|
---|
Category:Letter
MONTHYEARIR 05000335/20230102024-01-26026 January 2024 NRC Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000335/2023010 and 05000389/2023010 L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) IR 05000335/20230042024-01-24024 January 2024 Integrated Inspection Report 05000335/2023004 and 05000389/2023004 L-2024-004, Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years2024-01-18018 January 2024 Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years L-2024-002, Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2024-01-0808 January 2024 Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-179, Unusual or Important Environmental Event - Turtle Mortality2023-12-14014 December 2023 Unusual or Important Environmental Event - Turtle Mortality L-2023-168, License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 52023-12-12012 December 2023 License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 5 L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, ML23332A1772023-11-28028 November 2023 Correction to the 2022 Annual Radioactive Effluent Release Report L-2023-162, Response to 50.69 2nd Round of Rals2023-11-21021 November 2023 Response to 50.69 2nd Round of Rals IR 05000335/20230032023-11-0606 November 2023 Integrated Inspection Report 05000335/2023003 and 05000389/2023003 ML23270B8882023-10-23023 October 2023 Regulatory Audit Summary Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structure, Systems, and Components for Nuclear Power Reactors EPID L-2022-LLA-0182 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23275A1102023-10-0202 October 2023 License Amendment Request Revision 2 for the Technical Specifications Conversion to NUREG-1432, Revision 5 L-2023-131, Subsequent License Renewal Application - Second Annual Update2023-09-28028 September 2023 Subsequent License Renewal Application - Second Annual Update L-2023-136, Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-26026 September 2023 Supplement to License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2023-122, Corrections to the 2022 Annual Radiological Environmental Operating Report2023-09-20020 September 2023 Corrections to the 2022 Annual Radiological Environmental Operating Report IR 05000335/20233012023-09-20020 September 2023 NRC Operator License Examination Report 05000335/2023301 and 05000389/2023301 L-2023-127, Correction to the 2022 Annual Radioactive Effluent Release Report2023-09-18018 September 2023 Correction to the 2022 Annual Radioactive Effluent Release Report L-2023-113, Correction to the 2020 Annual Radiological Environmental Operating Report2023-09-14014 September 2023 Correction to the 2020 Annual Radiological Environmental Operating Report L-2023-108, Report of 10 CFR 50.59 Plant Changes2023-09-11011 September 2023 Report of 10 CFR 50.59 Plant Changes L-2023-118, Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-11011 September 2023 Response to Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors L-2023-112, Corrections to the 2021 Annual Radioactive Effluent Release Report2023-09-0606 September 2023 Corrections to the 2021 Annual Radioactive Effluent Release Report L-2023-107, Technical Specification Bases Control Program Periodic Report of Bases Changes TS 6.8.4.j.42023-09-0606 September 2023 Technical Specification Bases Control Program Periodic Report of Bases Changes TS 6.8.4.j.4 ML23219A0042023-09-0101 September 2023 Transmittal Letter - Safety Evaluation Related to the SLRA of St. Lucie Plant, Units 1and 2, Revision 1 L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 IR 05000335/20230022023-08-0707 August 2023 Integrated Inspection Report 05000335/2023002 and 05000389/2023002 L-2023-105, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment ML23212B2652023-07-27027 July 2023 Operator Licensing Written Examination Approval 05000335/2023301 and 05000389/2023301 L-2023-099, Pump Relief Request 10 (PR-10), One-Time Request for an Alternative to the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2023-07-26026 July 2023 Pump Relief Request 10 (PR-10), One-Time Request for an Alternative to the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-102, Relief Request PSL2-15-RR-01, Proposed Alternative to ASME Section XI Code Examination Requirements for Reactor Vessel Bottom Area and Piping in Covered Trenches2023-07-26026 July 2023 Relief Request PSL2-15-RR-01, Proposed Alternative to ASME Section XI Code Examination Requirements for Reactor Vessel Bottom Area and Piping in Covered Trenches ML23200A1232023-07-21021 July 2023 Transmittal Letter for the St. Lucie SLRA Review L-2023-097, Subsequent License Renewal Application Revision 1 - Supplement 62023-07-13013 July 2023 Subsequent License Renewal Application Revision 1 - Supplement 6 L-2023-076, In-Service Inspection Program Owner'S Activity Report (OAR-1)2023-07-11011 July 2023 In-Service Inspection Program Owner'S Activity Report (OAR-1) ML23184A0352023-06-30030 June 2023 Notification of St. Lucie Units 1 & 2 Focused Engineering Inspection (FEI) 05000335/2023010 and 05000389/2023010 and Initial Information Request L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) IR 05000335/20234032023-06-29029 June 2023 Security Inspection