)(iv)(A). This issue was entered in to the corrective action system as CR2014-00485.
CONCLUSION
Troubleshooting determined that the rectifier for CEDM RC-10-41 had failed. Additional review of the rectifier failure is being performed and any significant findings will be addressed in a supplement to this LER if needed.
CORRECTIVE ACTIONS
Immediate Corrective Actions
The failed CEDM rectifier and associated fuses for RC-10-41 were replaced.
SAFETY SIGNIFICANCE
Although the failure of the rectifier and associated fuse would not allow the CEDM to be manually repositioned the failure mechanism has no impact on the ability of the reactor trip (redundant rapid shutdown) circuitry to allow tripping this rod or tripping the reactor.
SAFETY SYSTEM FUNCTIONAL FAILURE
This does not represent a safety system functional failure in accordance with NEI 99-02. Revision 7.
PREVIOUS EVENTS
|
---|
|
|
| | Reporting criterion |
---|
05000285/LER-2014-001 | Reactor Shutdown due to Sluice Gate Failure | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000285/LER-2014-002 | Reactor Manual Trip due to Control Rod Misalignment | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000285/LER-2014-003 | Reactor Trip Due to Stator Water Cooling Leak During Maintenance | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000285/LER-2014-004 | Unqualified Limit Switches Render Safety Equipment Inoperable | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ix)(A), Prevented Safety Function in Multiple System | 05000285/LER-2014-005 | Technical Specification Violation of Containment Integrity | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000285/LER-2014-006 | ler Omaha Public Power District 444 South 16th Street Mall Omaha, NE 68102-2247 10 CFR 50.73 LIC-14-0123 November 12, 2014 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Fort Calhoun Station, Unit No. 1 Renewed Facility Operating License No. DPR-40 NRC Docket No. 50-285 Subject: Licensee Event Report 2014-006, Revision 0, for the Fort Calhoun Station Please find attached Licensee Event Report 2014-006, Revision 0. This report is being submitted pursuant to 10 CFR 50.73(a)(2)(i)(B). There are no new commitments being made in this letter. If you should have any questions, please contact Terrence W. Simpkin, Manager, Site Regulatory Assurance, at (402) 533-6263. Louis P. Cortopassi Site Vice President and CNO LPC/epm Attachment c: M. L. Dapas, NRC Regional Administrator, Region IV C. F. Lyon, NRC Senior Project Manager S.M. Schneider, NRC Senior Resident Inspector NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION (02-2014) LICENSEE EVENT REPORT (LER) (See Page 2 for required number of digits/characters for each block) APPROVED BY OMB: NO. 3150-0104 EXPIRES: 01/31/2017 Estimated burden per response to comply with this mandatory collection request 80 hou rs. Reported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the FOIA, Privacy a nd Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 205 55-0001, or by intemet e-mail to Infocollects.Resource@nrogov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. 1. FACILITY NAME Fort Calhoun Station 2. DOCKET NUMBER 05000285 3. PAGE 1 OF 3 Inoperability of Radiation Monitors Due to an Error in Technical Specifications | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000285/LER-2014-007 | AMIN& 1111111106 1111111111111 11111111111111111 IlMr111111.11 11111Wil Omaha Parthfic ifitswerOistrid 444 South le Street Mall Omaha, NE 68102-2247 10 CFR 50.73 LIC-15-0001 February 13, 2015 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Fort Calhoun Station, Unit No. 1 Renewed Facility Operating License No. DPR-40 NRC Docket No. 50-285 Subject: Licensee Event Report 2014-007, Revision 0, for the Fort Calhoun Station Please find attached Licensee Event Report 2014-007, Revision 0. This report is being submitted pursuant to 10 CFR 50.73(a)(2)(iv)(A), Specified System Actuation (RPS). There are no new commitments being made in this letter. If you should have any questions, please contact Terrence W. Simpkin, Manager, Site Regulatory Assurance, at (4s2) 533-6263. Lo s P. Cortopassi Site Vice President and CNO LPC/epm Attachment c: M. L. Dapas, NRC Regional Administrator, Region IV C. F. Lyon, NRC Senior Project Manager S.M. Schneider, NRC Senior Resident Inspector NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION (02-2014) LICENSEE EVENT REPORT (LER) (See Page 2 for required number of digits/characters for each block) APPROVED BY OMB: NO. 3160-0104 EXPIRES: 01131/2017 Estimated burden per response to comply with this mandatory collection request 80 hours. Reported lessons learned are incorporated into the licensing process and led back to industry. Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by interne' e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (31500104), Office of Management and Budget, Washington. DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the Information collection. 1. FACILITY NAME Fort Calhoun Station ,2. DOCKET NUMBER 05000285 3. PAGE 1 OF 3 Plant Trip Due to Moisture Intrusion into a Transformer Control Cabinet | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
|