MONTHYEARML0807806002008-03-25025 March 2008 Acceptance for Review of Nuclear Energy Institute Topical Report Material Reliability Program Project stage: Acceptance Review ML0809402802008-04-0707 April 2008 Request for Additional Information, Topical Report Material Reliability Program (Mrp): Technical Basis for Preemptive Weld Overlays for Alloy 82/182 Butt Welds in Pressurized Water Reactors (MRP-169) Project stage: RAI ML0912105492009-05-13013 May 2009 Request for Additional Information (RAI) Regarding Nuclear Energy Institute Topical Report Material Reliability Program (MRP) Technical Basis for Preemptive Weld Overlays for Alloy 82/182 Butt Welds in Pressurized Water Reactors (MRP-169) Project stage: RAI ML0923700952009-08-28028 August 2009 Request for Additional Information Nuclear Energy Institute Topical Report Material Reliability Program (Mrp): Technical Basis for Preemptive Weld Overlays for Alloy 82/182 Butt Welds in Pressurized Water Reactors (MRP-169), (MRP-169) (TAC Project stage: RAI ML1007404662010-03-25025 March 2010 Cover Letter: Draft Safety Evaluation for Nuclear Energy Institutes Topical Report Materials Reliability Program (Mrp): Technical Basis for Preemptive Weld Overlays for Alloy 82/182 Butt Welds in Pressurized Water Reactors (MRP-169)- Project stage: Draft Approval ML1016604682010-08-0909 August 2010 Final Safety Evaluation by the Office of Nuclear Reactor Regulation Topical Report Materials Reliability Program (Mrp): Technical Basis for Preemptive Weld Overlays for Alloy 82/182 Butt Welds in Pwrs (MRP-169). Project stage: Approval ML1016200102010-08-0909 August 2010 Final Safety Evaluation for Nuclear Energy Institute Topical Report Materials Reliability Program (Mrp): Technical Basis for Preemptive Weld Overlays for Alloy 82/182 Butt Welds in Pressurized Water Reactors (MRP-169) Project stage: Approval NL-12-0403, Exigent Technical Specification Revision Request for TS 3.5.4 Refueling Water Storage Tank (RWST)2012-02-28028 February 2012 Exigent Technical Specification Revision Request for TS 3.5.4 Refueling Water Storage Tank (RWST) Project stage: Request ML12053A1452012-02-29029 February 2012 FRN - Joseph M. Farley Nuclear Plant, Units 1 and 2 - Individual Notice of Consideration Project stage: Other ML12053A1442012-02-29029 February 2012 Letter - Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing Project stage: Other NRC-2012-0053, FRN - Joseph M. Farley Nuclear Plant, Units 1 and 2 - Individual Notice of Consideration2012-02-29029 February 2012 FRN - Joseph M. Farley Nuclear Plant, Units 1 and 2 - Individual Notice of Consideration Project stage: Other NL-12-0462, Additional Information Regarding the Exigent Technical Specification Revision Request for TS 3.5.4 Refueling Water Storage Tank (RWST)2012-03-0202 March 2012 Additional Information Regarding the Exigent Technical Specification Revision Request for TS 3.5.4 Refueling Water Storage Tank (RWST) Project stage: Request NL-12-0545, Information Regarding Manual Action in Support of Exigent Technical Specification Revision Request for TS 3.5.4 - Refueling Water Storage Tank (RWST)2012-03-0909 March 2012 Information Regarding Manual Action in Support of Exigent Technical Specification Revision Request for TS 3.5.4 - Refueling Water Storage Tank (RWST) Project stage: Request ML1207306102012-03-24024 March 2012 Issuance of Amendment Regarding Water Storage Tank Project stage: Approval 2010-08-09
[Table View] |
|
---|
Category:Letter
MONTHYEARML24304A3482024-10-29029 October 2024 10-29-24 NEI Letter to NRC Status and Way Forward on NEI 99-04 Revision 1 ML24274A3112024-09-30030 September 2024 Request for NRC Review and Endorsement of NEI 99-01, Development of Emergency Action Levels for Non-Passive Reactors, Revision 7 ML24255A0702024-09-0909 September 2024 09-09-24_NRC_Industry Timeliness Request Regarding Items Relied Upon for Safety ML24204A2162024-07-22022 July 2024 Withdrawal of Fee Exemption Request for Endorsement of NEI White Paper, Selection of a Seismic Scenario for an EPZ Boundary Determination ML24204A2082024-07-22022 July 2024 07-22-24_NRC_NEI Withdrawal of Fee Exemption Request for Wp Selection of Seismic Scenario for EPZ Determination