05000445/LER-2016-001 | 22 August 2016 | Safety Chiller Inoperable For Longer Than Allowed By Technical Specifications LER 16-001-00 for Comanche Peak Nuclear Power Plant, Unit 1, Regarding Safety Chiller Inoperable For Longer Than Allowed By Technical Specifications | Fitness for Duty Probabilistic Risk Assessment Large early release frequency |
05000445/LER-2016-002 | 22 February 2017 | Unanalyzed Condition Involving Potential Moderate Energy Line Break LER 16-002-01 for Comanche Peak Nuclear Power Plant, Units 1 & 2 Regarding Unanalyzed Condition Involving Potential Moderate Energy Line Break | Unanalyzed Condition Boric Acid Time of Discovery |
05000446/LER-2017-001 | 5 October 2017 | Auxiliary Feedwater System Actuation During Unit 2 Turbine Trip LER 17-001-00 for Comanche Peak Nuclear Power Plant Regarding Auxiliary Feedwater System Actuation During Unit 2 Turbine Trip | |
05000446/LER-2017-003 | 22 January 2018 | Manual Reactor Trip due to trip of both Main Feedwater Pumps LER 17-003-00 for Comanche Peak, Unit 2, Regarding Manual Reactor Trip Due to Trip of Both Main Feedwater Pumps | |
BYRON 2005-0016, January 2005 Monthly Operating Report for Byron Station Units 1 and 2 | 15 February 2005 | January 2005 Monthly Operating Report for Byron Station Units 1 and 2 | Offsite Dose Calculation Manual |
CP-200130010, Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 1, Integrated Assessment Approach | 24 January 2013 | Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 1, Integrated Assessment Approach | Fukushima Dai-Ichi |
CP-200700016, Supplemental Information to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage. | 24 October 2007 | Supplemental Information to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage. | |
CP-200700022, License Amendment Request (LAR) 2007-008 to Technical Specification 3.6.7, Spray Additive System | 29 November 2007 | License Amendment Request (LAR) 2007-008 to Technical Specification 3.6.7, Spray Additive System | Boric Acid |
CP-200700024, Supplement to License Amendment Request (LAR) 07-003 Response to Request for Additional Information Related to Review Associated with Large and Small Break LOCA Analyses | 15 November 2007 | Supplement to License Amendment Request (LAR) 07-003 Response to Request for Additional Information Related to Review Associated with Large and Small Break LOCA Analyses | Boric Acid Loop seal |
CP-200700046, Submittal of Information Required by Order Approving the Indirect Transfer of Facility Operating Licenses and Conforming License Amendments | 5 November 2007 | Submittal of Information Required by Order Approving the Indirect Transfer of Facility Operating Licenses and Conforming License Amendments | |
CP-200700075, Clarification of Proprietary Nature of Information Regarding Gothic Code Input Data | 7 November 2007 | Clarification of Proprietary Nature of Information Regarding Gothic Code Input Data | GOTHIC |
CP-200700085, Supporting Information Regarding the Proprietary Nature of Gothic Code Input Data | 3 December 2007 | Supporting Information Regarding the Proprietary Nature of Gothic Code Input Data | |
CP-200700090, Supplement to Response to NRC Generic Letter (GL) 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors | 3 December 2007 | Supplement to Response to NRC Generic Letter (GL) 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors | |
CP-200700132, Supplement to License Amendment Request (LAR) 07-003 - Response to Request for Additional Information Related to Review Associated with Large and Small Break LOCA Analyses | 19 November 2007 | Supplement to License Amendment Request (LAR) 07-003 - Response to Request for Additional Information Related to Review Associated with Large and Small Break LOCA Analyses | Boric Acid Loop seal |
CP-200700169, Supplement to License Amendment Request (LAR) 06-012, Response to Request for Additional Information Related to Administrative Controls | 30 November 2007 | Supplement to License Amendment Request (LAR) 06-012, Response to Request for Additional Information Related to Administrative Controls | |
CP-200800053, Submittal of Annual Report of Changes in Peak Cladding Temperature for Comanche Peak Steam Electric Station (CPNPP) Units 1 and 2 | 10 January 2008 | Submittal of Annual Report of Changes in Peak Cladding Temperature for Comanche Peak Steam Electric Station (CPNPP) Units 1 and 2 | |
CP-200800057, Supplement to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | 10 January 2008 | Supplement to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | Safe Shutdown Shutdown Margin Fire Barrier Anticipated operational occurrence Aging Management Time Critical Operator Action Fuel cladding Fire Protection Program |
