MONTHYEARML24277A3062024-10-0303 October 2024 Restart La Docs - 9-18-2024 Michigan SHPO Comments on Palisades Phase I Archaeological Survey ML24277A3082024-10-0303 October 2024 Restart La Docs - 10-2-2024 Michigan SHPO Comments Re Palisades Nuclear Plant Architectural Survey ML24277A3042024-10-0303 October 2024 Restart La Docs - Sokaogon Chippewa Community Reply to NRC Status Update Re Palisades Restart ML24262A0732024-09-18018 September 2024 Restart La Docs - FW Palisades Scoping Comment Period Ended ...E-mail Capture Platform Status ML24262A0742024-09-18018 September 2024 Restart La Docs - FW Palisades Scoping Comment Period Ended ...E-mail Capture Platform Status ML24260A3552024-09-16016 September 2024 Restart La Docs - Palisades Reauthorization of Power Operations- Environmental Audit RCI Responses ML24248A2622024-09-0404 September 2024 Restart La Docs - FW Palisades Reauthorization of Power Operations- Environmental Audit Draft RCIs ML24248A2612024-09-0404 September 2024 Restart La Docs - Palisades Reauthorization of Power Operations- Environmental Audit Draft RCIs ML24248A0572024-09-0404 September 2024 Restart La Docs - Draft Letter in Support of Draft RAIs and Draft Environmental Regulatory Audit Plan ML24247A1602024-09-0303 September 2024 Kairos - Hermes 2 Docs - Final Environmental Assessment and Finding of No Significant Impact for Kairos Hermes 2 Test Reactors in Oak Ridge, Tennessee ML24213A3222024-07-30030 July 2024 NRR E-mail Capture - Fermi 2 Audit Questions from the Audit Team Supporting Review of the LAR to Adopt TSTF-505 ML24248A0562024-06-27027 June 2024 Restart La Docs - Draft Letter in Support of Draft RAIs and Draft Environmental Regulatory Audit Plan ML24166A2222024-06-14014 June 2024 Kairos - Hermes 2 Docs - FW FW (External) Re Fw Kairos Power Test Reactor NRC ML24138A1562024-05-17017 May 2024 Kairos - Hermes 2 Docs - Preliminary Chapter 5 of Hermes 2 SE to ACRS ML24138A2072024-05-17017 May 2024 Kairos - Hermes 2 Docs - Preliminary Chapter 13 of Hermes 2 SE to ACRS ML24137A2662024-05-15015 May 2024 Kairos - Hermes 2 Docs - Preliminary Chapter 9 of Hermes 2 SE to ACRS ML24120A0262024-04-29029 April 2024 COL Docs - FW Vogtle Electric Generating Plant, Unit 4 - Project Manager Reassignment ML24120A0462024-04-29029 April 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24119A0012024-04-28028 April 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24116A1622024-04-25025 April 2024 Kairos - Hermes 2 Docs - Draft Environmental Assessment and Finding of No Significant Impact for Kairos Hermes 2 Test Reactors in Oak Ridge, Tennessee ML24114A2802024-04-23023 April 2024 Kairos - Hermes 2 Docs - Preliminary Chapter of Hermes 2 SE to ACRS ML24114A2822024-04-23023 April 2024 Kairos - Hermes 2 Docs - Preliminary Chapter of Hermes 2 SE ML24113A2722024-04-22022 April 2024 Kairos - Hermes 2 Docs - Preliminary Chapter of Hermes 2 SE ML24105A0002024-04-14014 April 2024 Kairos - Hermes 2 Docs - Environmental Audit Summary Report for Hermes 2 ML24095A2922024-04-0404 April 2024 Kairos - Hermes 2 Docs - Preliminary Chapter of Hermes 2 SE ML24080A4502024-03-20020 March 2024 Kairos - Hermes 2 Docs - FW Kairos Power Test Reactor NRC ML24074A3712024-03-14014 March 2024 Kairos - Hermes 2 Docs - Preliminary Chapters of Hermes 2 SE ML24072A3162024-03-12012 March 2024 Kairos - Hermes 2 Docs - FW Transmittal of Responses to NRC Requests for Confirmatory Information for the Review of the Hermes 2 Environmental Report (Courtesy Copy) ML24059A3892024-02-28028 February 2024 Kairos - Hermes 2 Docs - Feb 28 2024 Ipac Updated Species List_ Tennessee Ecological Services Field Office (1).pdf ML24057A4222024-02-26026 February 2024 Kairos - Hermes 2 Docs - RCI Confirmation Message ML24051A2412024-02-20020 February 2024 Kairos - Hermes 2 Docs - Quick Question ML24051A2352024-02-20020 February 2024 Kairos - Hermes 2 Docs - FW HC-1 Status ML24046A1352024-02-15015 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Initial Criticality and Low-Power Testing ML24039A1122024-02-0808 February 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1922024-02-0808 February 2024 COL Docs - Correction - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A0882024-02-0808 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24030A9732024-01-30030 January 2024 Kairos - Hermes 2 Docs - RCI Preview for Hermes 2 Environmental Audit ML23331A9992023-11-27027 November 2023 COL Docs - Re Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23326A2802023-11-22022 November 2023 COL Docs - Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23320A0342023-11-16016 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23312A2632023-11-0808 November 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Monday, November 13, 2023 - Vogtle Units 3&4, LAR-22-002, TS 3.8.3, Inverters - Operating Completion Time Extension ML23311A1512023-11-0707 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23289A1362023-10-16016 October 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Friday, October 20, 2023 - Vogtle Units 3&4, LAR-23-006, Rev.1, More Restrictive Action for Tech. Spec. 3.1.9 ML23283A0332023-10-10010 October 2023 COL Docs - FW Vogtle Units 3 and 4 (LAR 23-009) ML23275A1002023-10-0202 October 2023 COL Docs - Re Action Summary of 9.27.23 Clarification Call with Southern Nuclear Company on LAR-22-0002, TS 3.8.3 Inverters - Operating Completion Time ML23274A0062023-10-0101 October 2023 Hermes CP Doc - Public Summary of Sep 14 Meeting with Consulting Tribe ML23270B1912023-09-27027 September 2023 COL Docs - Update Vogtle Units 3&4 Acceptance Letter for LAR-22-002 Technical Specification 3.8.3, Inverters Operating ML23263A1042023-09-20020 September 2023 COL Docs - FW Fyi for Tomorrow'S Psm Meeting ML23256A2682023-09-13013 September 2023 COL Docs - Acceptance Review of Southern Nuclear Operating Companys License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) 2024-09-04
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
From: Giacinto, Joseph Sent: Tuesday, May 25, 2021 2:05 PM To: AdvancedReactors-GEISDocsPEm Resource
Subject:
INL - INL HALEU Capabilities Attachments: Todd 2020 INL_Capabilities.pdf
INL HALEU Capabilities Terry Todd, Laboratory Fellow NEI/GAIN/EPRI HALEU Video Workshop April 28, 2020
Outline
- Recast- metal product
- Small-scale polishing- oxide product
- Headend treatment (ZIRCEX)
- Processing (pilot-scale and engineering-scale) 2
EBR-II Driver fuel processing Electrorefined uranium dendrite product Cast uranium product 3 ingot 3
Pyroprocessing - EBR II Driver Fuel Spent Driver Electrorefined Uranium Ingot
HALEU EBR-II Metal Feedstock Progress
- HALEU as metal from EBR-II is the nearest term feedstock available to support fast-spectrum advanced reactor concepts
- Processing of EBR-II driver fuel will continue until all driver fuel is processed
- Production of EBR-II HALEU reguli will continue until all EBR-II driver fuel has been treated
- Operations ramp up to 7 day/wk, 12 hr/day
- 0.365 MT produced in 2019
- 2nd furnace available 2020 - 1 MT/year
- 5 MT forecast to be available by 2024 Recovered U metal Large metallic ingot New graphite crucible Low dose rate, small size Novel Multi-function furnace HALEU metal regulus 5
HALEU EBR-II Oxide Feedstock Demonstration
- Polished EBR-II uranium product suitable for thermal spectrum reactors
- Demonstrated U Polishing in small-scale equipment (using equipment on-hand)
- Dissolution of EBR II uranium metal regulus
- Uranium purification from residual fission products by solvent extraction
- Precipitation of uranium using peroxide process
- Uranium oxide produced by calcination Uranyl Peroxide Uranium Oxide Low dose rate, small size Uranium Trioxide HALEU metal regulus U metal dissolution U purification 6
U metal regulus Uranyl Peroxide - UO2(O2).4H2O UO2 pellets EBR-II oxide product characteristics
- All metal species except uranium were below analytical detection limits
- Uranium isotopic analysis (same as metal)
- U-235: 19.77%
- U-238: 79.5 %
- U-234: 0.18%
- U-236: 0.55 %
- Dose rates (theoretical dose for unirradiated 20% U-235 HALEU) 8
Dry headend for zirconium or aluminum clad fuels 9
ZIRCEX Headend Progress
- Pilot plant operational on October 3, 2019
- Zirconium decladding testing initiated (10 completed runs to date)
- 2020 test schedule to include Zr and Al
- Receipt of unirradiated HEU fuel elements was completed in November 2019 Instantaneous and overall reaction rate with HCl gas and zirconium Zirconium sample after dry ZIRCEX decladding process Simulated Zircaloy-2 clad fuel
Process scale-up
- Design of pilot-scale processing glove box line for clean or lightly irradiated materials - in progress
- Dissolution/solvent extraction/
conversion/waste vitrification
- EBR-II product (19.7% HALEU)
- ZIRCEX pilot plant product (unirradiated HEU)
- Other fuel/orphan materials
- Engineering-scale demonstration conceptual design in progress
- Projected 1-2 MT/yr of HALEU based on EBR-II and ATR recycled fuels 11
Projected INL HALEU Production Rates HALEU Production 2
1.8 1.6 1.4 1.2 HALEU (MT) 1 0.8 0.6 0.4 0.2 0
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Year EBR II Production HZD Production 12
2021 - Planned Activities
- Continue processing EBR-II driver fuel
- Continue to recast previously processed EBR-II uranium product into reguli
- A total of 1 MT of HALEU reguli will be produced per year
- Complete testing of Zr and Al simulated fuels
- Initiate testing of unirradiated HEU fuel
- Complete design of pilot-scale glovebox line for polishing EBR-II product and ZIRCEX HEU product
- Complete conceptual design of Hybrid-ZIRCEX Engineering-Scale Demonstration
- Initiate NEPA (Environmental Assessment) for Hybrid-ZIRCEX Engineering-Scale Demonstration
- Complete construction of in-can vitrification pilot plant 13