Vermont Yankee - Independent Spent Fuel Storage Installation Security Inspection Report 07200059/2018401 (Cover Letter Only - Public)
ML18324A882
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 11/20/2018
From: Raymond McKinley
Plant Support Branch 1
To: Daniels C
Entergy Nuclear Operations, Entergy Nuclear Vermont Yankee
McKinley R R
References
IR 2018401
Download: ML18324A882 (4)


Text

November 20, 2018

Docket No. 07200059License No. DPR-28

Mr. Corey Daniels Director, Nuclear Decommissioning Entergy Nuclear Operations, Inc.

Vermont Yankee Nuclear Power Station 320 Governor Hunt Rd.

Vernon, VT 05354

SUBJECT: VERMONT YANKEE- INDEPENDENT SPENT FUEL STORAGE INSTALLATION SECURITY INSPECTION REPORT 07200059/2018401

Dear Mr. Daniels:

On November 6, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an Independent Spent Fuel Storage Installation (ISFSI) security inspection at the Vermont Yankee, Independent Spent Fuel Storage Installation in Brattleboro, VT. The inspection covered the October 16, 2002, Interim Compensatory Measures for Dry Independent Spent Fuel Storage Installations Order and was conducted using NRC Inspection Procedure 81311, "Physical Security Requirements for Independent Spent Fuel Storage Installations."

The enclosed inspection report documents the inspection results, which were discussed with

you, on November 6, 2018.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection, no violations were identified.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Enclosure Contains Sensitive Unclassified Non-Safeguards Information. When separated from Enclosure, this transmittal document is decontrolled. However, the material enclosed herewith contains Security Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security Related Information is necessary to provide an acceptable response, please mark your entire response "Security Related Information - Withhold From Public Disclosure Under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.

Sincerely,/RA/ Raymond R. McKinley, Chief

Plant Support Branch Division of Reactor Safety

Enclosure:

Inspection Report No. 07200059/2018401 (CONTAINS ) (OUO-SRI)

cc w/encl; w/OUO-SRI RPT: P. Ryan, Security Manager, Vermont Yankee

cc w/o encl; w/o OUO-SRI RPT: Distribution via ListServ

ML18324A882 (Cover letter) ADAMS ACCESSION NUMBER: ML18324A876 (Cover letter w/enclosure) (OUO/SRI) Cover Letter Only X SUNSI Review X Non-Sensitive Sensitive X Publicly Available Non-Publicly Available Cover Letter w/Enclosure X SUNSI Review Non-Sensitive X Sensitive Publicly Available X Non-Publicly Available OFFICE RI/DRS RI/DNMS RI/DRS NAME DCaron RPowell RMcKinley DATE 11/14/2018 11/14/2018 11/20/2018 Letter to Mr. Corey Daniels from Mr. Raymond R. McKinley, dated November 20, 2018

SUBJECT: Vermont Yankee - Independent Spent Fuel Storage Installation Security Inspection Report 07200059/2018401

Distribution w/o encl; w/o OUO-SRI RPT: (via E-mail) D. Lew, RA (R1ORAMAIL RESOURCE)

R. Lorson, DRA (R1ORAMAIL RESOURCE)

J. Yerokun, DRS (R1DRSMAIL RESOURCE)

J. Trapp, DNMS (R1DNMSMAIL RESOURCE)

J. Nick, DNMS (R1DNMSMAIL RESOURCE)

D. Screnci, PAO N. Sheehan, PAO D. Tifft, SLO

Distribution w/encl; w/OUO-SRI RPT: D. Caron, DRS R. McKinley, DRS R. Powell, DNMS D. Huyck, NSIR N. Simonian, NSIR

E. Wharton, NSIR B. Desai, DRS, RII S. Orth, DRS, RIII

J. Groom, DRS, RIV