CP-200800123, Supplement to License Amendment Request (LAR) 07-003 Response to Request for Additional Information Related to LAR Associated with Methodology Used to Establish Core Operating Limits and LAR 07-004 Revision to Operating License. | 29 January 2008 | Supplement to License Amendment Request (LAR) 07-003 Response to Request for Additional Information Related to LAR Associated with Methodology Used to Establish Core Operating Limits and LAR 07-004 Revision to Operating License. | |
CP-200800124, Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | 31 January 2008 | Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | Ultimate heat sink Coatings |
CP-200800125, Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | 28 February 2008 | Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | Loop seal Anticipated operational occurrence |
CP-200800183, Withdrawal of License Amendment Request (LAR) 06-009, Revision to Technical Specification 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators | 30 January 2008 | Withdrawal of License Amendment Request (LAR) 06-009, Revision to Technical Specification 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators | |
CP-200800212, Response to Request for Additional Information Related to License Amendment Request 07-003 Revision to Technical Specifications 3.1, Reactivity Control Systems, 3.2, Power Distribution Limits, 3.3, Instrumentations, and 5.6.5b. | 11 February 2008 | Response to Request for Additional Information Related to License Amendment Request 07-003 Revision to Technical Specifications 3.1, Reactivity Control Systems, 3.2, Power Distribution Limits, 3.3, Instrumentations, and 5.6.5b. | |
CP-200800213, Response to Request for Additional Information | 26 February 2008 | Response to Request for Additional Information | Flow Induced Vibration |
CP-200800214, Guarantees of Payment of Deferred Premiums | 7 February 2008 | Guarantees of Payment of Deferred Premiums | |
CP-200800244, Transmittal of Annual Operating Report for 2007 | 28 February 2008 | Transmittal of Annual Operating Report for 2007 | Weld Overlay Power change |
CP-200800263, Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | 21 February 2008 | Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | Unanalyzed Condition Operator Manual Action Flow Induced Vibration Coast down |
CP-200800264, Supplement to License Amendment Request (LAR) 07-003: Response to Request for Additional Information Related to License Amendment Request Associated with Methodology Used to Establish Core Operating Limits | 6 March 2008 | Supplement to License Amendment Request (LAR) 07-003: Response to Request for Additional Information Related to License Amendment Request Associated with Methodology Used to Establish Core Operating Limits | |
CP-200800265, Transmittal of Supplemental Response to NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors | 29 February 2008 | Transmittal of Supplemental Response to NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors | Safe Shutdown Earthquake Hydrostatic Coatings Operating Basis Earthquake Scaffolding |
CP-200800276, Commanche Peak, Transmittal of Second-Half 2007 Fitness-for-Duty Program Performance Data | 27 February 2008 | Commanche Peak, Transmittal of Second-Half 2007 Fitness-for-Duty Program Performance Data | Fitness for Duty |
CP-200800348, Transmittal of Inservice Inspection Program Plan, Revision 3, (ASME Code Section XI 1998 Edition, 1999 and 2000 Addenda, Interval Start Date August 3, 2004, Second Interval) | 6 March 2008 | Transmittal of Inservice Inspection Program Plan, Revision 3, (ASME Code Section XI 1998 Edition, 1999 and 2000 Addenda, Interval Start Date August 3, 2004, Second Interval) | High Radiation Area Weld Overlay Hydrostatic Nondestructive Examination VT-2 Liquid penetrant Dissimilar Metal Weld |
CP-200800357, Supplement to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | 6 March 2008 | Supplement to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | Finite Element Analysis |
CP-200800403, Property Damage Insurance as of April 1, 2008 | 27 March 2008 | Property Damage Insurance as of April 1, 2008 | |
CP-200800410, Reply to a Notice of Violation; EA-08-028 | 27 March 2008 | Reply to a Notice of Violation; EA-08-028 | Significance Determination Process |
