RS-06-058, Operational Plan Commitments
Letter Sequence Request | |
---|---|
TAC:MC0875, (Open) | |
Administration
| |
MONTHYEARRS-05-061, Response to Request for Additional Information for Review of Quad Cities Replacement Steam Dryer2005-05-12012 May 2005
[Table View]Response to Request for Additional Information for Review of Quad Cities Replacement Steam Dryer Project stage: Response to RAI ML0518100572005-07-14014 July 2005 Withholding from Public Disclosure, Updated Responses to DNPS and QCNPS EPU RAIs 3B & 7, August 14, 2003 (GE Proprietary Information) Project stage: RAI ML0518200102005-07-18018 July 2005 Continuum Dynamics, Inc., Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0528704802005-12-0707 December 2005 Report of Project Manager Site Visit- Dresden Steam Dryer Licensing Issues Project stage: Other RS-06-015, Commitments and Plans Related to Extended Power Uprate Operation2006-01-26026 January 2006 Commitments and Plans Related to Extended Power Uprate Operation Project stage: Request ML0604507082006-03-0808 March 2006 General Electric Company, Request for Withholding Information from Public Disclosure for Dresden, Units 2 and 3 and Quad Cities, Units 1 and 2 Project stage: Withholding Request Acceptance ML0604002722006-03-16016 March 2006 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0610805702006-04-10010 April 2006 Quad Cities Unit 2 Dryer Inspection Results Project stage: Request ML0610806102006-04-13013 April 2006 Request for Additional Information - Dryer Inspection, Start-up and Power Ascension Plan Project stage: RAI RS-06-058, Operational Plan Commitments2006-04-14014 April 2006 Operational Plan Commitments Project stage: Request ML0610406142006-04-20020 April 2006 Dryer Inspection Results Decision Project stage: Other ML0610102872006-04-28028 April 2006 General Electric Company, Request for Withholding Information from Public Disclosure for Dreden Nuclear Power Station, Units 1 and 2 (TAC Nos. MC0875, MC0876, MC0877 and MC0878 Project stage: Withholding Request Acceptance ML0609603942006-04-28028 April 2006 GE Request for Withholding Information from Public Disclosure Dresden and Quad by Letter Dated May 13, 2005 Project stage: Withholding Request Acceptance ML0610200462006-04-28028 April 2006 General Electric Company, Request for Withholding Information from Public Disclosure for Dresden Nuclear Power Station, Units 2 and 3, and Quad Cities Nuclear Power Station, Units 1 and 2 Project stage: Withholding Request Acceptance ML0611604452006-04-28028 April 2006 RAI Related to Unit 2 Steam Dryer Inspection Project stage: RAI ML0609603632006-05-0101 May 2006 General Electric, Withholding from Public Disclosure, GE-NE-0000-0032-1827P, Quad Cities Replacement Steam Dryer Instrumentation Acceptance Criteria, Dated April 2005 Project stage: Other ML0608905262006-05-0101 May 2006 GE Request for Withholding Information from Public Disclosure for Dresden, Units 2 and 3 and Quad, Units 1 and 2 Project stage: Withholding Request Acceptance ML0610202772006-05-19019 May 2006 General Electric Company, Request for Withholding Information from Public Disclosure for Dresden Nuclear Power Station, Unit 2 and 3, and Quad Cities Nuclear Power Station, Units 1 and 2 Project stage: Withholding Request Acceptance ML0608201332006-07-0505 July 2006 Quad Cities, Units 1 and 2 - GE, Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0614401352006-07-0505 July 2006 General Electric Company, Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0614406092006-07-0505 July 2006 Quad Cities, Units 1 and 2 - GE, Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0614402522006-07-25025 July 2006 GE Company, Request for Withholding Information from Public Disclosure for Dresden and Quad Cities - Quintana Ltr Project stage: Withholding Request Acceptance ML0615301212006-08-17017 August 2006 Continuum Dynamics, Inc. Request for Withholding Information from Public Disclosure, Bilanin Letter Project stage: Withholding Request Acceptance ML0507701992006-09-0505 September 2006 Withholding from Public Disclosure, C.D.I. Proprietary Report No. 04-09P, Rev. 5 and Presentation Entitled, Methodology to Determine Unsteady Pressure Loading on Components in Reactor Steam Domes, Dated January 25, 2005 Project stage: Other ML0615001032006-09-0505 September 2006 GE, Withholding from Public Disclosure, GENE-0000-0038-6481-01-R1-P, Exelon Steam Dryer Dynamic Time History Analyses: Dresden Unit 2 2004 Repair & Dresden Unit 3 2003 & 2004 Repair Dryer Configurations Using Loads from Plant Measurements, Project stage: Other ML0610103752006-09-21021 September 2006 General Electric Company, Request for Withholding Information from Public Disclosure for Dresden Nuclear Power Station, Units 2 and 3, and Quad Cities Nuclear Power Station, Units 1 and 2 Project stage: Withholding Request Acceptance 2006-04-14 |
