Semantic search
Jump to navigation
Jump to search
Issue date | Title | |
---|---|---|
05000293/FIN-2017002-02 | Reporting of Unplanned Scrams with Complications Performance Indicator for Feedwater Regulating Valve Scram | |
05000293/LER-1993-020 | 23 August 1993 | LER 93-020-00:on 930726,plant Personnel Found Anticipated Transient Without Scram Div 1 Pressure Transmitters Valved Out of Svc.Caused by Lack of Procedural Clarity.Personnel Revised procedure.W/930823 Ltr |
05000293/LER-1998-017, Forwards LER 98-017-00 Re Performance of Incomplete Surveillance for Reactor Water Level Instrument Channels. Action Being Taken to Preclude Recurrence,Listed | 12 August 1998 | Forwards LER 98-017-00 Re Performance of Incomplete Surveillance for Reactor Water Level Instrument Channels. Action Being Taken to Preclude Recurrence,Listed |
05000293/LER-2008-006 | Automatic Scram Resulting From Switchyard Breaker Fault During Winter Storm 05000 | |
05000293/LER-2013-003 | Loss of Off-Site Power Events Due to Winter Storm Nemo | |
05000293/LER-2016-007 | 4 November 2016 | Manual Reactor Scram Due To Feedwater Regulating Valve Malfunction LER 16-007-00 for Pilgrim Nuclear Power Station Regarding Manual Reactor Scram Due To Feedwater Regulating Valve Malfunction |
BECO-84-200, Responds to Generic Ltr 84-23 Re Improvements to Reactor Water Level Instrumentation Sys.Mods Either Rerouting or Preventing Ref Leg Overheating Are in Internal Review Cycle to Evaluate Feasibility & Impact on Safety | 28 November 1984 | Responds to Generic Ltr 84-23 Re Improvements to Reactor Water Level Instrumentation Sys.Mods Either Rerouting or Preventing Ref Leg Overheating Are in Internal Review Cycle to Evaluate Feasibility & Impact on Safety |
BECO-85-099, Responds to Generic Ltr 84-23, Reactor Vessel Water Level Instrumentation in Bwrs. Ref Leg Rerouting Will Provide Improvements in Accuracy & Reliability of Reactor Water Level Monitoring Control Sys | 28 May 1985 | Responds to Generic Ltr 84-23, Reactor Vessel Water Level Instrumentation in Bwrs. Ref Leg Rerouting Will Provide Improvements in Accuracy & Reliability of Reactor Water Level Monitoring Control Sys |
BECO-87-021, Forwards Response to Open Items Noted in Eg&G Idaho,Inc Review of Reg Guide 1.97 Compliance & Comparison of Accident Monitoring Instrumentation at Facility Vs Instrumentation Recommended by Reg Guide 1.97,per Generic Ltr 82-33 | 10 February 1987 | Forwards Response to Open Items Noted in Eg&G Idaho,Inc Review of Reg Guide 1.97 Compliance & Comparison of Accident Monitoring Instrumentation at Facility Vs Instrumentation Recommended by Reg Guide 1.97,per Generic Ltr 82-33 |
BECO-90-135, Proposed Tech Specs,Deleting Ref to Improved BWR Tech Specs & Withdrawing Requests for Changes to Reactor Water Level Safety Limit,Incorporation of Generic Ltr 90-02 Recommendations & Changes Re APRM Gain | 8 November 1990 | Proposed Tech Specs,Deleting Ref to Improved BWR Tech Specs & Withdrawing Requests for Changes to Reactor Water Level Safety Limit,Incorporation of Generic Ltr 90-02 Recommendations & Changes Re APRM Gain |
BECO-91-040, Forwards Summary of Compliance W/Reg Guide 1.97,Rev 2 to Assist NRC in Review of Compliance W/Reg Guide 1.97,Rev 3, Per 9100115 & 0405 Ltrs | 20 March 1991 | Forwards Summary of Compliance W/Reg Guide 1.97,Rev 2 to Assist NRC in Review of Compliance W/Reg Guide 1.97,Rev 3, Per 9100115 & 0405 Ltrs |
BECO-91-066, Forwards Updated Summary of Compliance W/Reg Guide 1.97 & Responds to NRC SER | 13 May 1991 | Forwards Updated Summary of Compliance W/Reg Guide 1.97 & Responds to NRC SER |
BECO-91-126, Forwards Revised Tech Spec Bases to Correct Refs to Fsar. Bases Not Legal Part of Tech Specs & Do Not Constitute Amend to License DPR-35 | 4 October 1991 | Forwards Revised Tech Spec Bases to Correct Refs to Fsar. Bases Not Legal Part of Tech Specs & Do Not Constitute Amend to License DPR-35 |
BECO-91-148, Reactor Containment Bldg Integrated Leakage Rate Test Rept | 5 August 1991 | Reactor Containment Bldg Integrated Leakage Rate Test Rept |
