Peach Bottom Unit 2, Technical Specification Pages Re Main Steam Isolation Valve Leakage
ML072600189
Person / Time
Site: Peach Bottom Constellation icon.png
Issue date: 09/14/2007
From:
NRC/NRR/ADRO/DORL/LPLI-2
To:
Hughey J D, NRR/DORL, 301-415-3204
Shared Package
ml072470712 List:
References
TAC MD4823, TAC MD4824
Download: ML072600189 (2)


Text

(5) Exelon Generation Company, pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not to separate, such byproduct and special nuclear material as may be produced by operation of the facility.C. This renewed license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Chapter I: Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Section 50.54 of Part 50, and Section 70.32 of Part 70; all applicable provisions of the Act and the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified below: (1) Maximum Power Level Exelon Generation Company is authorized to operate the Peach Bottom Atomic Power Station, Unit 2, at steady state reactor core power levels not in excess of 3514 megawatts thermal.(2) Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No.263 are hereby incorporated in the license. Exelon Generation Company shall operate the facility in accordance with the Technical Specifications.

(3) Physical Protection Exelon Generation Company shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans, including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and the authority of 10 CFR 50.90 and 10 CFR 50.54(p).

The combined set of plans 1 , submitted by letter dated May 17, 2006, is entitled: "Peach Bottom Atomic Power Station Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program, Revision 3." The set contains Safeguards Information protected under 10 CFR 73.21.(4) Fire Protection The Exelon Generation Company shall implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report for the facility, and as approved in the NRC Safety Evaluation Report (SER) dated May 23, 1979, and Supplements dated August 14, September 15, October 10 and November 24, 1980, and in the NRC SERs dated September 16, 1993, and August 24, 1994, subject to the following provision:

The Exelon Generation Company may make changes to the approved 1 The Training and Qualification Plan and Safeguards Contingency Plan are Appendices to the Security Plan.Renewed Lcense N,. DEPR-44 Revised by letter dated--ctober 28, 2004 Rlevised by letter dated May 29, 2007-Amendment No.2-6 3 Page 3 PCIVs 3.6.1.3 SURVEILLANCE REQUIREMENTS (continued)

SURVEILLANCE FREQUENCY SR 3.6.1.3.14 Verify combined main steam line leakage In accordance rate is ! 46 scfh when tested at with the 25 psig. Primary Containment Leakage Rate Testing Program SR 3.6.1.3.15 Verify each 6 inch and 18 inch primary 24 months containment purge valve and each 18 inch primary containment exhaust valve is blocked to restrict opening greater than the required maximum opening angle.SR 3.6.1.3.16 Replace the inflatable seal of each 96 months 6 inch and 18 inch primary containment purge valve and each 18 inch primary containment exhaust valve.PBAIPS U'iT- -J.0-10 A J n e -Amendment No. 263