CP-200800411, Supplement to License Amendment Request (LAR) 07-003 Response to Request for Additional Information Related to Review Associated with Large and Small Break LOCA Analyses | 13 March 2008 | Supplement to License Amendment Request (LAR) 07-003 Response to Request for Additional Information Related to Review Associated with Large and Small Break LOCA Analyses | Shutdown Margin High Radiation Area Post Accident Monitoring Hydrostatic Nondestructive Examination Pressure and Temperature Limits Report |
CP-200800455, Supplement to License Amendment Request (LAR) 07-003, Additional Information Related to License Amendment Request Associated with Methodology Used to Establish Core Operating Limits | 26 March 2008 | Supplement to License Amendment Request (LAR) 07-003, Additional Information Related to License Amendment Request Associated with Methodology Used to Establish Core Operating Limits | |
CP-200800514, Cycle 11, Core Operating Limits Reports | 22 April 2008 | Cycle 11, Core Operating Limits Reports | Shutdown Margin |
CP-200800540, Three Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. | 10 April 2008 | Three Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. | High Radiation Area Scaffolding |
CP-200800560, Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | 17 April 2008 | Supplement to License Amendment Request (LAR) 07-004 Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | Mission time |
CP-200800609, Pressurizer Weld Overlay 60 Day Report and Results of the Final Pdi/Ut Examination of Weld Overlays | 24 April 2008 | Pressurizer Weld Overlay 60 Day Report and Results of the Final Pdi/Ut Examination of Weld Overlays | Weld Overlay DM weld |
CP-200800612, Commanche Peak, Units 1 & 2 - Transmittal of Revised Pressure and Temperature Limits Report | 24 April 2008 | Commanche Peak, Units 1 & 2 - Transmittal of Revised Pressure and Temperature Limits Report | Hydrostatic Pressure and Temperature Limits Report |
CP-200800613, Transmittal of Year 2007 Annual Radiological Environmental Operating Report | 24 April 2008 | Transmittal of Year 2007 Annual Radiological Environmental Operating Report | Grab sample Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report |
CP-200800614, Transmittal of 2007 Radioactive Effluent Release Report & Revision to the Offsite Dose Calculation Manual | 28 April 2008 | Transmittal of 2007 Radioactive Effluent Release Report & Revision to the Offsite Dose Calculation Manual | Offsite Dose Calculation Manual |
CP-200800645, Supplement to License Amendment Request Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | 14 May 2008 | Supplement to License Amendment Request Revision to the Operating License and Technical Specification 1.0, Use and Application to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt | Loop seal Post Accident Monitoring Finite Element Analysis |
CP-200800646, Transmittal of Endorsements to Nuclear Energy Liability Insurance Policy | 12 May 2008 | Transmittal of Endorsements to Nuclear Energy Liability Insurance Policy | |
CP-200800655, Submittal of the Annual Non-Radiological Environmental Operating Report for 2007 | 6 May 2008 | Submittal of the Annual Non-Radiological Environmental Operating Report for 2007 | |
CP-200800762, Submittal of Notice of Change in Trustee for Nuclear Decommissioning Trusts | 29 May 2008 | Submittal of Notice of Change in Trustee for Nuclear Decommissioning Trusts | |
CP-200800769, Response to Request for Additional Information, Relief Request No. B-2 for the Unit 2 Second 10 Year ISI Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences | 29 May 2008 | Response to Request for Additional Information, Relief Request No. B-2 for the Unit 2 Second 10 Year ISI Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences | VT-2 |
CP-200800805, Report of Unusual or Important Environmental Event, Operating License, Appendix B, Environmental Protection Plan (Non Radiological) - Mortality of Avian Species | 4 June 2008 | Report of Unusual or Important Environmental Event, Operating License, Appendix B, Environmental Protection Plan (Non Radiological) - Mortality of Avian Species | |
CP-200800809, Submittal of Core Operating Limits Reports | 9 June 2008 | Submittal of Core Operating Limits Reports | Shutdown Margin |
CP-200800810, Transmittal of Comanche Peak, Units 1 and 2, Supplement to License Amendment Request (LAR) 07-004 Revision to the Technical Specifications for Spent Fuel Pool Criticality | 30 June 2008 | Transmittal of Comanche Peak, Units 1 and 2, Supplement to License Amendment Request (LAR) 07-004 Revision to the Technical Specifications for Spent Fuel Pool Criticality | |