ML061070354 | |
Person / Time | |
---|---|
Site: | Quad Cities |
Issue date: | 04/14/2006 |
From: | Jury K Exelon Nuclear |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
RS-06-058 | |
Download: ML061070354 (2) | |
Similar Documents at Quad Cities | |
---|---|
Category:Letter type:RS
MONTHYEARRS-24-078, Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval2024-08-20020 August 2024
[Table view]Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations RS-24-053, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed2024-06-0606 June 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-042, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-05-10010 May 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-046, 10 CFR 50.46 Annual Report2024-05-0606 May 2024 10 CFR 50.46 Annual Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-032, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-04-0505 April 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-019, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF2024-03-19019 March 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF RS-24-020, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS2024-03-15015 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS RS-24-015, Submittal of RP-01 Relief Request Associated with the Sixth Inservice Testing Interval2024-02-29029 February 2024 Submittal of RP-01 Relief Request Associated with the Sixth Inservice Testing Interval RS-24-001, Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2024-01-0303 January 2024 Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-128, Response to Request for Additional Information for the Emergency License Amendment Request – Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-15015 December 2023 Response to Request for Additional Information for the Emergency License Amendment Request – Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-13013 December 2023 Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-104, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-113, Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 262023-10-20020 October 2023 Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 26 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-089, Sixth Ten-Year Interval Inservice Testing Program2023-09-0505 September 2023 Sixth Ten-Year Interval Inservice Testing Program RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-086, Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-08-28028 August 2023 Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-060, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2023-06-0808 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors RS-23-059, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0808 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling RS-22-067, 10 CFR 50.46 Annual Report2023-05-0404 May 2023 10 CFR 50.46 Annual Report RS-23-068, Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell2023-04-28028 April 2023 Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell RS-23-058, Submittal of Sixth Inservice Inspection Interval Relief Request I6R-11 Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell Flanges2023-04-24024 April 2023 Submittal of Sixth Inservice Inspection Interval Relief Request I6R-11 Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell Flanges RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-007, Application to Adopt TSTF-564, Safety Limit MCPR2023-03-0303 March 2023 Application to Adopt TSTF-564, Safety Limit MCPR RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-032, Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location2023-02-0303 February 2023 Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location RS-23-034, Notification of Extension to the Fifth Ten-Year Interval of the Inservice Testing Program2023-02-0202 February 2023 Notification of Extension to the Fifth Ten-Year Interval of the Inservice Testing Program RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-23-033, Request for Exemption from 10 CFR 2.109(b)2023-01-27027 January 2023 Request for Exemption from 10 CFR 2.109(b) RS-23-005, Response to Request for Additional Information for Quad Cities Relief Request RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves2023-01-17017 January 2023 Response to Request for Additional Information for Quad Cities Relief Request RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves RS-22-127, Submittal of Sixth Inservice Inspection Interval Relief Request I6R-10 Reactor Pressure Vessel Penetration N-11B Repair2022-12-14014 December 2022 Submittal