IR 05000225/20050034 June 1985Insp Rept 50-458/85-18 on 850225-0503.Deviation Noted: Ranges of Display Instrumentation for HPCS Flow & RHR Svc Water Flow Contrary to Table 7.5-1 of Fsar,Amend 11, Dtd Jan 1984
IR 05000311/200401910 May 1985Insp Rept 50-458/85-22 on 850311-0419.No Violation or Deviation Noted.Major Areas Inspected:Maint Program,Test & Measurement Equipment,Surveillance Testing & Calibr Control Program,Design Changes & Mods & Document ControlTemporary Modification
Fire Watch
IR 05000311/20050171 August 1985Insp Rept 50-458/85-19 on 850311-0517.Violation Noted: Failure to Incorporate Engineering & Design Coordination Rept Info Into Drawings & Use External Historical Data in Evaluation of SuppliersSquib
Scaffolding
IR 05000311/200801023 January 1986Insp Rept 50-458/85-09 on 850311-0810.Violations Noted: Failure to Adequately Check Calculations,Document & Verify Assumptions & Provide Basis for Design InputSafe Shutdown Earthquake
Operating Basis Earthquake
Earthquake
IR 05000401/20070122 August 1985Notice of Violation from Insp on 850401-0712.Violation Noted:Failure to Assure Conformance of safety-related Structural Steel Welds W/Criterion X of App B to 10CFR50 & Aws Structural Welding Code Aws D 1.1-75
IR 05000401/200800917 September 1985Insp Rept 50-458/85-29 on 850401-0809.Violation Noted: Failure to Assure Conformance of safety-related Structural Steel Welds W/Requirements of Aws D1.1-75 Structural Steel Welding CodeLoctite
IR 05000415/200602715 August 1985Insp Rept 50-458/85-33 on 850415-0627.Violation Noted: Failure to Adequately Document Changes to Insp Rept Results
IR 05000458/197800522 September 1978Insp Rept 50-458/78-05 on 780905-08.No Noncompliance Noted. Major Areas Inspected:Previously Identified Unresolved Items & Const Deficiency Rept Re Nonconforming Rebar
IR 05000458/198200219 May 1982IE Insp Rept 50-458/82-02 on 820419-23.No Noncompliance Noted.Major Areas Inspected:Review of QA Program for Welding & Nondestructive Exam of safety-related Piping & Observation of Work for Subj Piping
IR 05000458/198200615 July 1982IE Insp Rept 50-458/82-06 on 820614-18.No Noncompliance Noted.Major Areas Inspected:Previous Insp Findings,Qa Program Review & Work for Erection/Installation & Welding of safety-related Structural Steel & Supports
IR 05000458/19850273 June 1985Insp Rept 50-458/85-27 on 850401-04.No Violation or Deviation Noted.Major Areas Inspected:Implementation of Fire Protection Program & Compliance w/10CFR50,App R Re Safe Shutdown Per FSAR Commitments & SER EvaluationSafe Shutdown
Fire Barrier
Emergency Lighting
Fire Protection Program
Fire Watch
IR 05000458/19850325 August 1985Insp Rept 50-458/85-32 on 850624-28.No Violations or Deviations Noted.Major Areas Inspected:Licensee Radiation Protection Program,Tmi Action Items & Emergency Preparedness ActivitiesLoop seal
Grab sample
IR 05000458/198503619 June 1985Insp Rept 50-458/85-36 on 850506-10.No Violation or Deviation Noted.Major Areas Inspected:Training,Organization, Coordination W/Offsite Groups,Emergency Procedures & Emergency Response Facilities & Equipment
IR 05000458/198503729 May 1985Insp Rept 50-458/85-37 on 850506-10.No Violation or Deviation Noted.Major Areas Inspected:Correction of Deficiencies Previously Identified Per 10CFR50.55(e)
IR 05000458/198503817 July 1985Insp Rept 50-458/85-38 on 850513-17.No Violations or Deviations Noted.Major Areas Inspected:Preoperational Test Witnessing,Preoperational Test Results Evaluation & TMI Action Items
IR 05000458/198503920 June 1985Insp Rept 50-458/85-39 on 850520-25.No Violation or Deviation Noted.Major Areas Inspected:Preoperational Test Performance & Results & Licensee Actions on Previous Insp Findings & 10CFR50.55(e) Items
IR 05000458/198504129 August 1985Insp Rept 50-458/85-41 on 850522-0712.No Violation or Deviation Noted.Major Areas Inspected:Followup on Previous Findings,Comparison of as-built Plant to FSAR Description, Verification of as-built Electrical Routing & TerminationsSafe Shutdown
Fire Barrier
Emergency Lighting
Fire Watch
IR 05000458/198504412 September 1985Insp Rept 50-458/85-44 on 850603-0726.No Violations or Deviations Identified.Major Areas Inspected:Open Significant Const Deficiencies Per 10CFR50.55(e) & Previous Insp FindingsScram Discharge Volume
Grace period
IR 05000458/198504517 July 1985Insp Rept 50-458/85-45 on 850520-0603.No Violation or Deviation Noted.Major Areas Inspected:Licensee Action on Previous Insp Findings & Site ToursTemporary Modification
IR 05000458/198504629 July 1985Insp Rept 50-458/85-46 on 850603-07.No Violations or Deviations Noted.Major Areas Inspected:Radwaste Mgt & Transportation Activities,Including Organization,Audits & Process Control PlanProcess Control Program
IR 05000458/198504719 July 1985Insp Rept 50-458/85-47 on 850610-14.No Violations or Deviations Noted.Major Areas Inspected:Chemistry/ Radiochemistry Program,Including Organization,Staffing,Staff Qualifications,Facilities & Equipment & QA Program
IR 05000458/19850489 August 1985Insp Rept 50-458/85-48 on 850624-28.No Violations or Deviations Identified.Major Areas Inspected:Preoperational Test Results Evaluation & Operating Procedures
IR 05000458/198505028 August 1985Insp Rept 50-458/85-50 on 850624-29.No Violation or Deviation Noted.Major Areas Inspected:Alarm Stations, Security Sys Power Supply,Access control-personnel & Access control-packages.Details Withheld (Ref 10CFR73.21)
IR 05000458/198505223 August 1985Insp Rept 50-458/85-52 on 850708-12.No Violation or Deviation Noted.Major Areas Inspected:Emergency & Abnormal Operating Procedures,Ie Bulletin & post-TMI Action Plan Requirements Followup & Corrective Actions TakenFuel cladding
IR 05000458/19850534 September 1985Insp Rept 50-458/85-53 on 850805-09.No Violation or Deviation Noted.Major Areas Inspected:Radiation Protection Training,Selected TMI Action Items,Chemistry Sample Stations,Radwaste Processing Sys & Environ ProgramGrab sample
Process Control Program
IR 05000458/19850544 October 1985Insp Rept 50-458/85-54 on 850722-26 & 31-0802.No Violation or Deviation Noted.Major Areas Inspected: Preoperational Test Results Evaluation & IE Bulletin Followup
IR 05000458/198505513 September 1985Insp Rept 50-458/85-55 on 850715-19 & 29-0801.No Violation or Deviation Noted.Major Areas Inspected:Mgt Effectiveness, Security Organization,Records & Repts & Lock & Key Controls. Details Withheld (Ref 10CFR73.21)
IR 05000458/198505630 August 1985Special Insp Rept 50-458/85-56 on 850715-17.No Violations or Deviations Noted.Major Areas Inspected:Followup in Findings from Emergency Appraisal & 1985 Emergency ExerciseSiren
IR 05000458/198505724 August 1985Insp Rept 50-458/85-57 on 850722-26.No Violation or Deviation Noted.Major Areas Inspected:Training Program, Chemistry/Radiochemistry Program,Facilities & Equipment & Administrative & Analytical Procedures
IR 05000458/198505823 August 1985Insp Rept 50-458/85-58 on 850722-26.No Violation or Deviation Noted.Major Areas Inspected:Tech Specs & Implementing Procedures
IR 05000458/198505917 October 1985Insp Rept 50-458/85-59 on 850819-23.Violation Noted: Improper Disposition of Nonconformance Repts Re Test Procedure CriteriaFitness for Duty
IR 05000458/19850609 October 1985Insp Rept 50-458/85-60 on 850909-13.No Violation or Deviation Noted.Major Areas Inspected:Deficiency Repts,Tmi Action Items & Fuel Load WitnessingShutdown Margin
IR 05000458/198506115 October 1985Insp Rept 50-458/85-61 on 850823-25.No Violations or Deviations Noted.Major Areas Inspected:Allegations of Improprieties on Part of Certain Licensee Contractor &/Or Subcontractor PersonnelLiquid penetrant
IR 05000458/198506324 October 1985Insp Rept 50-458/85-63 on 850923-27.No Violation or Deviation Noted.Major Areas Inspected:Followup of Various Open Items & License ConditionsShutdown Margin
IR 05000458/198506416 October 1985Insp Rept 50-458/85-64 on 850916-20.No Violation or Deviation Noted.Major Areas Inspected:Radwaste Mgt Controls, Training & Qualifications,Radwaste Startup & Liquid & Gaseous Waste Sys
IR 05000458/198506521 October 1985Insp Rept 50-458/85-65 on 850916-20.No Violation or Deviation Noted.Major Areas Inspected:Radiological Environ Monitoring Program,Including Organization & Mgt Controls, Meteorological Monitoring Program & QA ProgramGrab sample
Offsite Dose Calculation Manual
IR 05000458/19850681 November 1985Insp Rept 50-458/85-68 on 850930-1003.No Violation or Deviation Noted.Major Areas Inspected:Quality Concerns Program,Asme Certification Program & Followup on Previous Insp FindingsFitness for Duty
Hydrostatic
IR 05000458/198507021 October 1985Insp Rept 50-458/85-70 on 851002-03.No Violation or Deviation Noted.Major Areas Inspected:Licensee Actions to Resolve OL Precriticality Conditions,Including Plant Air Flow Characteristics
IR 05000458/19850722 December 1985Insp Rept 50-458/85-72 on 851009-11.No Violation or Deviation Noted.Major Areas Inspected:Emergency Procedures Appraisal Findings Identified in Insp Rept 50-458/84-34
IR 05000458/198507910 January 1986Insp Rept 50-458/85-79 on 851202-06.No Violation or Deviation Noted.Major Areas Inspected:Startup Test Procedure Review (Turbine Trip) & Startup Test Witnessing
IR 05000458/19850829 January 1986Insp Rept 50-458/85-82 on 851216-20.Violation Noted: Electronic Calibr on Primary Containment Area Radiation Monitor Only Included Every Other Decade Range Between 0 & 100% Full Scale
IR 05000458/19860075 May 1986SALP Rept 50-458/86-07 for Jan 1985 - Jan 1986.Overall Performance Indicates High Level of Dedication to Nuclear Safety & High Degree of Technical CompetenceFitness for Duty
Reactor Vessel Water Level
Ultimate heat sink
Grab sample
Offsite Dose Calculation Manual
Squib
Emergency Lighting
Scram Discharge Volume
Process Control Program
Systematic Assessment of Licensee Performance
Fire Protection Program
IR 05000458/198601229 May 1986Insp Repts 50-458/86-12 & 50-458/86-18 Cancelled
IR 05000458/198601723 May 1986Partially Withheld Insp Rept 50-458/86-17 on 860331-0404 & 0502 (Ref 10CFR73.21).Violations Noted Re Vital Area Physical Barriers & Personnel Access Control
IR 05000458/19860219 June 1986Insp Rept 50-458/86-21 on 860512-16.No Violation or Deviation Noted.Major Areas Inspected:Licensed Operator Training & Nonlicensed Staff Training
IR 05000458/198602319 August 1986Insp Rept 50-458/86-23 on 860615-0731.No Violations or Deviations Noted.Major Areas Inspected:Evaluation of Startup Test Results,Operational Safety Verification,Safety Sys Walkdown,Maint Witnessing & Surveillance Witnessing
IR 05000458/198602421 October 1986Insp Rept 50-458/86-24 on 860818-22.Deviation Noted:Failure to Verify Certain Abnormal Operating Procedures
IR 05000458/19860258 August 1986Insp Rept 50-458/86-25 on 860721-25.Violation Noted:Failure to Follow Procedures.Deficiencies Noted Re Dose Assessment Training & Equipment
IR 05000458/198602619 December 1986Insp Rept 50-458/86-26 Canceled
IR 05000458/198602716 October 1986Insp Rept 50-458/86-27 on 860801-0915.Violations Noted: Failure to Meet Electrical Spec Requirements & Failure to Follow Surveillance Test ProcedureSafe Shutdown
Half scram
Ultimate heat sink