ML18092B462 | 31 December 1986 | Delmarva Power,1986 Annual Rept. | |
ML18092B466 | 31 December 1986 | Public Svc Enterprise Group 1986 Annual Rept. | |
ML18092B468 | 31 December 1986 | Philadelphia Electric Co,1986 Annual Rept. | |
ML18092B469 | 31 December 1986 | Atlantic Electric 1986 Annual Rept. | |
ML18092B497 | 3 April 1987 | S-C-E500-NSE-0675-R-1, Justification for Operation of All Three Units at Artificial Island at Increased Power During Hope Creek-Keeney Line Outage. | |
ML18093A179 | 19 June 1987 | Installation of Trip-A-Unit Protection Scheme Suppl Info Salem & Hope Creek Generating Stations. | |
ML18093A738 | 31 December 1987 | Philadelphia Electric Co Annual Rept,1987. | |
ML18093A739 | 31 December 1987 | Delmarva 1987 Annual Rept. | |
ML18093A740 | 31 December 1987 | Public Svc Enterprise Group Inc 1987 Annual Rept. | Exemption Request |
ML18093A741 | 31 December 1987 | Atlantic Energy 1987 Annual Rept. | Safe Shutdown Systematic Assessment of Licensee Performance |
ML18093A800 | 31 December 1987 | 1987 Annual Rept,Public Svc Enterprise Group,Inc. W/880422 Ltr | |
ML18093A828 | 6 May 1988 | Part 21 & Deficiency Rept Re Asea Brown Boveri,Power Distribution,Inc Low Voltage K-Line Circuit Breakers. Efforts Underway to Define Quantity & Type of Component Parts That May Need to Be Replaced | |
ML18093B337 | 31 December 1988 | Artificial Island Emergency Plan,Annual Exercise, Conducted on 881123-1202 | |
ML18094A355 | 30 April 1989 | Assessment of Impacts of Salem & Hope Creek Generating Stations on Kemps Ridley (Lepidochelys Kempi) & Loggerhead (Carretta Caretta) Sea Turtles. | Safe Shutdown Earthquake |
ML18094B147 | 25 October 1989 | Emergency Plan Annual Exercise 1989 for Artificial Island on 891025. W/One Oversize Drawing | |
ML18094B321 | 28 February 1990 | Annual Operating Repts for 1989 for Salem & Hope Creek Generating Stations | |
ML18095B017 | 31 December 1988 | 1988 Annual Rept. W/890406 Ltr | Fuel cladding |
ML18101A493 | 13 June 1989 | Radiological Emergency Preparedness Exercise Evaluation Rept. | |
ML18113A771 | 31 October 1978 | Vepco Flame Model. Util Developed 3 Dimensional(X,Y,Z) Modified Diffusion Therory Calculational Model Designated as Vepco Flame Model.Accuracy of Model Is Demonstrated Through Comparisons Taken at Units 1 & 2 | |
ML18130A352 | 26 March 1982 | Annual Financial Rept 1981.Financial Statements Attached | |
ML18130A395 | 10 November 1983 | VEPCO North Anna Power Station & Surry Power Station Compliance W/10CFR50.49(b)(2). | |
ML18139B819 | 31 March 1982 | Nine-Month Response to NRC Ltr Dtd 801220 on Control of Heavy Loads for VEPCO North Anna Units 1 & 2. | Control of Heavy Loads |
ML18139B925 | 30 June 1982 | PWR Safety & Relief Valve Adequacy Rept for North Anna Units 1 & 2. | Loop seal Stroke time |
ML18139C010 | 31 August 1982 | PWR Safety & Relief Valve Test Program,Porv Block Valve Adequacy Rept for Vepco,North Anna Unit 1 & Unit 2. | Stroke time Control of Heavy Loads |
ML18139C026 | 31 October 1982 | Final Draft of Amend 4 to QA Program-Operations Phase, Topical Rept | Hydrostatic Early Warning Fire Detection |
ML18139C061 | 4 October 1982 | Errata to VEPCO Reactor Core Thermal Hydraulic Analysis Using COBRA-IIIc/MIT Computer Code. | |
ML18139C291 | 30 April 1982 | Evaluation of Online Boron Analyzers, Final Rept | Boric Acid High Radiation Area Grab sample |
ML18141A258 | 31 October 1983 | Revised Reactor Core Thermal-Hydraulic Analysis Using Cobra Iiic/Mit Computer Code. | Fuel cladding |
ML18141A468 | 20 January 1984 | Safety Parameter Display Sys SAR for NUREG-0696 Computer Project,North Anna & Surry Nuclear Power Stations. | Boric Acid Shutdown Margin Reactor Vessel Water Level Fuel cladding |
