MONTHYEARML24303A0712024-11-0404 November 2024 Letter to K. Meshigaud, Chairperson Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1422024-11-0101 November 2024 Letter to V. Jefferson, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1442024-11-0101 November 2024 Letter to V. Kitcheyna, Chairwoman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0152024-11-0101 November 2024 Letter to C. Harper, Chief Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0492024-11-0101 November 2024 Letter G. Kakkak, Chairwoman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0302024-11-0101 November 2024 Letter to D.G. Lankford, Chief Request to Initiate Section 106 Consultation for SLR of DNP Station RS-24-104, Nuclear Radiological Emergency Plan Document Revision2024-11-0101 November 2024 Nuclear Radiological Emergency Plan Document Revision ML24303A0272024-11-0101 November 2024 Letter to D. Rios, Chairperson Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0512024-11-0101 November 2024 Letter to J. Barrett, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station IR 05000237/20254012024-11-0101 November 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000237/2025401 05000249/2025401 ML24303A0172024-11-0101 November 2024 Letter to B. Peters, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0472024-11-0101 November 2024 Letter to G. Cheatham, Chairwoman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1462024-11-0101 November 2024 Letter to W. Gravelle, Chairperson Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0132024-11-0101 November 2024 Letter to B. Barnes, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1342024-11-0101 November 2024 Letter to T. Carnes, Chairperson Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1172024-11-0101 November 2024 Letter to R. Yob, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24291A0252024-11-0101 November 2024 Letter to R. Blanchard Tribal Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0692024-11-0101 November 2024 Letter to J.A. Crawford, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1352024-11-0101 November 2024 Letter to T. Rhodd, Chairperson Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0642024-11-0101 November 2024 Letter to J. Rupnick, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0432024-11-0101 November 2024 Letter to E. Elizondo, Sr. Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0892024-11-0101 November 2024 Letter to M. J. Wesaw, Chair Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0602024-11-0101 November 2024 Letter to J. R. Shotton, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0992024-11-0101 November 2024 Lett to R. Carter, Principal Chief Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0532024-11-0101 November 2024 Letter to J. Greendeer, President Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A1102024-11-0101 November 2024 Letter to R. Gasco, Chairperson Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0202024-11-0101 November 2024 Letter to C. Chavers, Chairwoman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0552024-11-0101 November 2024 Letter to J. Keys, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24303A0242024-11-0101 November 2024 Letter to D. Kaskaske, Chairman Request to Initiate Section 106 Consultation for SLR of DNP Station ML24291A0272024-10-31031 October 2024 NRC Letter to C. Mayer Illinois SHPO Request to Initiate Section 106 Consultation for Subsequent License Renewal of Units 2 and 3 ML24291A0202024-10-31031 October 2024 NRC Letter to J. Loichinger Achp Request for Comments Concerning the Environmental Review of DNPS Units 2 and 3 Subsequent License Renewal Application IR 05000237/20240032024-10-29029 October 2024 Integrated Inspection Report 05000237/2024003 and 05000249/2024003 RS-24-103, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-10-21021 October 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-24-102, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-5912024-10-21021 October 2024 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-591 RS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24225A2132024-09-26026 September 2024 Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval ML24253A0942024-09-23023 September 2024 License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application (EPID L-2024-Sle-0002) (Docket Numbers: 50-237 and 50-249) SVPLTR 24-0030, ISFSI Annual Effluent Release Report2024-09-20020 September 2024 ISFSI Annual Effluent Release Report ML24270A0332024-09-20020 September 2024 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report IR 05000237/20244022024-09-19019 September 2024 – Security Baseline Inspection Report 05000237/2024402 and 05000249/2024402 - (Public) ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24260A2152024-09-16016 September 2024 Confirmation of Initial License Examination ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000237/20230052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2023005; 05000249/2024005) ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000237/20240022024-08-14014 August 2024 Integrated Inspection Report 05000237/2024002 and 05000249/2024002 ML24215A2912024-08-14014 August 2024 Request for Withholding Information from Public Disclosure Alternative Schedule to Complete Decommissioning Beyond 60-Years of Permanent Cessation of Operations 2024-09-06
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24066A0872024-03-0404 March 2024 NRR E-mail Capture - Dresden 2 and 3 - Request for Additional Information for Alternative Request I5R-22 ML24067A1242024-03-0101 March 2024 Email to Christian Williams: Request for Additional Information Regarding Dresden Relief Request Dated February 23, 2024 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC Fleet Request License Amendment Request to Adopt TSTF-580, Revision 1 ML23187A0462023-07-0606 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2023004 ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23052A0652023-02-21021 February 2023 NRR E-mail Capture - Dresden Units 2 and 3 - Request for Additional Information for Alternative Request RV-23H ML23037A9192023-02-0707 February 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000237/2023011 and 05000249/2023011 ML23019A0132023-01-12012 January 2023 NRR E-mail Capture - Final RAI Dresden 2 and 3 - License Amendment Pertaining to GNF3 Fuel Transition ML22290A0842022-10-13013 October 2022 NRR E-mail Capture - Dresden 2 and 3 - RAI License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies ML22270A1032022-09-27027 September 2022 Notification of NRC Baseline Inspection and Request for Information (05000249/2022004) ML22203A0442022-07-21021 July 2022 Request for Additional Information (RAI) ML22199A2422022-07-13013 July 2022 NRR E-mail Capture - Draft RAI Dresden 2 and 3 Proposed Alternative Related to Sblc Nozzle Inspection for the Sixth Inservice Inspection Interval ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21244A4012021-08-10010 August 2021 (Final) Request for Information (RAI) Dresden, Units 1, 2, 3, and ISFSI Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR 50 Appendix E ML21190A0192021-07-0808 July 2021 NRR E-mail Capture - Exelon Fleet - Request for Additional Information Regarding Adoption of TSTF-582 and TSTF-583-T ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21097A2602021-04-0808 April 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21096A1752021-04-0606 April 2021 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000237/2021011; 05000249/2021011 ML21063A3202021-03-0202 March 2021 RAIs for Dresden, Units 2 and 3, Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition (EPID L-2020-LLA-0239) (E-mail) ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML20337A4242020-12-0202 December 2020 Information Request for the Cyber-Security Full Implementation Inspection, Notification to Perform Inspection 05000237/2021401 and 05000249/2021401 ML20239A7982020-08-25025 August 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet License Amendment Request to Adopt TSTF-568, Revision 2 ML20231A7432020-08-18018 August 2020 Request for Additional Information (IOLB/HFT-RAI-1) Dresden MSIV LAR ML20224A3532020-08-11011 August 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000249/2020004 ML20135H1972020-05-14014 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Extend Safety Relief Valve Test Interval ML20094H0292020-03-27027 March 2020 Final: Dresden, Units 2 & 3 LAR Request for Additional Information to Modify Technical Specifications to Main Steam Isolation Valve Leakage Requirements ML20071G2242020-03-11011 March 2020 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML19330E1772019-11-25025 November 2019 RAI Dresden/Clinton Request for LAR to Modify TSs Following Adoption of TSTF-542 ML19226A3712019-08-14014 August 2019 Ltr. 08/14/19 Dresden Nuclear Power Station, Unit 2 - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2019004 (DRS-M.Domke) ML18330A2382018-11-21021 November 2018 Initial Information Request (Part 1) for the Upcoming Phase IV License Renewal Inspection; Inspection Report 05000237(249)/2019010; E-Mailed 11/21/18 (DRS-J.Corujo-Sandin) ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML17353A9492018-01-0909 January 2018 Supplemental Information Needed for Acceptance of License Amendment Request to Revise Technical Specification Requirements for Secondary Containment ML18002A4572017-12-22022 December 2017 NRR E-mail Capture - (External_Sender) (External) Dresden Nuclear Power Station, Units 2 and 3 - RAIs to Support Request to Revise TS 5.5.12 Primary Containment Leakage Rate Testing Program ML17360A0082017-12-22022 December 2017 NRR E-mail Capture - Dresden Nuclear Power Station, Units 2 and 3 - RAIs to Support Request to Revise TS 5.5.12 Primary Containment Leakage Rate Testing Program ML17363A4422017-12-21021 December 2017 Supplemental Request for Information for 50.59 Inspection (DRS-A.Shaikh) ML17342A7372017-12-0808 December 2017 NRR E-mail Capture - Dresden Nuclear Power Station, Units 2 and 3 - Draft RAIs to Support Request to Revise TS 5.5.12 Primary Containment Leakage Rate Testing Program ML17191A2582017-07-11011 July 2017 RAI Related to License Amendment Request to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler-542, Revision 2 (CAC NOS.MF9295 and MF9296) ML17159A6292017-06-0707 June 2017 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML17062A4912017-03-0303 March 2017 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative to RPV Threads in Flange Examination (CAC Nos. MF8712-MF8729) ML16308A1002016-11-10010 November 2016 Request for Additional Information Regarding License Amendment Request to Revise Secondary Containment Access Opening Requirements (Cac. No. MF7325-MF7330) ML16208A0282016-07-25025 July 2016 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000249/2016004 (LAS) ML16172A1112016-06-29029 June 2016 Request for Additional Information Regarding License Amendment Request to Revise Secondary Containment Access Opening Requirements(Cac Nos.MF7325-MF7330) ML16153A2812016-06-0808 June 2016 Request for Additional Information Related to the License Amendment Request to Increase the Minimum Required Fuel Oil in Each Standby Diesel Generator Fuel Oil Day Tank (CAC Nos. MF7158 and MF7159) ML16071A2062016-03-15015 March 2016 RAI Regarding License Amendment Request to Revise the Reactor Steam Dome Pressure in Technical Specification 2.1.1, Reactor Core Sls(Cac Nos. MF6640 & MF6644) ML15329A2462016-01-19019 January 2016 Request for Additional Information Related to the License Amendment Request to Transition to Areva Fuel ML15232A6702015-09-29029 September 2015 Request for Additional Information Related to Dresden Units 2 and 3 License Amendment Request for Spent Fuel Storage Criticality Methodology 2024-05-21
[Table view] |
Text
January 9, 2008
Mr. Charles G. Pardee Chief Nuclear Officer and Senior Vice President Exelon Generation Company, LLC 4300 Winfield Road Warrenville IL 60555
SUBJECT:
INFORMATION REQUEST TO SUPPORT UPCOMING PROBLEM IDENTIFICATION AND RESOLUTION (PI&R) INSPECTION
Dear Mr. Pardee:
This letter is to request information to support our PI&R inspection beginning March 10, 2008, at the Dresden Nuclear Power Station, Units 2 and 3. This inspection will be performed in accordance with the NRC baseline Inspection Procedure 71152.
Experience has shown that these inspections are extremely resource intensive both for the NRC inspectors and the utility staff. In order to minimize the impact that the inspection has on the site and to ensure a productive inspection, we have enclosed a list of documents required for the inspection.
The documents requested are copies of performance reports and lists of information, necessary to ensure the inspection team is adequately prepared for the inspection. The information may be provided in either CD-ROM or hard copy format and should be ready for NRC review by February 22, 2008. Mr. Allan Barker, the Lead Inspector, will contact you to determine the best method of providing the requested information.
If there are any questions about the material requested, or the inspection in general, please do not hesitate to call Mr. Barker at 630-829-9679 or ARB3@nrc.gov.
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public
C. Pardee Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/ Mark A. Ring, Chief Branch 1 Division of Reactor Projects Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25
Enclosure:
Requested Information to Support PI&R Inspection cc w/encl: Site Vice President - Dresden Nuclear Power Station Plant Manager - Dresden Nuclear Power Station Regulatory Assurance Manager - Dresden Nuclear Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden, and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer Chairman, Illinois Commerce Commission
C. Pardee Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely, Mark A. Ring, Chief Branch 1 Division of Reactor Projects Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25
Enclosure:
Requested Information to Support PI&R Inspection cc w/encl: Site Vice President - Dresden Nuclear Power Station Plant Manager - Dresden Nuclear Power Station Regulatory Assurance Manager - Dresden Nuclear Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden, and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer Chairman, Illinois Commerce Commission
DOCUMENT NAME: G:\Dresden\PI&R input Dresden 2008.doc To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII E RIII NAME ABarker:dtp MRing DATE 01/09/08 01/09/08 OFFICIAL RECORD COPY
Letter to C. Pardee from M. Ring dated January 9, 2008
SUBJECT:
INFORMATION REQUEST TO SUPPORT UPCOMING PROBLEM IDENTIFICATION AND RESOLUTION (PI&R) INSPECTION DISTRIBUTION:
TEB RAG1 CXG1 RidsNrrDirsIrib MAS KGO JKH3 CJP3 DRPIII DRSIII PLB1 TXN
Requested Information for a Problem Identification and Resolution (PI&R) Inspection
- 1. A copy of administrative procedure(s) for the corrective action process, trending program, quality assurance audit program, self-assessment program, corrective action effectiveness review program, and industry experience review program.
- 2. A copy of the Employee Concerns Program/Ombudsman administrative procedure.
- 3. A list of Quality Assurance audits completed since February 2006 with brief description of areas where findings were identified.
- 4. A copy of Quality Assurance audits and/or self-assessments of the corrective action program completed since February 2006.
- 5. A list of self-assessments completed since February 2006.
- 6. A list of root cause evaluations completed since February 2006.
- 7. A list of test failures (IST or Technical Specifications surveillances) since February 2006, with a brief description of component/system which failed.
- 8. A list of all open condition reports sorted by significance level and then initiation date. Include the date initiated, a description of the issue, and the significance level.
- 9. A list of condition reports closed since February 2006 sorted by significance level and then initiation date. Include a description, the significance level, the date initiated and closed, and whether there was an associated operability evaluation.
- 10. A list of condition reports initiated since February 2006 that involve inadequate or ineffective corrective actions. Include the date initiated, a brief description, status, and significance level of the issue.
- 11. A list of condition reports initiated since February 2006 that identify trends of conditions adverse to quality. Include the date initiated, a brief description, status, and significance level for each item.
- 12. A copy of any performance reports for the past two years used to track the corrective action program effectiveness.
- 13. A list of condition reports issued during the past two refueling outages sorted by system and component, including a brief description, status, and significant level for each item.
- 14. A list of Maintenance Rule (a)(1) systems and components, and the associated health reports since February 2006.
- 15. Copies of corrective actions taken for issues identified in NRC findings.
- 16. A list of Corrective Action Program routine meeting times and places.
- 17. A list of the top ten risk significant systems and top ten risk significant components.
- 18. A copy of the most recent operating experience program effectiveness review.
- 19. A copy of any Corrective Action Program trend reports for the past two years.