Issue date | Title | Topic | |
---|---|---|---|
ML091810046 | 26 June 2009 | Tennessee Valley Authority - Submittal of Report in Accordance with 10 CFR 26.719 (c)(1) for Drug and Alcohol Testing Errors | |
ML091810062 | 30 June 2009 | Initial Exam 2008-302 Draft RO Written Exam | Safe Shutdown Shutdown Margin Reactor Vessel Water Level Half scram Hydrostatic Squib Foreign Material Exclusion Scram Discharge Volume Feedwater Controller Failure Severe Accident Management Guideline Overtravel Fuel cladding |
ML091810066 | 30 June 2009 | Initial Exam 2008-302 Draft Administrative JPMs | Fitness for Duty High Radiation Area Grab sample Met Tower Job Performance Measure Deep Dose Equivalent Affidavit |
ML091810090 | 30 June 2009 | Initial Exam 2008-302 Draft Sim/In-Plant JPMs | Squib Job Performance Measure |
ML091810102 | 30 June 2009 | Initial Exam 2008-302 Draft Administrative Documents | |
ML091810120 | 30 June 2009 | Initial Exam 2008-302 Draft SRO Written Exam | Safe Shutdown Unanalyzed Condition Time of Discovery Shutdown Margin Reactor Vessel Water Level Half scram Fire Barrier Operator Manual Action Squib Abnormal operational transient Scram Discharge Volume Severe Accident Management Guideline Earthquake Fuel cladding Offsite Circuit Fire Watch Grace period Coast down |
ML091810122 | 30 June 2009 | Initial Exam 2008-302 Draft Simulator Scenarios | Half scram Stroke time Severe Accident Management Guideline Power change |
ML091810124 | 30 June 2009 | Initial Exam 2008-302 Final Simulator Scenarios | Half scram Stroke time Squib Scram Discharge Volume Overtravel Power change |
ML091810128 | 30 June 2009 | Initial Exam 2008-302 Final Administrative JPMs | Fitness for Duty Grab sample Met Tower Job Performance Measure |
ML091810132 | 30 June 2009 | Initial Exam 2008-302 Final SIM/In-Plant JPMs | Safe Shutdown Squib Job Performance Measure |
ML092020223 | 30 April 2009 | CDI Report No. 08-05NP, Rev. 4, Acoustic and Low Frequency Hydrodynamic Loads at CLTP Power Level on Browns Ferry Nuclear Unit 2 Steam Dryer to 250 Hz, Enclosure 5 | |
ML092020224 | 31 May 2009 | CDI Technical Note No. 08-13NP, Rev. 1, Limit Curve Analysis with ACM Rev. 4 for Power Ascension at Browns Ferry Nuclear Unit 2, Enclosure 6 | Finite Element Analysis |
ML092020229 | 30 June 2009 | CDI Report No. 09-13NP, Rev. 0, Stress Assessment of Browns Ferry Nuclear Unit 2 Steam Dryer with Steam Dam, Outer Hood and Tie-Bar Reinforcements, Introduction Through Page 62, Enclosure 4 | Finite Element Analysis Liquid penetrant |
ML092020231 | 30 June 2009 | CDI Report No. 09-13NP, Rev. 0, Stress Assessment of Browns Ferry Nuclear Unit 2 Steam Dryer with Steam Dam, Outer Hood and Tie-Bar Reinforcements, Page 63 Through 128, Enclosure 4 | |
ML093080160 | 30 June 2009 | Attachment 9, Browns Ferry Unit 1 - Technical Specification Change 467, ANP-2807(NP), Revision 0, Thermal Hydraulic Design Report for ATRIUM-10 Fuel Assemblies | Anticipated operational occurrence |
ML093350658 | 30 June 2009 | ANP-2821(NP), Rev. 0, Browns Ferry Unit 1 Thermal-Hydraulic Design Report for ATRIUM-10 Fuel Assemblies (105% Oltp). | Anticipated operational occurrence |
ML101160154 | 30 June 2009 | ANP-2821(NP), Revision 0, Browns Ferry Unit 1 Thermal-Hydraulic Design Report for ATRIUM-10 Fuel Assemblies (105% Oltp). | Anticipated operational occurrence |
ML110691285 | 22 May 2009 | E-mail from D. Frumkin, NRR to B. Metzger, NRR FW: Support for Manual Action Exemption Reviews | |
ML110831041 | 31 May 2009 | Engineering Evaluation of Hesco Barriers Performance at Fargo, Nd 2009, Wenck File 2283-01, Enclosure 2 | Hydrostatic |
Press Release-II-09-020, NRC to Discuss 2008 Performance of Browns Ferry Nuclear Power Plant | 15 April 2009 | Press Release-II-09-020: NRC to Discuss 2008 Performance of Browns Ferry Nuclear Power Plant | |
TAC:MD9359 | 16 June 2009 | ||
TAC:ME0024 | 29 May 2009 | ||
TAC:ME0889 | 4 June 2009 | ||
TAC:ME1319 | 12 June 2009 | ||
TAC:ME1320 | 21 May 2009 |