Letter Sequence Acceptance Review |
---|
CAC:MF8844, Implement 10 CFR 50, Appendix J, Option B (Approved, Closed) |
|
MONTHYEARNL-16-1128, License Amendment Request to Revise Technical Specification Section 5.5.17 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2016-10-0404 October 2016 License Amendment Request to Revise Technical Specification Section 5.5.17 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies Project stage: Request NL-16-2335, Re-Submittal of License Amendment Request to Revise Technical Specification Section 5.5.17 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2016-11-15015 November 2016 Re-Submittal of License Amendment Request to Revise Technical Specification Section 5.5.17 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies Project stage: Request ML16340A1772016-12-0505 December 2016 NRR E-mail Capture - Joseph M. Farley, Units 1 and 2 - Acceptance of Requested Licensing Action Regarding TS 5.5.17, Extension of Type a and Type C Leak Rate Test Frequencies Project stage: Acceptance Review ML17058A1132017-03-15015 March 2017 Request for Additional Information Project stage: RAI NL-17-0480, License Amendment Request to Revise Technical Specification Section 5.5.17 Containment Leakage Rate Testing Program Responses to NRC Requests for Additional Information2017-06-22022 June 2017 License Amendment Request to Revise Technical Specification Section 5.5.17 Containment Leakage Rate Testing Program Responses to NRC Requests for Additional Information Project stage: Response to RAI ML17219A0012017-08-0303 August 2017 NRR E-mail Capture - Joseph M. Farley, Units 1 and 2 - Supplemental RAI Request No. 5(b), 5(c), and 6 Related to License Amendment Request to Revise TS 5.5.17 Containment Leakage Rate Testing Program Project stage: RAI NL-17-1443, License Amendment Request to Revise Technical Specification Section 5.5.17 Containment Leakage Rate Testing Program Final Response to NRC Requests for Additional Information2017-10-12012 October 2017 License Amendment Request to Revise Technical Specification Section 5.5.17 Containment Leakage Rate Testing Program Final Response to NRC Requests for Additional Information Project stage: Response to RAI ML17360A0552017-12-20020 December 2017 NRR E-mail Capture - Joseph M. Farley, Units 1 and 2 - Supplemental RAI Request No. 7 to License Amendment Request to Revise TS 5.5.17 Containment Leakage Rate Testing Program (CAC Nos. MF8844, MF8845; EPID No. L-2016-LLA-0015) Project stage: RAI NL-17-2135, License Amendment Request to Revise Technical Specification Section 5.5.17 Containment Leakage Rate Testing Program, Response to NRC Request for Additional Information2018-02-0909 February 2018 License Amendment Request to Revise Technical Specification Section 5.5.17 Containment Leakage Rate Testing Program, Response to NRC Request for Additional Information Project stage: Response to RAI ML17261A0872018-02-28028 February 2018 Issuance of Amendments to Revise Actions of TS 5.5.17, Containment Leakage Rate Testing Program (CAC Nos. MF8844 and MF8845; EPID No. L-2016-LLA-0015) Project stage: Approval 2017-12-20
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24304A8922024-10-30030 October 2024 Acceptance Review - Farley Units 1 and 2 - RG 1.183 Table 3 Footnote 11 Exception UFSAR Change LAR ML24297A6042024-10-22022 October 2024 Acceptance Review - License Amendment Request to Revise TS SR 3.4.14.3 and Correct Admin Oversight ML24290A1572024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds (L-2024-LLR-0047) ML24290A1552024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley, Hatch, and Vogtle 1 and 2 - Proposed Alternative Request for Code Case N-572 ML24276A1132024-10-0202 October 2024 Acceptance Review - License Amendment Request to Revise TS SR 3.4.14.3 and Correct Administrative Oversight ML24271A0052024-09-26026 September 2024 NRR E-mail Capture - for Your Response - RAI - Farley and Vogtle 1 and 2 - Proposed Alternative Request for Steam Generator Welds (L-2024-LLR-0041) ML24227A0512024-08-14014 August 2024 August 14, 2024 - Request for Additional Information - Farley, Units 1 and 2 - Proposed LAR to Revise TS SR 3.6.6.8 Frequency ML24212A2232024-07-30030 July 2024 Acceptance Review - License Amendment Request to Adopt TSTF-500, Rev 2 DC Electrical Rewrite (EPID L-2024-LLA-0091) - Email ML24205A2142024-07-23023 July 2024 Acceptance Review - License Amendment Request to Change TS 3.6.5, Containment Air Temperature ML24197A1572024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Farley and Vogtle 1 and 2, LAR - TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24197A0172024-07-12012 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds ML24194A0032024-07-11011 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley, Hatch, and Vogtle 1 and 2 - Alternative Request for Code Case N-572 ML24180A0012024-06-26026 June 2024 NRR E-mail Capture - Acceptance Review Farley 1 and 2 and Vogtle 1 and 2 - Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) (L-2024-LLR-0041) ML24170A9362024-06-18018 June 2024 NRR E-mail Capture - Fyi - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24142A4992024-05-21021 May 2024 NRR E-mail Capture - Acceptance Review - Farley and Hatch - LAR to Revise TS 1.1 and Add Online Monitoring (OLM) Program (L-2024-LLA-0058) ML24114A2452024-04-23023 April 2024 Acceptance Review - Farley, Units 1 and 2-Proposed LAR to Revise TS SR 3.6.6.8 ML24037A1352024-02-0505 February 2024 E-mail ML23335A0122023-12-0101 December 2023 FNP - IP95001 Inspection Notification and Request for Information (Email to Farley) ML23243A9952023-08-31031 August 2023 Request for Baseline RP Inspection ML23236A0022023-08-22022 August 2023 NRR E-mail Capture - Request for Additional Information - Farley, Units 1&2, Emergency TS 3.6.5 LAR ML23223A0142023-08-10010 August 2023 NRR E-mail Capture - Acceptance Review - SNC Fleet Exemption to 10 CFR 73.2, Physical Barriers ML23198A1552023-07-17017 July 2023 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Hatch, Farley, and Vogtle, Units 1 and 2 Quality Assurance Topical Report (QATR) Submittal Dated June 15, 2023 ML23135A0922023-05-11011 May 2023 NRR E-mail Capture - Acceptance Review - SNC Fleet Request to Use Specific Provision of a Later Edition of the ASME BPV Code, Section XI (L-2023-LLR-0016) ML23095A0832023-04-0505 April 2023 NRR E-mail Capture - for Your Action - RAI - Farley - Containment Isolation Valves, Surveillance Requirement 3.6.3.5 LAR (L-2022-LLA-0189) ML23086A0232023-03-24024 March 2023 NRR E-mail Capture - for Your Action - Draft RAIs - Farley Surveillance Requirement (SR) 3.6.3.5 License Amendment Request (LAR) (L-2022-LLA-0189) ML23073A0252023-03-13013 March 2023 NRR E-mail Capture - Fyi - Closeout the Evacuation Time Estimate (ETE) Reviews for SNC Fleet ML23045A0782023-02-13013 February 2023 NRR E-mail Capture - Fyi - Revised Estimated Hours - Farley - TS 3.4.10 LAR, Psv Setpoint (L-2022-LLA-0098) ML23009A0062023-01-0606 January 2023 NRR E-mail Capture - Corrected - Acceptance Review - Farley Surveillance Requirement (SR) 3.6.3.5 LAR ML23009A0152023-01-0606 January 2023 NRR E-mail Capture - Acceptance Review - Farley Surveillance Requirement (SR) 3.6.3.5 LAR ML23003A8092023-01-0303 January 2023 NRR E-mail Capture - for Your Action - RAI - Farley - ISI Alternative FNP-ISI-ALT-05-05 (L-2022-LLR-0068) ML22354A0112022-12-19019 December 2022 NRR E-mail Capture - Acceptance Review - Requested Licensing Action Regarding TS Revision to Adopt WCAP-17661-P-A, Improved Relaxed Axial Offset Control and Constant Axial Offset Control Fq Surveillance TS (L-2022-LLA-0148 and L-2022-LLA-01 ML22334A1482022-11-30030 November 2022 NRR E-mail Capture - for Your Action - RAI - Farley - TS 3.4.10 LAR, Psv Setpoint (L-2022-LLA-0098) ML22285A2532022-10-12012 October 2022 NRR E-mail Capture - Acceptance Review - Farley Proposed Inservice Inspection Alternative FNP-ISI-ALT-05-05, Version 1.0 ML22285A0082022-10-11011 October 2022 NRR E-mail Capture - Acceptance Review - Farley TS 4.3 LAR (L-2022-LLA-0138) ML22229A4792022-08-15015 August 2022 HP Baseline Inspection Document Request ML22213A2692022-08-0101 August 2022 NRR E-mail Capture - Joseph M. Farley Nuclear Plant Units 1 and 2 - Acceptance of Requested Licensing Action Revise Technical Specification 3.4.10, Pressurizer Safety Valves ML22123A1782022-05-0303 May 2022 NRR E-mail Capture - RAIs for Farley LAR Re. TS 5.5.17 Containment Leakage Rate Testing Program ML22123A1802022-05-0303 May 2022 NRR E-mail Capture - Correction - RAIs for Farley LAR Re. TS 5.5.17 Containment Leakage Rate Testing Program ML22112A0892022-04-22022 April 2022 NRR E-mail Capture - Draft RAIs for Farley LAR Re. TS 5.5.17 ML22104A1312022-04-14014 April 2022 NRR E-mail Capture - Request for Additional Information - Farley and Vogtle - Relocate Piping Inspection License Amendment Request (L-2021-LLA-0235) ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML22020A0662022-01-13013 January 2022 NRR E-mail Capture - Acceptance Review - Farley and Vogtle TSTF-269-A LAR (L-2021-LLA-0234) ML22012A0632022-01-11011 January 2022 NRR E-mail Capture - Acceptance Review - Farley and Vogtle TS 5.5.16 LAR (L-2021-LLA-0235) ML22010A2402022-01-10010 January 2022 NRR E-mail Capture - Farley 1 and 2 - Acceptance of Requested Licensing Action Revise TS 5.5.17, Containment Leakage Rate Testing Program to Increase Calculated Peak Containment Pressure ML21321A3772021-11-16016 November 2021 NRR E-mail Capture - RAIs for Farley LAR Sump Recirculation Valve Encapsulation Vessel Removal ML21321A3752021-11-10010 November 2021 NRR E-mail Capture - Draft RAIs for Farley LAR Sump Recirculation Valve Encapsulation Vessel Removal ML21292A1562021-10-19019 October 2021 NRR E-mail Capture - Acceptance Review - SNC Operating Fleet TSTF-554 LAR ML21274A0462021-10-0101 October 2021 NRR E-mail Capture - Acceptance Review - Farley and Vogtle TSTF-577 LAR (L-2021-LLA-0163) ML21236A3142021-08-24024 August 2021 NRR E-mail Capture - Joseph M. Farley Nuclear Plant Units 1 and 2 - Acceptance of Requested Licensing Action Amendment to Remove Sump Recirculation Valve Encapsulation ML21180A2002021-06-28028 June 2021 NRR E-mail Capture - Acceptance Review - Farley and Vogtle - Voluntary License Amendment Request to Use Beacon Power Distribution Monitoring System (L-2021-LLA-0109) 2024-09-26
[Table view] |
Text
NRR-PMDAPEm Resource From: Williams, Shawn Sent: Monday, December 05, 2016 9:51 AM To: 'gkmcelro@southernco.com' Cc: Coleman, Jamie Marquess
Subject:
Joseph M. Farley, Units 1 and 2 - Acceptance of Requested Licensing Action regarding TS 5.5.17, Extension of Type A and Type C Leak Rate Test Frequencies (CAC Nos.
MF8844and MF8845)
Dear Mr. McElroy,
By letter dated November 15, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16320A540), the Southern Nuclear Operating Company, Inc., (SNC) submitted an amendment request to revise the Joseph M. Farley Nuclear Plant, Unit 1 and Unit 2, Technical Specifications. The November 22, 2016, application replaced in its entirety the October 4, 2016 application (ADAMS Accession No. ML16280A294). Specifically, the proposed change is a request to revise TS 5.5.17 "Containment Leakage Rate Testing Program" to allow the following:
- Increase in the existing Type A integrated leakage rate test (ILRT) program test interval from 10 years to 15 years in accordance with Nuclear Energy Institute (NEI) Topical Report NEI 94-01, Revision 3-A and the conditions and limitations specified in NEI 94-01, Revision 2-A.
- Adopt an extension of the containment isolation valve (CIV) leakage testing (Type C) frequency from the 60 months currently permitted by 1 O CFR 50, Appendix J, Option B, to a 75-month frequency for Type C leakage rate testing of selected components, in accordance with NEI 94-01, Revision 3-A.
- Adopt the use of American National Standards Institute/American Nuclear Society (ANSI/ANS) 56.8-2002, Containment System Leakage Testing Requirements.
- Adopt a more conservative grace interval of 9 months, for Type A, Type B and Type C leakage tests in accordance with NEI 94-01, Revision 3-A.
The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. The application made numerous references to updating the Probabilistic Risk Assessment (PRA) model to credit the Generation III RCP [Reactor Coolant Pump] seals after Topical Report PWROG-14001-P/NP, Revision 1, "PRA Model for the Westinghouse Shutdown Seal" (Topical Report) is approved. However, at this time, the Topical Report is not yet approved, therefore the NRC will review the application without consideration of the Topical Report. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are 1
identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 490 hours20.417 days <br />2.917 weeks <br />0.671 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager. These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.
If you have any questions, please contact me at (301) 415-1009.
Shawn Williams, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-348 and 50-364 2
Hearing Identifier: NRR_PMDA Email Number: 3198 Mail Envelope Properties (8f837aea24254b14afc97c402b11fbfb)
Subject:
Joseph M. Farley, Units 1 and 2 - Acceptance of Requested Licensing Action regarding TS 5.5.17, Extension of Type A and Type C Leak Rate Test Frequencies (CAC Nos.
MF8844and MF8845)
Sent Date: 12/5/2016 9:50:46 AM Received Date: 12/5/2016 9:50:46 AM From: Williams, Shawn Created By: Shawn.Williams@nrc.gov Recipients:
"Coleman, Jamie Marquess" <JAMIEMCO@SOUTHERNCO.COM>
Tracking Status: None
"'gkmcelro@southernco.com'" <gkmcelro@southernco.com>
Tracking Status: None Post Office: HQPWMSMRS03.nrc.gov Files Size Date & Time MESSAGE 5106 12/5/2016 9:50:46 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: