Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
NL-03-1386, Startup Test Report24 June 2003Startup Test ReportShutdown Margin
NL-03-1398, Submittal of Updated Fire Hazards Analysis Report (FHA) for Edwin I. Hatch Nuclear Plant, Units 1 & 211 July 2003Submittal of Updated Fire Hazards Analysis Report (FHA) for Edwin I. Hatch Nuclear Plant, Units 1 & 2Safe Shutdown
Fire Barrier
Incorporated by reference
Exemption Request
Continuous fire watch
Fire Protection Program
Hourly Fire Watch
Grace period
NL-03-1401, Response to Request for Additional Information24 June 2003Response to Request for Additional InformationOperating Basis Earthquake
Earthquake
NL-03-1499, Response to Request for Additional Information Regarding Technical Specification Revision Request Integrated Leakage Rate Testing Interval Extension25 July 2003Response to Request for Additional Information Regarding Technical Specification Revision Request Integrated Leakage Rate Testing Interval ExtensionProbabilistic Risk Assessment
Coatings
Moisture barrier
Liquid penetrant
Dissimilar Metal Weld
NL-03-1514, 60 Day Response to NRC Bulletin 2003-01 Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized Water Reactors for Joseph M. Farley Nuclear Plant & Vogtle Electric Generating Plant7 August 200360 Day Response to NRC Bulletin 2003-01 Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized Water Reactors for Joseph M. Farley Nuclear Plant & Vogtle Electric Generating PlantJob Performance Measure
Severe Accident Management Guideline
NL-03-1620, Response to Generic Letter 2003-01, Control Room Habitability4 August 2003Response to Generic Letter 2003-01, Control Room Habitability
NL-03-1654, Cycle 21 Core Operating Limits Report (Colr), Revision 17 August 2003Cycle 21 Core Operating Limits Report (Colr), Revision 1
NL-03-1661, Transmittal of Edwin I. Hatch Revised Emergency Plan Implementing Procedures 73EP-EIP-054-0, Version 6.0 & 73EP-EIP-073-0, Version 15.211 August 2003Transmittal of Edwin I. Hatch Revised Emergency Plan Implementing Procedures 73EP-EIP-054-0, Version 6.0 & 73EP-EIP-073-0, Version 15.2Health Physics Network
Met Tower
NL-03-1687, Response to Request for Additional Information on Oscillating Power Range Monitor Technical Specifications Change Request19 August 2003Response to Request for Additional Information on Oscillating Power Range Monitor Technical Specifications Change Request
NL-03-1744, Third 10-Year Interval Inservice Testing Program Submittal of Revised Relief Request RR-V-18 and Response to Request for Additional Information (RAI)12 September 2003Third 10-Year Interval Inservice Testing Program Submittal of Revised Relief Request RR-V-18 and Response to Request for Additional Information (RAI)Probabilistic Risk Assessment
Large early release frequency
Power Operated Valves
NL-03-1792, Plants - Emergency Operations Facility Relocation Request for Prior Approval16 October 2003Plants - Emergency Operations Facility Relocation Request for Prior ApprovalHealth Physics Network
NL-03-1798, Measurement Uncertainty Recapture Power Uprate (Murpu) Post Murpu Steam Dryer Performance Monitoring and Inspections4 September 2003Measurement Uncertainty Recapture Power Uprate (Murpu) Post Murpu Steam Dryer Performance Monitoring and Inspections
NL-03-1850, August 2003 Monthly Operating Report for Edwin I. Hatch10 September 2003August 2003 Monthly Operating Report for Edwin I. Hatch
NL-03-1858, Cycle 12 and Unit 2 Cycle 10 Core Operating Limits Reports2 October 2003Cycle 12 and Unit 2 Cycle 10 Core Operating Limits ReportsShutdown Margin
NL-03-1926, Withdrawal of Technical Specifications Change Request on Oscillating Power Range Monitor System12 September 2003Withdrawal of Technical Specifications Change Request on Oscillating Power Range Monitor System
NL-03-1932, Measurement Uncertainty Recapture Power Uprate (Murpu) Post Murpu Steam Dryer Performance Monitoring and Inspections12 September 2003Measurement Uncertainty Recapture Power Uprate (Murpu) Post Murpu Steam Dryer Performance Monitoring and Inspections
NL-03-1958, Response to NRC Bulletin 2003-02, Leakage from Reactor Pressure Vessel Lower Head Penetrations and Reactor Coolant Pressure Boundary Integrity.19 September 2003Response to NRC Bulletin 2003-02, Leakage from Reactor Pressure Vessel Lower Head Penetrations and Reactor Coolant Pressure Boundary Integrity.Boric Acid
VT-2
Pressure Boundary Leakage
Through-Wall Leak
NL-03-1997, Response to Regulatory Issue Summary 2003-14 Regarding Preparation and Scheduling of Operator Licensing Examination26 September 2003Response to Regulatory Issue Summary 2003-14 Regarding Preparation and Scheduling of Operator Licensing ExaminationGeneric Fundamentals Examination
NL-03-2008, Results of Reactor Pressure Vessel Head Inspections Required by Order EA-03-09913 October 2003Results of Reactor Pressure Vessel Head Inspections Required by Order EA-03-099Boric Acid
NL-03-2037, Response to IR 05000321-03-006, 05000366-03-006, with Notes1 October 2003Response to IR 05000321-03-006, 05000366-03-006, with NotesHot Short
Safe Shutdown
Operator Manual Action
Emergency Lighting
Exemption Request
Continuous fire watch
NL-03-2064, September 2003 Monthly Operating Report for Edwin I. Hatch, Units 1 and 27 October 2003September 2003 Monthly Operating Report for Edwin I. Hatch, Units 1 and 2
NL-03-2137, Unit 1 Cycle 21 Core Operating Limits Report (Colr), Revision 222 October 2003Unit 1 Cycle 21 Core Operating Limits Report (Colr), Revision 2
NL-03-2154, Response to RAI on the Turbine Building Area Temperature High Primary Containment Isolation Allowable Value Change Request23 October 2003Response to RAI on the Turbine Building Area Temperature High Primary Containment Isolation Allowable Value Change RequestGOTHIC
NL-03-2158, Updated Analysis of Core Shroud Vertical Welds14 November 2003Updated Analysis of Core Shroud Vertical WeldsFinite Element Analysis
EVT-1
NL-03-2177, Request to Revise Technical Specifications and Pressure and Temperature Limits Report26 February 2004Request to Revise Technical Specifications and Pressure and Temperature Limits ReportHydrostatic
Incorporated by reference
Pressure and Temperature Limits Report
Exemption Request
Fire Protection Program
Scaffolding
Affidavit
NL-03-2200, Technical Specification Report 1-2003-1 Number of Steam Generator Tubes Plugged During 1R1127 October 2003Technical Specification Report 1-2003-1 Number of Steam Generator Tubes Plugged During 1R11
NL-03-2237, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10CFR50.75(f)(1)27 October 2003Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10CFR50.75(f)(1)
NL-03-2239, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10CFR50.75(f)(1)31 October 2003Financial Assurance Requirements for Decommissioning Nuclear Power Reactors (10CFR50.75(f)(1)
NL-03-2266, Follow-Up Written Request for Notice of Enforcement Discretion and Request to Revise Technical Specification Surveillance Requirements 3.3.1.5 and 3.3.3.2, on an Exigent Basis5 November 2003Follow-Up Written Request for Notice of Enforcement Discretion and Request to Revise Technical Specification Surveillance Requirements 3.3.1.5 and 3.3.3.2, on an Exigent BasisEnforcement Discretion
NL-03-2313, Report of Unsatisfactory Performance Testing11 November 2003Report of Unsatisfactory Performance Testing
NL-03-2383, Inservice Inspection Summary Report16 January 2004Inservice Inspection Summary ReportBoric Acid
Hydrostatic
Nondestructive Examination
VT-2
Liquid penetrant
NL-03-2394, Results of Reactor Pressure Vessel Head Inspections, as Required by NRC Bulleting 2003-0219 December 2003Results of Reactor Pressure Vessel Head Inspections, as Required by NRC Bulleting 2003-02
NL-03-2400, Response to Request for Additional Information Regarding Generic Letter 96-0621 November 2003Response to Request for Additional Information Regarding Generic Letter 96-06Finite Element Analysis
