IR 05000428/2005002 | 21 April 1975 | Notification of 750428-0502 Meeting W/Util & Westinghouse in San Francisco,Ca to Review Util Seismic Design | |
IR 05000445/1978020 | 9 February 1979 | Corrects Notice of Deviation Re Insp Rept 50-445/78-20,per Util 790209 Response | |
IR 05000454/1983038 | 27 January 1984 | Identifies Addl Insp Repts 50-454/83-38 & 50-455/83-28 Re Reinsp Program,Per 840120 Memo | |
IR 05000482/1983013 | 26 July 1983 | Informs That Allegation 4-83-A-17 Re Improper Use of white-out Unsubstantiated.Forwards Insp Rept 50-482/83-13. Engineering Section Insp to Be Conducted.W/O Encl | |
IR 05000482/1983028 | 26 October 1983 | Informs That Allegation 4-83-A-17 Inspected by R Hall on 830919-22 & Findings Reported in Encl 50-482/83-28.W/o Insp Rept.Related Info Encl | Affidavit |
IR 05000482/1984001 | 22 February 1984 | Informs That Remaining Item on Allegation 4-83-A-25 Completed.W/O Insp Rept 50-482/84-01 | |
IR 05000482/1984051 | 11 December 1984 | Forwards Special Const Verification Insp Rept 50-482/84-51 of Voluntary Const self-assessment on 841023-1102,per 840924 Request,For Transmittal to Applicant.Transmittal Ltr, Potential Enforcement Actions & Unresolved Items Also Encl | |
IR 05000528/1985012 | 25 September 1985 | Forwards 850806 & 0730 Ltrs & Insp Rept 50-528/85-12 Per ACRS 811215 Request for Info Re Startup Experience on Unit 1 Prior to Loading on Unit 2.Unit 2 Fuel Load Scheduled for Nov.Initial Criticality Expected by Jan 1986 | |
IR 05000529/1985044 | 27 November 1985 | Comments on Comparison of as-built Plant W/Facility Tech Specs.Details of Review to Be Reflected in Insp Rept 50-529/85-44 & IE Insp Procedure 71301, Tech Spec Review, Dtd 850322.Proposed Tech Specs Clear & Enforceable | |
ML082320170 | 4 October 1985 | Responds to 850828 Concerns That Procedures in Draft Manual Chapter 0514 Not Followed in Addressing Util 850604 Backfit Claim.Nrr Completed Actions within Stipulated 3-wk Time Frame.Ie Concurrence Delayed NRC Response | Backfit |
ML082380843 | 7 November 1985 | Discusses Util 850531 Response to NRC Request for Addl Info Re Item 2.2.2 of Generic Ltr 83-28 Contending That Request Violated plant-specific Backfit Manual.Appeal Not Planned. Item Closed | Backfit |
ML082890913 | 18 March 1985 | Forwards Monthly Status Rept on plant-specific Backfitting Activities Current Through 850308.Nine of 15 SER Open Items Resolved Prior to Appeal Meetings.Ser Scheduled for Completion on 850329 | |
ML093630131 | 5 March 1971 | Advises That Vol I Needs Further Improvement Re Discrepancies in Phraseology | |
ML18046B289 | 4 February 1982 | Advises That Encl Cover Sheets Should Be Placed in Appropriate Binders of Security Plans,Safeguards Contingency Plans & Suitability,Training & Qualification Plans.Encl Withheld (Ref 10CFR73.21) | |
ML18046B290 | 10 February 1982 | Advises That Encl Cover Sheets Should Be Placed in Appropriate Binders of Security Plans,Safeguards Contingency Plans & Suitability,Training & Qualification Plans.Encl Withheld (Ref 10CFR73.21) | |
ML20054E923 | 10 June 1982 | Board Notification:Notifying of Drywell to Wetwell Vacuum Breakers Which Can Be Subj to air-clearing Load Resulting from Pool Swell Following Postulated Loca.Components Can Be Overstressed by Impact Load | |
ML20054F369 | 14 June 1982 | Releases Public Version of Revised Emergency Plan Implementing Procedures | |
ML20054G582 | 15 June 1982 | Responds to 820512 Memo Re Control of Occupational Doses by Prevention of Transport & Buildup of Radioactive Crud,By Removal of Radionuclide Deposits & Minimization of Failure of Major Plant Components | |