Report 05000335/2023403 and 05000389/2023403 IR 05000335/20234022023-06-20020 June 2023 Security Baseline Inspection Report 05000335/2023402 and 05000389/2023402 L-2023-082, Subsequent License Renewal Application Revision 1, Supplement 52023-06-14014 June 2023 Subsequent License Renewal Application Revision 1, Supplement 5 L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal IR 05000335/20234012023-05-16016 May 2023 Cyber Security Inspection Report 05000335/2023401 and 05000389/2023401 (Cover Letter) IR 05000335/20230012023-05-0909 May 2023 Integrated Inspection Report 05000335/2023001 and 05000389/2023001 ML23109A1132023-04-30030 April 2023 SLRA Change Schedule Letter L-2023-059, Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response2023-04-21021 April 2023 Subsequent License Renewal Application - Aging Management Requests for Additional Information (RAI) Set 4 Supplemental Response ML23097A1642023-04-17017 April 2023 Summary of March 23, 2023, Meeting with Florida Power and Light on St. Lucie and Turkey Point Improved Technical Specifications Conversion License Amendment Requests L-2023-055, 2022 Annual Environmental Operating Report2023-04-12012 April 2023 2022 Annual Environmental Operating Report 2024-01-08
[Table view] |
See also: IR 05000335/2012301
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257
December 5, 2012 Florida Power and Light Company
ATTN: Mr. Mike Baughman
Training Manager St. Lucie Nuclear Plant
6501 South Ocean Drive Jensen Beach, FL 34957
SUBJECT: ST. LUCIE - OPERATOR LICENSING WRITTEN EXAMINATION APPROVAL 05000335/2012301 AND 05000389/2012301
Dear Mr. Baughman:
The purpose of this letter is to confirm the final arrangements for the upcoming operator
licensing written examination at St. Lucie Nuclear Plant.
The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to Mr. Terry Benton, Training Supervisor. The NRC staff is in the
process of administering the operating tests to these individuals, as applicable, from
December 3-14, 2012. Note that any examination waivers and application denials have been addressed in separate correspondence.
The NRC has approved the subject written examination and hereby authorizes you to
administer the written examination in accordance
with Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," the week of
December 17, 2012.
This examination has undergone extensive review by my staff and representatives responsible for operator training at your facility. Based on this review I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By
administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the qualifications of licensed operators at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at (404) 997-4550.
Please contact your Chief Examiner, Mr. P
hillip Capehart, at (404) 997-4483 if you have any questions or identify any errors or changes in license level (RO or SRO) specified for each applicant on the list of approved applicants.
Sincerely,
/RA/
Malcolm T. Widmann, Chief
Operations Branch 1
Division of Reactor Safety Docket Nos.: 50-335, 50-389
License Nos.: DPR-67, NPF-16
December 5, 2012 Florida Power and Light Company
ATTN: Mr. Mike Baughman
Training Manager St. Lucie Nuclear Plant
6501 South Ocean Drive
Jensen Beach, FL 34957
SUBJECT: ST. LUCIE - OPERATOR LICENSING WRITTEN EXAMINATION APPROVAL 05000335/2012301 AND 05000389/2012301
Dear Mr. Baughman:
The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing written examination at St. Lucie Nuclear Plant.
The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator
license applications submitted in connection with this examination and separately provided a list of approved applicants to Mr. Terry Benton, Training Supervisor. The NRC staff is in the process of administering the operating tests to these individuals, as applicable, from December 3-14, 2012. Note that any examination waivers and application denials have been addressed in separate correspondence.
The NRC has approved the subject written examination and hereby authorizes you to
administer the written examination in accordance
with Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," the week of December 17, 2012.
This examination has undergone extensive review by my staff and representatives responsible for operator training at your facility. Based on this review I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By
administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the qualifications of licensed operators at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at (404) 997-4550.
Please contact your Chief Examiner, Mr. P
hillip Capehart, at (404) 997-4483 if you have any questions or identify any errors or changes in license level (RO or SRO) specified for each
applicant on the list of approved applicants.
Sincerely, /RA/ Malcolm T. Widmann, Chief
Operations Branch 1
Division of Reactor Safety Docket Nos.: 50-335, 50-389
License Nos.: DPR-67, NPF-16 x PUBLICLY AVAILABLE X NON-SENSITIVE ADAMS: Yes ACCESSION NUMBER: ML12341A168 x PGC - SUNSI REVIEW COMPLETE OFFICE RII:DRS RII:DRS SIGNATURE PEC VIA EMAIL MTW NAME PCAPEHART MWIDMANN DATE 12/4/2012 12/5/2012 12/ /2012 12/ /2012 12/ /2012 12/ /2012 12/ /2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO