ML020300072 | 18 January 2002 | Part 1 of 3, J. M. Farley Unit 1 Nuclear Generating Plant, Inservice Inspection Report, Refueling 17, Interval 3, Period 2, Outage 1 | Boric Acid Hydrostatic Nondestructive Examination VT-2 Liquid penetrant Dissimilar Metal Weld |
ML020300139 | 18 January 2002 | Part 3 of 3, J. M. Farley Unit 1 Nuclear Generating Plant, Inservice Inspection Report, Refueling 17, Interval 3, Period 2, Outage 1 | Hydrostatic Nondestructive Examination VT-2 Liquid penetrant |
ML041960077 | 7 July 2004 | Inservice Inspection Summary Report | Boric Acid Hydrostatic Nondestructive Examination |
ML052850011 | 11 October 2005 | Notification of NRC Inspection and Request for Information | Boric Acid Nondestructive Examination VT-2 |
ML12045A067 | 9 February 2012 | Unit 2 Refueling Outage 2R21 Inservice Inspection Report | Hydrostatic Nondestructive Examination VT-2 Moisture barrier Dissimilar Metal Weld |
ML14148A492 | 28 May 2014 | ISI Program Alternative FNP-ISI-ALT-16. Version 1 | |
ML17180A439 | 18 July 2017 | Inservice Testing Alternative for Pumps Per Code Case OMN-20 (RR-VR-01) | Grace period |
NL-03-0167, J. M. Farley Unit 2, Inservice Inspection Report, Refueling 15, Interval 3, Period 1, Outage 1, Td Certs | 21 January 2003 | J. M. Farley Unit 2, Inservice Inspection Report, Refueling 15, Interval 3, Period 1, Outage 1, Td Certs | Hydrostatic Nondestructive Examination VT-2 Liquid penetrant |
NL-03-0455, Inservice Inspection Program, Additional Information for Request for Relief No. RR-48 | 10 March 2003 | Inservice Inspection Program, Additional Information for Request for Relief No. RR-48 | |
NL-03-1259, Risk-Informed Inservice Inspection Program - ASME Code Category B-F, B-J, C-F-1 & C-F-2 Piping | 17 July 2003 | Risk-Informed Inservice Inspection Program - ASME Code Category B-F, B-J, C-F-1 & C-F-2 Piping | Loop seal Non-Destructive Examination Mission time Probabilistic Risk Assessment Nondestructive Examination VT-2 Large early release frequency Maintenance Rule Program Dissimilar Metal Weld |
NL-03-1556, Inservice Inspection Summary Report | 25 July 2003 | Inservice Inspection Summary Report | Boric Acid Hydrostatic Nondestructive Examination Liquid penetrant Scaffolding |
NL-05-0285, ASME Section XI Request for Alternative Numbers RR-57, Proposed Alternative to IWL-2421(a) Requirements, and RR-58, Proposed Alternative to IWL-2421 (B) Requirements | 31 May 2005 | ASME Section XI Request for Alternative Numbers RR-57, Proposed Alternative to IWL-2421(a) Requirements, and RR-58, Proposed Alternative to IWL-2421 (B) Requirements | |
NL-06-1766, Unit 1, Inservice Inspection Summary Report | 17 August 2006 | Unit 1, Inservice Inspection Summary Report | Hydrostatic Nondestructive Examination VT-2 Moisture barrier |
NL-07-1418, Fourth Ten-Year Interval Inservice Testing Program Update | 14 August 2007 | Fourth Ten-Year Interval Inservice Testing Program Update | Safe Shutdown Boric Acid Ultimate heat sink Stroke time Incorporated by reference Cold shutdown justification Power Operated Valves |
NL-07-1560, Inservice Inspection Summary Report | 14 August 2007 | Inservice Inspection Summary Report | Weld Overlay Hydrostatic Nondestructive Examination VT-2 Through Wall Leak Dissimilar Metal Weld |
NL-08-0136, Inservice Inspection Summary Report | 6 February 2008 | Inservice Inspection Summary Report | Weld Overlay Hydrostatic Anchor Darling Nondestructive Examination VT-2 Dissimilar Metal Weld |
NL-08-1007, Withdrawal of Proposed Alternative FNP-ISI-ALT-07-02 Continued Operation with Pinhole Leaks in Class 2 Valve Q2N11V003B | 27 June 2008 | Withdrawal of Proposed Alternative FNP-ISI-ALT-07-02 Continued Operation with Pinhole Leaks in Class 2 Valve Q2N11V003B | |
NL-10-1514, 2R20 Inservice Inspection Report | 11 August 2010 | 2R20 Inservice Inspection Report | Weld Overlay Hydrostatic Nondestructive Examination VT-2 Moisture barrier Code Reconciliation Dissimilar Metal Weld |
NL-10-2355, Request for Approval of Risk-Informed/Safety Based Inservice Inspection Alternative for Class 1 and 2 Piping FNP-ISI-AL T-12, Version 2.0 | 5 January 2011 | Request for Approval of Risk-Informed/Safety Based Inservice Inspection Alternative for Class 1 and 2 Piping FNP-ISI-AL T-12, Version 2.0 | High winds Mission time Weld Overlay Internal Flooding Probabilistic Risk Assessment Nondestructive Examination VT-2 Seismically rugged Large early release frequency Dissimilar Metal Weld |
NL-11-0255, Outage Inservice Inspection Summary Report | 15 February 2011 | Outage Inservice Inspection Summary Report | Hydrostatic Nondestructive Examination VT-2 FLEX Dissimilar Metal Weld |
NL-12-0242, Joseph M. Farley Nuclear Plant - Unit 2 Refueling Outage 2R21 Inservice Inspection Report | 9 February 2012 | Joseph M. Farley Nuclear Plant - Unit 2 Refueling Outage 2R21 Inservice Inspection Report | Hydrostatic Nondestructive Examination VT-2 Moisture barrier Dissimilar Metal Weld |
NL-12-0242, NL-12-0242 Part 2, Form NIS-2 Owner'S Report for Repair/Replacement Activity | 9 February 2012 | NL-12-0242 Part 2, Form NIS-2 Owner'S Report for Repair/Replacement Activity | Hydrostatic |
NL-12-1499, Refueling Outage 1R24 Inservice Inspection Report | 20 July 2012 | Refueling Outage 1R24 Inservice Inspection Report | |
NL-12-2014, Proposed Inservice Inspection Alternative FNP-ISI-AL T-13 Version 1.0 | 1 October 2012 | Proposed Inservice Inspection Alternative FNP-ISI-AL T-13 Version 1.0 | Boric Acid Probabilistic Risk Assessment Finite Element Analysis Large early release frequency Through-Wall Leak Through Wall Leak Dissimilar Metal Weld DM weld |
NL-13-1729, Refueling Outage 2R22 Inservice Inspection Report | 7 August 2013 | Refueling Outage 2R22 Inservice Inspection Report | |
NL-14-0143, Refueling Outage 1R25 Lnservice Inspection Report | 24 January 2014 | Refueling Outage 1R25 Lnservice Inspection Report | Hydrostatic Nondestructive Examination VT-2 Dissimilar Metal Weld |
NL-14-0295, Proposed Lnservice Inspection Alternative FNP-ISI-ALT-15, Version 1.0 | 24 March 2014 | Proposed Lnservice Inspection Alternative FNP-ISI-ALT-15, Version 1.0 | Through-Wall Leak Dissimilar Metal Weld DM weld |
NL-14-1276, Snubber Inspection Plan Submittal in Accordance with ASME OM Code | 31 October 2014 | Snubber Inspection Plan Submittal in Accordance with ASME OM Code | Safe Shutdown Anchor Darling |
NL-15-0317, Refueling Outage 2R23 Inservice Inspection Report | 16 February 2015 | Refueling Outage 2R23 Inservice Inspection Report | |
NL-15-0718, Proposed Inservice Inspection Alternative FNP-ISI-ALT-17, Version 2.0 | 21 April 2015 | Proposed Inservice Inspection Alternative FNP-ISI-ALT-17, Version 2.0 | Boric Acid Nondestructive Examination Through-Wall Leak |
NL-15-0850, Refueling Outage 2R23 Steam Generator Tube Inspection Report | 11 May 2015 | Refueling Outage 2R23 Steam Generator Tube Inspection Report | Nondestructive Examination |
NL-15-1483, Refueling Outage 1R26 Inservice Inspection Report | 4 August 2015 | Refueling Outage 1R26 Inservice Inspection Report | Packing leak Hydrostatic Nondestructive Examination VT-2 FLEX Moisture barrier Through Wall Leak |
NL-15-2130, Responds to Request for Additional Information for Proposed Inservice Inspection Alternative FNP-ISI-ALT-18, Version 1.0 | 25 November 2015 | Responds to Request for Additional Information for Proposed Inservice Inspection Alternative FNP-ISI-ALT-18, Version 1.0 | |
NL-16-0723, Proposed Inservice Inspection Alternative FNP-ISI-ALT-19, Version 1.0 | 30 June 2016 | Proposed Inservice Inspection Alternative FNP-ISI-ALT-19, Version 1.0 | Pressure Boundary Leakage Weak link |
NL-16-1277, 2R24 Lnservice Inspection Report Summary | 9 August 2016 | 2R24 Lnservice Inspection Report Summary | |
NL-16-1329, Proposed Inservice Inspection Alternative VEGP-ISI-ALT-11, Version 2.0 and Proposed Inservice Inspection Alternative FNP-ISI-ALT-19, Version 2.0 | 4 August 2016 | Proposed Inservice Inspection Alternative VEGP-ISI-ALT-11, Version 2.0 and Proposed Inservice Inspection Alternative FNP-ISI-ALT-19, Version 2.0 | Finite Element Analysis Weak link |
NL-17-0082, Submittal of the Lnservice Testing Program Alternatives for the Fifth Ten-Year Interval | 6 February 2017 | Submittal of the Lnservice Testing Program Alternatives for the Fifth Ten-Year Interval | Boric Acid Grace period |
NL-17-0167, Refueling Outage 1R27 Inservice Inspection Report | 6 February 2017 | Refueling Outage 1R27 Inservice Inspection Report | Packing leak Hydrostatic Coatings Nondestructive Examination VT-2 FLEX Through Wall Leak |
NL-17-2005, Fifth Ten-Year Interval Inservice Testing Program Update | 11 March 2019 | Fifth Ten-Year Interval Inservice Testing Program Update | Safe Shutdown Boric Acid Ultimate heat sink Stroke time Incorporated by reference Surveillance Frequency Control Program Cold shutdown justification Power Operated Valves Grace period |
NL-18-0192, Submittal of Refueling Outage 2R25 Lnservice Inspection Report | 12 February 2018 | Submittal of Refueling Outage 2R25 Lnservice Inspection Report | |
NL-18-1000, Lnservice Inspection Program Owner'S Activity Report for Outage 1R28 | 31 July 2018 | Lnservice Inspection Program Owner'S Activity Report for Outage 1R28 | Boric Acid Through Wall Leak |
NL-18-1041, Proposed Alternative for the Fifth Interval Inservice Inspection FNP-ISI-AL T-05-04, Version 1.0 | 8 March 2019 | Proposed Alternative for the Fifth Interval Inservice Inspection FNP-ISI-AL T-05-04, Version 1.0 | Grace period |
NL-18-1384, Fourth 10-Year Interval Inservice Inspection Program ISI Program Update: Notification of Impractical ASME Code Requirements | 30 November 2018 | Fourth 10-Year Interval Inservice Inspection Program ISI Program Update: Notification of Impractical ASME Code Requirements | Nondestructive Examination |
NL-19-0347, Snubber Program Plan for the Fifth Ten Year Inservice Testing Interval | 10 April 2019 | Snubber Program Plan for the Fifth Ten Year Inservice Testing Interval | Safe Shutdown |
NL-19-0872, Inservice Inspection Program Owner'S Activity Report for Outage 2R26 | 26 July 2019 | Inservice Inspection Program Owner'S Activity Report for Outage 2R26 | Through-Wall Leak |
NL-19-1296, Refueling Outage 2R26 Steam Generator Tube Inspection Report | 24 October 2019 | Refueling Outage 2R26 Steam Generator Tube Inspection Report | Nondestructive Examination |
NL-20-0034, Inservice Inspection Program Owner'S Activity Report for Outage 1R29 | 17 January 2020 | Inservice Inspection Program Owner'S Activity Report for Outage 1R29 | Through-Wall Leak |
NL-20-0417, Refueling Outage 1R29 Steam Generator Tube Inspection Report | 17 April 2020 | Refueling Outage 1R29 Steam Generator Tube Inspection Report | Nondestructive Examination |
NL-21-0061, Inservice Inspection Program Owner'S Activity Report for Outage 2R27 | 12 February 2021 | Inservice Inspection Program Owner'S Activity Report for Outage 2R27 | Through-Wall Leak Through Wall Leak |
NL-21-0646, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1R30 | 16 July 2021 | Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1R30 | |