of Sixth Inservice Inspection Interval Relief Request I6R-10 Reactor Pressure Vessel Penetration N-11B Repair RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-119, Withdrawal of Relief Request RV-11 Associated with the Sixth Inservice Testing Interval2022-10-31031 October 2022 Withdrawal of Relief Request RV-11 Associated with the Sixth Inservice Testing Interval RS-22-109, Response to Request for Additional Information License Amendments Related to Fuel Storage2022-10-12012 October 2022 Response to Request for Additional Information License Amendments Related to Fuel Storage RS-22-112, Submittal of RV-04 Relief Request Associated with the Sixth Inservice Testing Interval2022-10-0707 October 2022 Submittal of RV-04 Relief Request Associated with the Sixth Inservice Testing Interval RS-22-108, Response to Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage2022-10-0505 October 2022 Response to Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-102, Supplement to Request to Revise Technical Specification 3.1.4, Control Rod Scam Times2022-08-18018 August 2022 Supplement to Request to Revise Technical Specification 3.1.4, Control Rod Scam Times RS-22-095, Response to Request for Additional Information Regarding Request to Expand Applicability of GNF Thermal Mechanical Analysis Methods to Framatome Fuel2022-08-10010 August 2022 Response to Request for Additional Information Regarding Request to Expand Applicability of GNF Thermal Mechanical Analysis Methods to Framatome Fuel RS-22-096, Response to Request for Additional Information Related to Relief Request I6R-01 Associated with the Sixth Inservice Inspection Interval2022-08-10010 August 2022 Response to Request for Additional Information Related to Relief Request I6R-01 Associated with the Sixth Inservice Inspection Interval RS-22-098, Response to Request for Additional Information for Quad Cities Relief Request RV-11, Code Case OMN-282022-08-0101 August 2022 Response to Request for Additional Information for Quad Cities Relief Request RV-11, Code Case OMN-28 RS-22-094, Submittal of Sixth Inservice Inspection Interval Relief Request I6R-09 to Permit Continued Application of Certain ASME Section XI 2013 Edition Non-Destructive Examination Requirements2022-07-25025 July 2022 Submittal of Sixth Inservice Inspection Interval Relief Request I6R-09 to Permit Continued Application of Certain ASME Section XI 2013 Edition Non-Destructive Examination Requirements 2024-08-20 |
Text
RS-06-058 April 14, 2006 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265
Subject:
Quad Cities Nuclear Power Station Operational Plan Commitments
Reference:
Letter from Keith R. Jury (Exelon Generation Company, LLC) to U. S. NRC, "Commitments and Plans Related to Extended Power Uprate Operation," dated January 26, 2006 This letter documents discussions between members of Exelon Generation Company, LLC (EGC) and the NRC on April 12, 2006, related to the near-term operational plans for Quad Cities Nuclear Power Station (QCNPS), Units 1 and 2. Following completion of the spring 2006 QCNPS Unit 2 refueling outage, QCNPS Unit 2 will be returned to service and implement the start-up test program described during the March 16, 2006, meeting between EGC and the NRC. The start-up test program includes collecting data during operation at extended power uprate (EPU) power levels. Once the EPU power level data collection effort is complete, QCNPS Unit 2 will reduce power to a pre-EPU level. QCNPS Unit 2 will remain at a pre-EPU power level until the QCNPS Unit 1 steam dryer is inspected during the planned May 2006 QCNPS Unit 1 outage. The QCNPS Unit 1 steam dryer inspection scope will consist of, as a minimum, those areas necessary to confirm conclusions reached regarding the cause of the QCNPS Unit 2 steam dryer damage described in our April 10, 2006 conference call. EGC intends to continue the dialog and interactions with the NRC as described during our March 16, 2006, meeting and in the referenced letter regarding resolution of the concerns related to QCNPS EPU long-term operation. In the referenced letter, EGC updated regulatory commitments regarding operation of Dresden Nuclear Power Station (DNPS), Units 2 and 3, and Quad Cities Nuclear Power Station April 14, 2006 U. S. Nuclear Regulatory Commission Page 2 (QCNPS), Units 1 and 2, at extended power uprate (EPU) conditions. Those commitments remain in effect and are not altered by this letter. If you have any questions concerning this submittal, please contact Mr. Patrick R. Simpson at (630) 657-2823. Respectfully, Keith R. Jury Director - Licensing and Regulatory Affairs cc: Regional Administrator - NRC Region III NRC Senior Resident Inspector - Quad Cities Nuclear Power Station