ML18142A153 | 31 December 1984 | Nonproprietary Version of Revised VEPCO Evaluation of Control Rod Ejection Transient. | Shutdown Margin |
ML18149A430 | 30 September 1986 | Rev 1-A to Reload Nuclear Design Methodology. | Shutdown Margin |
ML18149A512 | 30 November 1986 | Qualification of WRB-1 CHF Correlation in VEPCO Cobra Code. | |
ML18151A135 | 28 August 1987 | Rev 1 to SPDS SAR for VEPCO NUREG-0696 Computer Project, North Anna & Surry Nuclear Power Stations. | Fuel cladding |
ML18151A541 | 21 June 1989 | Updated Operational QA Program Topical Rept. | Nondestructive Examination Early Warning Fire Detection |
ML18152B010 | 30 April 1988 | Updated QA Program,Operations Phase. | Nondestructive Examination |
ML18153B845 | 30 April 1988 | Errata to Updated Operational QA Program Topical Rept, Consisting of Replacement Pages 17.2-33a,17.2-36 & 17.2-38 | |
ML18153C101 | 2 February 1990 | Part 21 Rept Re Two of Three Pc Cards in GE Type SLV11A1 Over/Undervoltage Relays Failing to Produce Output.Short Between Leads Would Result in Damage to Component 1C5. Sketch of Threshold Detection Board Encl | |
ML19253D000 | 5 December 1979 | Final Deficiency Rept on Discrepancy in Drawings Re Design Calculation Concrete Reinforcement Requirements for Control & Diesel Generator Bldgs.Reinforcement Deficiencies in Process of Being Fully Corrected to Agree W/Calculations | Operating Basis Earthquake Earthquake |
ML19257C048 | 6 December 1979 | Interim Deficiency Rept on Use of Invalid Seismic Amplified Response Spectra.Caused by Incorrect Analysis of Safety Class 2 & 3 Piping sys.Short-term Audit of Selected Seismic Category 1 Sys & Components Conducted | |
ML19257C208 | 13 December 1979 | Interim Deficiency Rept Re Rod Drop Analysis.Westinghouse Recommendations Will Be Reviewed & Included in Topical Rept. Final Rept Will Be Forwarded by 800829 | |
ML19263A686 | 28 October 1978 | Deficiency Rept Re Refueling Water Storage Tank Design Undersizing of Tank'S Useable Vol for Loca.Corrective Action:Tank Capacity Increased from 375,000 Gals to 475,000 Gals | |
ML19276H631 | 6 December 1979 | Interim Deficiency Rept Re Use of Invalid Seismic Amplified Response Spectra in Design of safety-related Components. Contractor Is Redesigning Containment Annular Steel Frame. Contractor 791106 Ltr Re Deficiency Encl | |
ML19291B920 | 6 December 1979 | Interim Deficiency Rept Re Potential Failure in Engineered Safety Features Actuation Sys.Problem Identified by Manufacturer,Westinghouse.Info on Problem Resolution Will Be Provided by 800530 | |
ML19301D257 | 27 August 1985 | Final Deficiency Rept CDR 84-00-19 Re Main Steam Safety Valve Ring Setting.Initially Reported on 841221.Crosby Valve & Gage Co Adjusted Settings to -25 Notches for Lower & +25 Notches for Upper Rings | |
ML19305E835 | 15 May 1980 | Final Deficiency Rept Re Undetected Failure in Engineered Safety Features Actuation Sys.Procedures Will Be Implemented as Described in Westinghouse 800215 Ltr | |
ML19309F881 | 6 March 1980 | Annual Financial Rept 1979.SEC Forms 10-K & Miscellaneous Financial Info Attached | |
ML19309F887 | 26 February 1980 | Annual Financial Rept 1979.SEC Form 10-K Encl | |
ML19309F889 | 30 April 1980 | Annual Financial Rept 1979.Addl Financial Info Attached | |
ML19309F890 | 30 April 1980 | Annual Financial Rept 1979 | |
ML19316A738 | 15 May 1980 | Final Deficiency Rept Re Undetected Failure in Engineered Safety Features Actuation Sys.Util Will Implement Procedures Described in Westinghouse 800215 Ltr |