BECO-92-038, Requests Temporary Waiver of Compliance for 96 H from Plant Startup to Cold Shutdown from Applicable Portions of Plant TS Associated W/Rv Water Level Instrumentation.Supercedes Previous Request | 7 April 1992 | Requests Temporary Waiver of Compliance for 96 H from Plant Startup to Cold Shutdown from Applicable Portions of Plant TS Associated W/Rv Water Level Instrumentation.Supercedes Previous Request |
BECO-92-113, Responds to Generic Ltr 92-04 Dtd 920819, Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in BWRs Pursuant to 10CFR50.54(f) | 28 September 1992 | Responds to Generic Ltr 92-04 Dtd 920819, Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in BWRs Pursuant to 10CFR50.54(f) |
BECO-93-117, Forwards Semiannual long-term Program Update Per Section V.A of Plan for Long-Term Program - Pilgrim Nuclear Power Station, Including Schedules for a & B Regulatory Items & Commitment Descriptions & Progress Since Last Update | 30 August 1993 | Forwards Semiannual long-term Program Update Per Section V.A of Plan for Long-Term Program - Pilgrim Nuclear Power Station, Including Schedules for a & B Regulatory Items & Commitment Descriptions & Progress Since Last Update |
IR 05000293/1982012 | 29 June 1982 | IE Insp Rept 50-293/82-12 on 820405-0509.Noncompliance Noted:Failure to Insert All Control Rods within 4-h of Having Less than Two Operable Reactor Vessel Low Water Level Instrument Channels in Both Trip Sys |
IR 05000293/1985011 | 28 June 1985 | Safety Insp Rept 50-293/85-11 on 850507-0608.No Violations Noted.Major Areas Inspected:Plant Operations,Including ESF Walkdown,Operational Safety Verification & Surveillance & Maint Activities |
IR 05000293/1985030 | 21 January 1986 | Insp Rept 50-293/85-30 on 851023-1122.No Noncompliance Noted.Major Areas Inspected:Operational Readiness of HPCI Sys.Partial Review Conducted in Areas of Core Spray & Standby Gas Treatment Sys |
IR 05000293/1986015 | 17 July 1986 | Combined Exam & Insp Rept 50-293/86-15OL,conducted During Wk of 860505.Exam Results:Four Reactor Operator & Two Senior Reactor Operator Candidates Passed.Major Areas Inspected: Requalification Training Program |
IR 05000293/1986040 | 4 February 1987 | Insp Rept 50-293/86-40 on 861124-1231.No Violations Noted. Major Areas Inspected:Radiation Protection,Physical Security,Plant Events,Maint,Surveillance,Outage Activities & Repts to Nrc.Inspector Concerns Listed |
IR 05000293/1987032 | 6 November 1987 | Insp Rept 50-293/87-32 on 870803-07,10-14 & 20.Violation Noted.Major Areas Inspected:Five Mods in Progress,Design Concept,Design Engineering process,10CFR50.59 Process,Mod Procurement process,post-mod Testing & Sys Restoration |
IR 05000293/1988034 | 14 February 1989 | Safety Insp Rept 50-293/88-34 on 881114-1226.No Violations Noted.Major Areas Inspected:Plant Operations,Radiation Protection,Physical Security,Plant Events,Maint, Surveillance,Part 21 Repts & Outage Activities |
IR 05000293/1989090 | 25 May 1989 | Forwards Plant Biweekly Status Rept for 890506-19.On 890508, Augmented Insp Team Rept 50-293/89-90 Issued Concluding That Safety Significance of 890412 Pressure Transient Minor Since Several Barriers Remained Intact or Available |
IR 05000293/1990020 | 7 November 1990 | Safety Insp Rept 50-293/90-20 on 900816-1008.Violation Noted.Major Areas Inspected:Plant Operations,Security, Maint & Surveillance,Engineering & Technical Support, Radiological Controls,Emergency Preparedness & Safety |
IR 05000293/1991099 | 28 April 1993 | SALP Rept 50-293/91-99 for 910929-930313 |
IR 05000293/1992023 | 29 December 1992 | Safety Insp Rept 50-293/92-23 on 921020-1123.No Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Emergency Preparedness, Security & Safety Assessment & Quality Verification |
IR 05000293/1992028 | 28 January 1993 | Insp Rept 50-293/92-28 on 921124-1231.Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint & Surveillance,Emergency Preparedness, Security,Safety Assessment & Quality Verification |
IR 05000293/1993014 | 8 September 1993 | Insp Rept 50-293/93-14 on 930713-0816.No Violations Noted. Major Areas Inspected:Plant Operations,Maintenance & Surveillance,Engineering & Plant Support |
IR 05000293/1993015 | 15 October 1993 | Insp Rept 50-293/93-15 on 930817-0927.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls Maint & Surveillance,Emergency Preparedness,Security,Safety Assessment & Quality Verification |
IR 05000293/1993020 | 10 January 1994 | Insp Rept 50-293/93-20 on Stated Date.No Violations Noted. Major Areas Inspected:Operations,Maintenance & Surveillance, Engineering & Plant Support |
IR 05000293/1993099 | 16 November 1994 | SALP Rept 50-293/93-99 for Period 930314-941008 |
IR 05000293/1996006 | 30 October 1996 | Insp Rept 50-293/96-06 on 960729-0923.Violations Noted.Major Areas Inspected:Licensee Operations,Engineering,Maint & Plant Support |
IR 05000293/1996008 | 18 December 1996 | Insp Rept 50-293/96-08 on 960924-1122.Violation Noted.Major Areas Inspected:Engineering,Maint,Plant Support,Radioactive Effluent Controls Program,Radiological Environmental Monitoring & Meteorological Monitoring.Meeting Slides Encl |
IR 05000293/1997001 | 16 September 1997 | Ack Receipt of 970417 & 0829 Ltrs Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-293/97-01 on 970318 |
IR 05000293/1997011 | 11 December 1997 | Insp Rept 50-293/97-11 on 970914-1110.Violations Noted:Major Areas Inspected:Operations,Maint,Engineering & Plant Support |
IR 05000293/1997013 | 6 February 1998 | Insp Rept 50-293/97-13 on 971111-980106.Violations Noted. Major Areas Inspected:Operations,Engineering,Maint & Plant Support |
IR 05000293/1997099 | 26 November 1997 | Correction to SALP Rept 50-293/97-99.Page 2 of Subj Rept Corrected |
IR 05000293/2001008 | 28 January 2002 | IR 05000293/2001-08, Pilgrim Nuclear Power Station, Inspection on 11/18 - 12/29/2001, Related to Personnel Performance During Non-routine Plant Evolutions, Human Performance Issues. Non-cited Violation Noted |
IR 05000293/2001012 | 18 March 2002 | IR 05000293/2001-012; on 12/30/2001 - 02/16/2002; Entergy Nuclear Generation Company; Pilgrim Nuclear Power Station, Resident Inspection. No Violations Identified |
IR 05000293/2002004 | 30 July 2002 | IR 05000293-02-004, on 05/12 - 06/29/02, Pilgrim Nuclear Power Station, Resident Inspection Report |
IR 05000293/2003006 | 30 July 2003 | IR 05000293-03-006; on 03/30 - 06/28/03; for Pilgrim Nuclear Power Station, Resident Inspection. Personnel Performance During Non-routine Plant Evolutions, Refueling and Other Outage Activities, and Surveillance Testing |
IR 05000293/2007003 | 2 August 2007 | IR 05000293-07-003; 04/01/2007-06/30/2007; Pilgrim Nuclear Power Station; Maintenance Effectiveness, Maintenance Risk Assessment and Emergent Work Control, Refueling and Other Outage Activities |
IR 05000293/2017002 | 14 August 2017 | Integrated Inspection Report 05000293/2017002 |
IR 05000293/2018004 | 13 February 2019 | Integrated Inspection Report 05000293/2018004 and Independent Spent Fuel Storage Installation Report 07201044/2018201 |
Information Notice 1990-22, Unanticipated Equipment Actuations Following Restoration of Power to Rosemount Transmitter Trip Units | 23 March 1990 | Unanticipated Equipment Actuations Following Restoration of Power to Rosemount Transmitter Trip Units |
Information Notice 1992-16, Loss of Flow from the Residual Heat Removal Pump During Refueling Cavity Draindown | 25 February 1992 | Loss of Flow from the Residual Heat Removal Pump During Refueling Cavity Draindown |
Information Notice 1993-27, Level Instrumentation Inaccuracies Observed During Normal Plant Depressurization | 8 April 1993 | Level Instrumentation Inaccuracies Observed During Normal Plant Depressurization |
Information Notice 1993-62, Thermal Stratification of Water in BWR Reactor Vessels | 10 August 1993 | Thermal Stratification of Water in BWR Reactor Vessels |