NL-03-2412, License Amendment Request for Delay in Implementation of the Measurement Uncertainty Recapture Power Uprate11 December 2003License Amendment Request for Delay in Implementation of the Measurement Uncertainty Recapture Power Uprate
NL-03-2436, Independent Spent Fuel Storage Installation Registration of Spent Fuel Cask Use1 December 2003Independent Spent Fuel Storage Installation Registration of Spent Fuel Cask Use
NL-03-2451, Request for Surveillance Test Interval Extensions for Components of the Reactor Protection System27 January 2005Request for Surveillance Test Interval Extensions for Components of the Reactor Protection SystemProbabilistic Risk Assessment
Large early release frequency
Maintenance Rule Program
NL-03-2459, Response to NRC Bulletin 2003-04 Rebaselining of Data in the Nuclear Materials Management and Safeguards System, for Joseph M. Farley Nuclear Plant, Edwin I. Hatch Nuclear Plant and Vogtle Electric Generating Plant22 December 2003Response to NRC Bulletin 2003-04 Rebaselining of Data in the Nuclear Materials Management and Safeguards System, for Joseph M. Farley Nuclear Plant, Edwin I. Hatch Nuclear Plant and Vogtle Electric Generating Plant
NL-03-2471, Request to Revise Technical Specifications, Administrative Controls 5.2.2.g20 February 2004Request to Revise Technical Specifications, Administrative Controls 5.2.2.g
NL-03-2473, November 2003 Monthly Operating Report for Edwin I. Hatch, Units 1 and 28 December 2003November 2003 Monthly Operating Report for Edwin I. Hatch, Units 1 and 2
NL-03-2510, November 2003 Monthly Operating Report for Vogtle Units 1 and 215 December 2003November 2003 Monthly Operating Report for Vogtle Units 1 and 2
NL-03-2517, Application for Technical Specification Improvement to Revise TS 3.1.8, Scram Discharge Volume (SDV) Vent and Drain Valves, Using the Consolidated Line Item Improvement Process2 February 2004Application for Technical Specification Improvement to Revise TS 3.1.8, Scram Discharge Volume (SDV) Vent and Drain Valves, Using the Consolidated Line Item Improvement ProcessIncorporated by reference
Scram Discharge Volume
NL-03-2523, NPDES Permit Renewal Application15 December 2003NPDES Permit Renewal ApplicationGrab sample
NL-03-2553, Withdrawal of Request for Delay in Implementation of the Measurement Uncertainty Recapture Power Uprate17 December 2003Withdrawal of Request for Delay in Implementation of the Measurement Uncertainty Recapture Power Uprate
NL-03-2575, E. I. Hatch, Units 1 and 2 - Independent Spent Fuel Storage Installation Registration of Spent Fuel Cask Use19 December 2003E. I. Hatch, Units 1 and 2 - Independent Spent Fuel Storage Installation Registration of Spent Fuel Cask Use
NL-04-0001, Southern Nuclear Operating Company, Organization Management Changes5 January 2004Southern Nuclear Operating Company, Organization Management Changes
NL-04-0010, December 2003 Monthly Operating Report for Edwin I. Hatch, Units 1 and 214 January 2004December 2003 Monthly Operating Report for Edwin I. Hatch, Units 1 and 2
NL-04-0027, December 2003 Monthly Operating Report for Vogtle Electric Generating Plant,Units 1 and 213 January 2004December 2003 Monthly Operating Report for Vogtle Electric Generating Plant,Units 1 and 2
NL-04-0047, Update the Hatch Biological Assessment Under the Endangered Species Act for Shortnose Sturgeon15 January 2004Update the Hatch Biological Assessment Under the Endangered Species Act for Shortnose SturgeonLicense Renewal
Biofouling
Power Uprate
NL-04-0072, Proposed Technical Specifications Revisions to Primary Containment Leakage Rate Testing Program23 January 2004Proposed Technical Specifications Revisions to Primary Containment Leakage Rate Testing Program
NL-04-0073, Fluence Calculations and Methodology for the Unit I Updated Analysis of Core Shroud Vertical Welds30 January 2004Fluence Calculations and Methodology for the Unit I Updated Analysis of Core Shroud Vertical Welds