ML24187A0552024-07-0303 July 2024 Fee Exemption Request for NEI White Paper Selection of Seismic Scenario for EPZ Determination ML24184C1212024-07-0202 July 2024 NEI - Request for NRC Endorsement of NEI 24-05 Revision 0, an Approach for Risk-Informed Performance-Based Emergency Planning ML24173A2712024-06-14014 June 2024 NEI - Proposed Changes to Inspection Procedure (IP) 71130.10, Cybersecurity ML24165A0862024-06-13013 June 2024 NEI White Paper - Proposed Control Room Dose Acceptance Criteria Supporting RG 1.183 R2 ML24165A0852024-06-13013 June 2024 NEI White Paper - Impact of Higher Source Term Fractions on EQ Doses ML24165A0872024-06-12012 June 2024 NEI White Papers Supporting NRC Workshop Discussions Regarding Nuclear Regulatory Commissions (NRC) Potential Changes to Regulatory Guide 1.183 ML24152A3242024-05-31031 May 2024 NEI Concept Paper: Regulation of Rapid High-Volume Deployable Reactors in Remote Locations ML24159A7312024-05-23023 May 2024 05-23-24 Nuclear Energy Institute Letter to the U.S. Nuclear Regulatory Commission Re Industry Comments on Buildings as Items Relied on for Safety ML24135A1982024-04-23023 April 2024 SFAQ No 2022-02, SAE Program Requirements - NEI Withdrawal Letter ML24078A2212024-03-15015 March 2024 3-15-24 NEI Letter Aveil from Juhle on Pur ML24061A0572024-02-29029 February 2024 Endorsement of NEI 08-09, Revision 7, Changes to NEI 08-09 Cyber Security Plan for Nuclear Power Reactors ML24023A0392024-01-22022 January 2024 NEI Comments on the Information Collection Renewal for Domestic Licensing of Special Nuclear Material, Docket Id NRC-2023-0118 ML23355A1972023-12-14014 December 2023 NEI, Comments on NRC Draft Resolution of SFAQ 2022-02, SAE Program Requirements ML23219A1672023-10-25025 October 2023 Response Letter to Fee Exemption Request for Pre-Submittal Activities, Review, and Endorsement of NEI 20-07 ML23270B9002023-09-27027 September 2023 NEI Letter Request for an Extension of Comment Period on Proposed Revision to Standard Review Plan Section 15.0, Introduction - Transient and Accident Analyses, Docket Id NRC 2023 0079 ML23268A0102023-09-22022 September 2023 NEI, Fee Exemption Request for Endorsement, Review and Meeting to Discuss Draft Nuclear Energy Institute Technical Report NEI 23-01, Operator Cold License Training Plan for Advanced Nuclear Reactors ML23241A8612023-08-25025 August 2023 Consolidated Industry Comments to NRC Regulatory Issue Summary 2023-02, Scheduling Information for the Licensing of Accident Tolerant, Increased Enrichment, and Higher Burnup Fuels ML23236A4992023-08-24024 August 2023 Industry Feedback on Region II Fuel Cycle Facility Construction Oversight Workshop Held August 15, 2023, and Suggested Topics for Additional Public Meetings in Fall 2023 ML23256A1622023-08-0101 August 2023 Incoming NEI Letter Dated August 1, 2023 Regarding Increase in Fees 2023-2025 ML23206A0292023-07-24024 July 2023 Incoming Fee Exemption Request for Pre-Submittal Activities, Review, and Endorsement of NEI 20-07 ML23143A1232023-06-22022 June 2023 NRC Fee Waiver Request for Draft NEI 23-01 ML23200A1662023-05-30030 May 2023 NEI Proposed Metrics for a Performance-Based Emergency Preparedness Program ML23116A0732023-05-25025 May 2023 Letter to Hillary Lane in Response to a Request for a Fee Exemption for NEI 23-03 ML23135A7332023-05-0909 May 2023 NEI Comments on NRC Safety Culture Program Effectiveness Review ML23110A6782023-04-18018 April 2023 Request for Review and Endorsement of NEI 23-03, Supplemental Guidance for Application of 10 CFR 50.59 to Digital Modifications at Non-Power Production or Utilization Facilities ML23110A6752023-04-18018 April 2023 04-18-23_NRC_Fee Waiver for NEI 23-03 ML23110A6762023-04-18018 April 2023 04-18-23_NRC_NEI 23-03 Review + Endorse ML24120A2702023-04-0404 April 2023 Melody Rodridguez NEI Comment on Controlled Unclassified Information ML23107A2302023-03-31031 March 2023 NEI Letter, to Andrea Veil, NRC, Regarding Industry Recommendations for a 10 CFR 50.46a/c Combined Rulemaking ML23138A1662023-03-24024 March 2023 Transmittal of NEI 22-05 Revision a, Technology Inclusive Risk Informed Change Evaluation (Tirice) Guidance for the Evaluation of Changes to Facilities Utilizing NEI 18-04 and NEI 21-07 ML23083B4622023-03-24024 March 2023 Transmittal of NEI 22-05 Revision a, Technology Inclusive Risk Informed Change Evaluation (Tirice) Guidance for the Evaluation of Changes to Facilities Utilizing NEI 18-04 and NEI 21-07 ML23060A2142023-03-0101 March 2023 NEI, Request for NRC Endorsement of NEI White Paper, Enabling a Remote Response by Members of an Emergency Response Organization, Revision 0 ML23060A3272023-03-0101 March 2023 NEI, Wireless Cyber Security Guidance ML23023A2752023-01-23023 January 2023 Request for Extension of Comment Period from the Nuclear Energy Institute on PRM-50-124 - Licensing Safety Analysis for Loss-of-Coolant Accidents ML22348A1122023-01-17017 January 2023 Letter to Richard Mogavero Response to Fee Exemption NEI 08-09 Revision 7 ML22353A6082023-01-11011 January 2023 U.S. Nuclear Regulatory Commission Report of the Regulatory Audit of the NEI-Proposed Aging Management Program Revision to Selective Leaching Program (XI.M33) ML22349A1012022-12-12012 December 2022 LTR-22-0343 Ellen Ginsberg, Sr. Vice President, General Counsel and Secretary, Nuclear Energy Institute, Expresses Concerns Related to Issuance of Regulatory Issue Summary 2022-02; Operational Leakage ML22321A3152022-11-16016 November 2022 NEI Letter with Comments on Significance Determination Process Timeliness Review ML22336A0372022-11-16016 November 2022 Fee Exemption Request for NEI 08-09 Revision 7 - Changes to NEI 08-09 Cyber Security Plan for Nuclear Power Reactors ML22298A2262022-10-25025 October 2022 Endorsement of NEI 15-09, Cyber Security Event Notifications, Revision 1, Dated October 2022 ML22298A2302022-10-17017 October 2022 Submittal of NEI 22-03, Draft Revision 0, Nuclear Generation Quality Assurance Program Description ML22207B6512022-07-26026 July 2022 NEI, Full Fee Exemption Request for Industry Guidance Proposal - Weather Related Administrative Controls During Transient Outdoor Dry Cask Operations ML22195A1662022-07-14014 July 2022 NEI, Draft G of NEI 99-01, Development of Emergency Action Levels for Non-Passive Reactors, Revision 7 ML22195A0202022-07-13013 July 2022 07-13-22 NRC Fee Exemption Request for NEI 21-05 Review ML22195A0672022-07-13013 July 2022 Fee Exemption Request for Review and Meeting to Discuss Draft Nuclear Energy Institute Technical Report NEI 21-05, Reporting Guidance for Licensees with Risk-Informed Licensing Bases 2024-09-09
[Table view] |
Text
March 25, 2010 Mr. James H. Riley, Director Engineering Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708
SUBJECT:
DRAFT SAFETY EVALUATION FOR NUCLEAR ENERGY INSTITUTE TOPICAL REPORT MATERIALS RELIABILITY PROGRAM (MRP): TECHNICAL BASIS FOR PREMPTIVE WELD OVERLAYS FOR ALLOY 82/182 BUTT WELDS IN PRESSURIZED WATER REACTORS (MRP-169) (TAC NO. MD8005)
Dear Mr. Riley:
By letter dated September 7, 2005, the Nuclear Energy Institute (NEI) submitted Topical Report (TR) Material Reliability Program (MRP): Technical Basis For Preemptive Weld Overlays For Alloy 82/182 Butt Welds in Pressurized Water Reactors (MRP-169), Revision 0, to the U.S.
Nuclear Regulatory Commission (NRC) staff for review. In a letter to NEI dated April 26, 2007, the NRC discontinued its review of TR MRP-169, Revision 0. After an August 23, 2007, public pre-submittal meeting with the NRC staff, the NEI and the Electric Power Research Institute stated that they would submit the necessary documentation to re-initiate the NRC's review of TR MRP-169, Revision 0. By letter dated January 9, 2008, NEI re-submitted for NRC staff review TR MRP-169, Revision 0. The transmittal memo for the January 9, 2008, letter from NEI states that this document is considered to be non-proprietary.
By letters dated August 3, 2006 and April 7, 2008, the NRC staff issued a request for additional information (RAI) to NEI to support the review of TR MRP-169. By letters dated January 9, 2008, May 2, 2008, March 2, 2009, November 30, 2009, and February 3, 2010, NEI responded to the NRC staff's RAIs and provided supplemental information in support of the NRC staff's review of TR MRP-169. Enclosed for NEI review and comment is a copy of the NRC staff's draft safety evaluation (SE) for the TR.
J. Riley 2 Twenty working days are provided for you to comment on any factual errors or clarity concerns contained in the SE. The final SE will be issued after making any necessary changes and will be made publicly available. The NRC staff's disposition of your comments on the draft SE will be discussed in the final SE.
To facilitate the NRC staff's review of your comments, please provide a marked-up copy of the draft SE showing proposed changes and provide a summary table of the proposed changes.
If you have any questions, please contact Tanya Mensah at 301-415-3610.
Sincerely, /RA/ Stacey L. Rosenberg, Chief Licensing Processes Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation
Project Nos. 669 and 689
Enclosure:
Draft SE cc w/encl: See next page J. Riley 2 Twenty working days are provided for you to comment on any factual errors or clarity concerns contained in the SE. The final SE will be issued after making any necessary changes and will be made publicly available. The NRC staff's disposition of your comments on the draft SE will be discussed in the final SE.
To facilitate the NRC staff's review of your comments, please provide a marked-up copy of the draft SE showing proposed changes and provide a summary table of the proposed changes.
If you have any questions, please contact Tanya Mensah at 301-415-3610.
Sincerely, /RA/ Stacey L. Rosenberg, Chief Licensing Processes Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project Nos. 669 and 689
Enclosure:
Draft SE cc w/encl: See next page DISTRIBUTION
- PUBLIC PLPB Reading File RidsNrrDpr RidsNrrDprPlpb RidsNrrPMTMensah RidsNrrLADBaxley RidsOgcMailCenter RidsAcrsAcnwMailCenter RidsNrrDciCpnb J Tsao T Lupold T Sullivan R Hardies
J Collins A Csontos DRudland H Rathbun EXTERNAL DISTRIBUTION:
vka@nei.org ewillis@epri.com ADAMS ACCESSION NO.: *No major changes to SE input. NRR-043 ML100740466 (Cover Letter); ML100740481 (Enclosure)
OFFICE PLPB/PM PLPB /LA DCI/CPNB* PLPB /BC NAME TMensah DBaxley TLupold SRosenberg DATE 3/ /10 3/ /10 2/28/10 3/25/10 OFFICIAL RECORD COPY J. Riley 3 Nuclear Energy Institute Project No. 689 Electric Power Research Institute Project No. 669
cc:Mr. Anthony Pietrangelo, Senior Vice President & Chief Nuclear Officer Nuclear Generation Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 arp@nei.org Mr. Jack Roe, Director Security Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 jwr@nei.org Mr. Charles B. Brinkman Washington Operations ABB-Combustion Engineering, Inc. 12300 Twinbrook Parkway, Suite 330 Rockville, MD 20852 brinkmcb@westinghouse.com Mr. James Gresham, Manager Regulatory Compliance and Plant Licensing Westinghouse Electric Company P.O. Box 355 Pittsburgh, PA 15230-0355 greshaja@westinghouse.com Ms. Barbara Lewis Assistant Editor Platts, Principal Editorial Office 1200 G St., N.W., Suite 1100 Washington, DC 20005 Barbara_lewis@platts.com Mr. Alexander Marion, Vice President Nuclear Operations Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 am@nei.org
Mr. John Butler, Director Operations Support Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 jcb@nei.org Mr. James H. Riley, Director Engineering Nuclear Energy Institute 1776 I Street, NW Washington, DC 20006-3708 jhr@nei.org Mr. Chris Larsen Vice President and Chief Nuclear Officer EPRI 3412 Hillview Avenue Palo Alto, CA 94304-1338 cblarsen@epri.com Mr. David J. Modeen Director, External Affairs EPRI 1300 W. T. Harris Boulevard Charlotte, NC 28262-8550 dmodeen@epri.com Dr. Sean Bushart EPRI 3412 Hillview Avenue Palo Alto, CA 94304-1338 sbushart@epri.com Mr. Kurt Edsinger EPRI 3412 Hillview Avenue Palo Alto, CA 94304-1338 kedsinge@epri.com
Mr. Ken Canavan EPRI 1300 W.T. Harris Boulevard Charlotte, NC 28262-8550 kcanavan@epri.com Mr. Greg Selby EPRI 1300 W. T. Harris Boulevard Charlotte, NC 28262-8550 gselby@epri.com Mr. David Steininger EPRI 3412 Hillview Avenue Palo Alto, CA 94304-1338 dsteinin@epri.com Mr. Neil Wilmshurst EPRI 1300 W. T. Harris Boulevard Charlotte, NC 28262-8550 nwilmshu@epri.com