ML20054G587 | 12 May 1982 | Discusses Inadequacy of Responses Re Prevention of Transport & Buildup of Radionuclide Concentrations within Primary Cooling Sys & Methods for Removal of Deposits If Preventive Measures Not Successful | |
ML20054H139 | 17 June 1982 | Releases Public Version of Generating Stations Emergency Plan Telephone Directory | |
ML20054H412 | 18 June 1982 | Releases Public Version of Generating Stations Emergency Plan Telephone Directory | |
ML20054H838 | 23 June 1982 | Advises That NRC Does Not Object to Util 820618 Motion for Extension of Time to Respond to Intervenor 820511 Motion,As Long as NRC Response Will Be Due 5 Days After Applicant Response | |
ML20054J024 | 17 June 1982 | Notification of 820720 Meeting W/B&W Owners Group in Bethesda,Md to Discuss Small Break Model Verification Program | |
ML20054J579 | 24 June 1982 | Discusses Use of Flammable Matl in Class IE Switchgear, Noted During IE Insps.Use of Mounting Bases May Void IEEE-323 & IEEE-383 Qualification Because of Flammable Nature.Licensee Plans to Justify Use | |
ML20054J856 | 23 June 1982 | Releases Public Version of Revised Generating Station Emergency Plan Environ Director Emergency Plan Implementing Procedures | |
ML20054K369 | 26 January 1982 | Advises That on 811208 Util Reported Discovery of Metal Filings in Scram Discharge Vol Piping During Flushing Operations on 811201 | Scram Discharge Volume |
ML20054K958 | 15 June 1982 | Notification of 820622 Meeting W/Bwr Owners Group in Bethesda,Md to Discuss Hydrodynamic Pressure Loads in Control Rod Drive Lines Resulting from Fast Scram,Test Data Base & Proposed Methodology | |
ML20054M214 | 9 November 1981 | Discusses 811105 Telcon W/P Kirby of FBI Concerning Allegation of Falsified QA Records Re Atlas Machine & Iron Works | |
ML20054M330 | 6 July 1982 | Releases Public Version of Revised Emergency Plan Implementing Procedure | |
ML20055A262 | 21 January 1982 | Forwards Responses Denying Licensee Requests for Exemption from 820201 Prompt Notification Sys Deadline.Fr Encl | |
ML20055A263 | 21 January 1981 | Forwards Responses Denying Licensee Requests for Exemption from 820201 Prompt Notification Sys Deadline.Related Info Encl | |
ML20055A269 | 27 January 1982 | Forwards Responses Denying Licensee Requests for Exemption from 820201 Prompt Notification Sys Deadline | |
ML20055A270 | 28 January 1982 | Forwards Response Denying Licensee Request for Exemption from 820201 Prompt Notification Sys Deadline.Related Info Encl | |
ML20055A275 | 10 February 1982 | Forwards Info Re Current Status of Exemption Requests for Alert & Notification Sys | Exemption Request |
ML20055A277 | 12 February 1982 | Forwards Response Denying Licensee Request for Exemption from 820201 Prompt Notification Sys Deadline | Exemption Request |
ML20055C031 | 5 August 1982 | Forwards Region 1 s to Licensees Re Emergency Preparedness | |
ML20055C352 | 26 February 1990 | Notification of 900305 Meeting W/Util in Rockville,Md to Discuss Status of Licensing Activities for Facility | |
ML20056E457 | 5 August 1993 | Forwards Technical Review Rept Re, Tardy Licensee Actions Initiated Because of Delayed Replacement of Batteries in Uninterruptible Power Supplies at Plant | |
ML20056E514 | 12 August 1993 | Submits SALP Schedule for FY94 Per Mgt Directive 8.6 | |
ML20057A994 | 14 September 1993 | Forwards NRC Proposed Transcript Corrections | Fire Watch |
ML20057B211 | 16 September 1993 | Forwards Update to Security Plan,Including Table of Contents,Rev 13 to Pages 18,19,21 & 24 & Chapter 11.Encl Withheld | |
ML20057C572 | 24 September 1993 | Forwards New Page 20,rev 12 of Security Plan Due to Rev 12 Copy Spillover from Page Nineteen Rev 13 Additions.Page Withheld | |
ML20058B378 | 6 July 1982 | Requests That Encl Incident Reporting Sys Repts Be Forwarded to Otsuka of NEA |