ML090430135

From kanterella
Revision as of 02:26, 12 July 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search

Response to Request for Additional Information in Regard to Proposed Technical Specifications (TS) Amendment, TS 5.5.9, Steam Generator (SG) Program, TS 5.6.8, Steam Generator (SG) Tube Inspection Report
ML090430135
Person / Time
Site: Catawba Duke Energy icon.png
Issue date: 02/05/2009
From: Morris J
Duke Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML090430135 (6)


Text

Duke EEnergyo Carolinas JAMES R. MORRIS, VICE PRESIDENT Duke Energy Carolinas, LLC Catawba Nuclear Station 4800 Concord Road / CN01 VP York, SC 29745 803-701-4251 803-701-3221 fax February 5, 2009 U.S. Nuclear Regulatory Commission Attention:

Document Control Desk Washington, D.C. 20555

Subject:

Duke Energy Carolinas, LLC (Duke)Catawba Nuclear Station, Unit 2 Docket Number 50-414 Proposed Technical Specifications (TS) Amendment TS 5.5.9, "Steam Generator (SG) Program" TS 5.6.8, "Steam Generator (SG) Tube Inspection Report"

Reference:

Letter from Duke to NRC, same subject, dated November 13, 2008 The reference letter requested an amendment to Catawba Facility Operating License NPF-52 and the subject TS. The amendment request proposed a one-cycle revision to the subject TS to incorporate an Interim Alternate Repair Criterion (IARC) in the provisions for SG tube repair criteria during the End of Cycle 16 Refueling Outage and subsequent Cycle 17 operation.

This change is supported by Westinghouse Electric Company LLC, LTR-CDME-08-11, Rev. 3,"Interim Alternate Repair Criterion (ARC) for Cracks in the Lower Region of the Tubesheet Expansion Zone", and LTR-CDME-08-43, Rev. 3, "Response to NRC Request for Additional Information Relating to LTR-CDME-08-11, Rev. 3, P-Attachment".

On February 2, 2009, a Request for Additional Information (RAI) was electronically transmitted from the NRC to Duke regarding-the reference amendment request. The purpose of this letter is to respond to this RAI. Our response is contained in the attachment to this letter.The original regulatory and environmental analyses supporting the amendment request are not impacted by this RAI response.4co/-)AJ4m www. duke-energy, corn U.S. Nuclear Regulatory Commission Page 2 February 5, 2009 There are no new NRC commitments contained in this letter or its attachment.

Pursuant to 10 CFR 50.91, a copy of this letter and its attachment is being sent to the designated official of the State of South Carolina.Inquiries on this matter should be-directed to L.J. Rudy at (803) 701-3084.Very truly yours, James. R.. Morris LJR/s Attachment f l U.S. Nuclear Regulatory Commission Page 3 February 5, 2009 James R. Morris affirms that he is the person who subscribed his. name to the. foregoing statement.,, and that all the matters and facts set forth herein are true and correct to the best of his knowledge.

...Jame .Morris, Vice President Subscribed and sworn to me: Date My. commission expires: Date U III N" SEAL U.S. Nuclear Regulatory Commission Page 4 February 5, 2009 xc (with attachment)-

L.A. Reyes U.S. Nuclear Regulatory Commission Regional Administrator, Region II Atlanta Federal Center 61 Forsyth St.,.SW, Suite 23T85 Atlanta, GA 30303'A.T. Sabisch Senior Resident Inspector (CNS)U.S. Nuclear Regulatory Commission Catawba Nuclear Station J.H. Thompson (.addressee only)NRC Project Manager (CNS)U.S. Nuclear Regulatory Commission One White Flint North, Mail Stop 8-G9A 11555 Rockville Pike Rockville, MD 20852-2738 S.E. Jenkins Se6tion Manager Division of Waste Management South Carolina Department of Health and Environmental Control 2600 Bull St.Columbia, SC 29201 ATTACHMENT RESPONSE TO NRC REQUEST FOR ADDITIONAL INFORMATION REQUEST FOR ADDITIONAL INFORMATION RELATING TO STEAM GENERATOR TUBESHEET AMENDMENT ON INTERIM ALTERNATE REPAIR CRITERIA CATAWBA NUCLEAR STATION, UNIT 2 The NRC staff has the following request for additional information related to your submittal:

1. On page 14 of Attachment 1 to the November 13, 2008, letter, you state that a ratio [a leakage factor ratio]of 2.5 will be used for both the condition monitoring (CM) and the operational assessment (OA) upon implementation of the interim alternate repair criteria (IARC). In a public meeting held on January 9, 2009 (summary located in ADAMS under Accession No.ML090140510), Westinghouse presented revised information on how leakage factor ratios should be calculated.

This revision may have an impact on the leakage factor ratio that is used at Catawba Nuclear Station, Unit 2. If so, please provide an update to the calculated leakage factor ratio and the calculation used to support the new leakage factor ratio.Note: The leakage factor ratio used for Catawba Nuclear Station, Unit 2 needs to be submitted with the license amendment request as a formal regulatory commitment.

Duke Response: In a public meeting held on January 9, 2009 at the NEI offices in Washington, D.C., an updated leakage factor analysis was presented and provided to the NRC staff in Westinghouse letter LTR-SGMP-09-2 (proprietary and non-proprietary), together with the appropriate Affidavit for Withholding.

The most recent analysis concludes that a leakage factor of 2 is bounding for all plants considered candidates for the IARC and the permanent H*. Therefore, the factor of 2.5 contained in the technical support document for the IARC (which was previously licensed by the NRC) conservatively bounds the justifiable leakage factor for all normal operating and design basis accident conditions contained in the current licensing basis for Catawba Unit 2. Based on the most current analysis results, no additional action is required, since Duke has already proposed a leakage factor ratio of 2.5 as a license condition in our November 13, 2008 letter.1