Submittal of Fifteenth Refueling Outage (2RF15), Inservice Inspection (ISI) Summary Report (2007 Edition of ASME Code,Section XI, 2008 Addenda, Third Interval Start Date: August 3, 2014, Third Interval End Date: August 2, 2023)ML16057A180 |
Person / Time |
---|
Site: |
Comanche Peak ![Luminant icon.png](/w/images/d/d7/Luminant_icon.png) |
---|
Issue date: |
02/08/2016 |
---|
From: |
Hope T, Peters K Luminant Generation Co, Luminant Power |
---|
To: |
Document Control Desk, Office of Nuclear Reactor Regulation |
---|
References |
---|
CP-201600117, TXX-16024 |
Download: ML16057A180 (5) |
|
|
---|
Category:Inservice/Preservice Inspection and Test Report
MONTHYEARCP-202300442, (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program2023-09-15015 September 2023 (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program CP-202300411, (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20)2023-08-17017 August 2023 (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20) CP-202200419, (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report2022-11-0303 November 2022 (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report CP-202200306, (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 22 (1RF22)2022-08-11011 August 2022 (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 22 (1RF22) CP-202200200, (CPNPP) Unit 2 Refueling Outage 19 (2RF19) Steam Generator 180 Day Report2022-05-0505 May 2022 (CPNPP) Unit 2 Refueling Outage 19 (2RF19) Steam Generator 180 Day Report TXX-2201, (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Report (OAR-1 Form) for Unit 2 Refueling Outage 19 (2RF19)2022-02-0101 February 2022 (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Report (OAR-1 Form) for Unit 2 Refueling Outage 19 (2RF19) CP-202100751, (CPNPP) - ASME OM Inservice Test Program Relief Request SNB-3, Snubber Inservice Program Third Internal Extension2022-01-0404 January 2022 (CPNPP) - ASME OM Inservice Test Program Relief Request SNB-3, Snubber Inservice Program Third Internal Extension CP-202100150, (CPNPP) Units 1 & 2 - Inservice Testing Plan for Pumps & Valves Third Interval, Revision 42021-03-23023 March 2021 (CPNPP) Units 1 & 2 - Inservice Testing Plan for Pumps & Valves Third Interval, Revision 4 CP-202100061, (CPNPP) - Inservice Inspection (Isi) Owner'S Activity Report (OAR-1 Form) for Unit 1 Refueling Outage 21 (1RF21)2021-01-27027 January 2021 (CPNPP) - Inservice Inspection (Isi) Owner'S Activity Report (OAR-1 Form) for Unit 1 Refueling Outage 21 (1RF21) ML20282A7342020-10-22022 October 2020 Proposed Alternative to the Requirements of the ASME Code to Extend the Inservice Inspection Interval (EPID L-2020-LLR-0059 (COVID-19)) CP-202000463, (CPNPP) - Inservice Test (IST) Program Request to Use Later Code Edition2020-08-31031 August 2020 (CPNPP) - Inservice Test (IST) Program Request to Use Later Code Edition CP-202000262, Snubber Testing and Snubber Visual Examinations Relief Request2020-04-10010 April 2020 Snubber Testing and Snubber Visual Examinations Relief Request CP-202000261, Inservice Inspection (ISI) and Inservice Testing (IST) Program Relief Requests2020-04-0707 April 2020 Inservice Inspection (ISI) and Inservice Testing (IST) Program Relief Requests CP-201900496, Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 20 (IRF20)2019-08-26026 August 2019 Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 20 (IRF20) CP-201800215, Submittal of Nineteenth Refueling Outage (1RF19) Steam Generator 180 Day Report2018-04-19019 April 2018 Submittal of Nineteenth Refueling Outage (1RF19) Steam Generator 180 Day Report CP-201800086, Submittal of Unit 1 Nineteenth Refueling Outage (IRF19) Inservice Inspection (ISI) Summary Report (2007 Edition of ASME Code, Section XI, 2008 Addenda Unit 1 Third Interval Start Date: August 13, 2010 Unit 1 Third ..2018-02-0707 February 2018 Submittal of Unit 1 Nineteenth Refueling Outage (IRF19) Inservice Inspection (ISI) Summary Report (2007 Edition of ASME Code, Section XI, 2008 Addenda Unit 1 Third Interval Start Date: August 13, 2010 Unit 1 Third .. CP-201700623, Submittal of Sixteenth Refueling Outage (2RF16) Inservice Inspection (ISI) Summary Report (2007 Edition of ASME Code, Section XI, 2008 Addenda Third Interval, Start Date: Aug. 3, 2014 Third Interval End Date: Aug. 2, 2023)2017-08-0101 August 2017 Submittal of Sixteenth Refueling Outage (2RF16) Inservice Inspection (ISI) Summary Report (2007 Edition of ASME Code, Section XI, 2008 Addenda Third Interval, Start Date: Aug. 3, 2014 Third Interval End Date: Aug. 2, 2023) CP-201600869, Submittal of Eighteenth Refueling Outage (1RF18) Inservice Inspection Summary Report2016-08-31031 August 2016 Submittal of Eighteenth Refueling Outage (1RF18) Inservice Inspection Summary Report CP-201600148, Requesting Additional Information for Relief Request b-9 for Unit 2 Second Ten Year Inservice Inspection Interval2016-03-0202 March 2016 Requesting Additional Information for Relief Request b-9 for Unit 2 Second Ten Year Inservice Inspection Interval CP-201600117, Submittal of Fifteenth Refueling Outage (2RF15), Inservice Inspection (ISI) Summary Report (2007 Edition of ASME Code, Section XI, 2008 Addenda, Third Interval Start Date: August 3, 2014, Third Interval End Date: August 2, 2023)2016-02-0808 February 2016 Submittal of Fifteenth Refueling Outage (2RF15), Inservice Inspection (ISI) Summary Report (2007 Edition of ASME Code, Section XI, 2008 Addenda, Third Interval Start Date: August 3, 2014, Third Interval End Date: August 2, 2023) CP-201500777, Relief Request B-10, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August..2015-08-0303 August 2015 Relief Request B-10, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August.. CP-201500775, Relief Request B-3, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August..2015-08-0303 August 2015 Relief Request B-3, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August.. CP-201500776, Relief Request B-9, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August..2015-08-0303 August 2015 Relief Request B-9, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August.. CP-201500778, Relief Request B-11, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August..2015-08-0303 August 2015 Relief Request B-11, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August.. CP-201500779, Relief Request B-15, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August..2015-08-0303 August 2015 Relief Request B-15, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August.. CP-201500780, Relief Request C-2, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August..2015-08-0303 August 2015 Relief Request C-2, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August.. CP-201500781, Relief Request C-4, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August..2015-08-0303 August 2015 Relief Request C-4, Second Ten Year Inservice Inspection Interval from 10CFR50.55a Inspection Requirements Due to Physical Interferences (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August.. CP-201500685, Response to Request for Additional Information for Relief Request 2A3-1, Unit 2, Inservice Inspection for Application of an Alternative to the ASME Boiler and Pressure Vessel Code Section XI Examination Requirements for Class 1 & 2.2015-07-22022 July 2015 Response to Request for Additional Information for Relief Request 2A3-1, Unit 2, Inservice Inspection for Application of an Alternative to the ASME Boiler and Pressure Vessel Code Section XI Examination Requirements for Class 1 & 2. CP-201500671, Relief Request T-1 for Inservice Testing Program for Application of an Alternative to the ASME OM Code Frequency Specifications, (2007 Edition of ASME Code, Section XI, 2008 Addenda Third Interval Start Date: August 3.2015-06-30030 June 2015 Relief Request T-1 for Inservice Testing Program for Application of an Alternative to the ASME OM Code Frequency Specifications, (2007 Edition of ASME Code, Section XI, 2008 Addenda Third Interval Start Date: August 3. CP-201500244, Relief Request 2A3-1 for Inservice Inspection for Application of an Alternative to the ASME Boiler and Pressure Vessel Code Section XI Examination Requirements for Class 1 and 2 Piping Welds (2007 Edition of ASME Code.2015-03-0404 March 2015 Relief Request 2A3-1 for Inservice Inspection for Application of an Alternative to the ASME Boiler and Pressure Vessel Code Section XI Examination Requirements for Class 1 and 2 Piping Welds (2007 Edition of ASME Code. CP-201500157, Relief Request No. 2C3-1 for the Reactor Pressure Vessel Leak-Off Flange (Third ISI Interval Start Date: August 3, 2014; Third ISI Interval End Date: August 2, 2023)2015-02-24024 February 2015 Relief Request No. 2C3-1 for the Reactor Pressure Vessel Leak-Off Flange (Third ISI Interval Start Date: August 3, 2014; Third ISI Interval End Date: August 2, 2023) CP-201500222, Submittal of Unit 1, Seventeenth Refueling Outage (1RF17) Inservice Inspection Summary Report (2007 Edition of ASME Code, Section XI, 2008 Addenda Third Interval Start Date August 13, 2010 Third Interval End Date: August 12, 2020)2015-02-18018 February 2015 Submittal of Unit 1, Seventeenth Refueling Outage (1RF17) Inservice Inspection Summary Report (2007 Edition of ASME Code, Section XI, 2008 Addenda Third Interval Start Date August 13, 2010 Third Interval End Date: August 12, 2020) ML14325A7592014-11-19019 November 2014 Transmittal of Inservice Testing Plan for Pumps and Valves Third Interval, Revision 1 CP-201401035, Relief Requests Nos. B-7, B-12 and B-13 for the Second 10-Year ISI Interval (Second ISI Interval Start Date: August 3, 2004; Second ISI Interval End Date: August 2, 2014)2014-08-27027 August 2014 Relief Requests Nos. B-7, B-12 and B-13 for the Second 10-Year ISI Interval (Second ISI Interval Start Date: August 3, 2004; Second ISI Interval End Date: August 2, 2014) CP-201400933, Submittal of Unit 2 Fourteenth Refueling Outage (2RF14) Inservice Inspection (ISI) Summary Report (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August 3, 2004 Second Interval End Date: August 2, 20142014-07-23023 July 2014 Submittal of Unit 2 Fourteenth Refueling Outage (2RF14) Inservice Inspection (ISI) Summary Report (1998 Edition of ASME Code, Section XI, 2000 Addenda Second Interval Start Date: August 3, 2004 Second Interval End Date: August 2, 2014 CP-201401379, Transmittal of Inservice Testing Plan for Pumps and Valves Third Interval, Revision 12014-02-24024 February 2014 Transmittal of Inservice Testing Plan for Pumps and Valves Third Interval, Revision 1 CP-201300143, Response to RAI for Unit 1 Relief Request No. B-22013-02-0707 February 2013 Response to RAI for Unit 1 Relief Request No. B-2 CP-201300005, Submittal of Inservice Inspection Summary Report for the 13th Refueling Outage2013-01-31031 January 2013 Submittal of Inservice Inspection Summary Report for the 13th Refueling Outage CP-201300003, Submittal of Relief Request No. B-2, Third 10 Year ISI Interval from 10CFR50.55a Requirements for Reactor Vessel Hot Leg Nozzle Weld Examinations (Third ISI Interval Start Date August 13, 2010)2013-01-16016 January 2013 Submittal of Relief Request No. B-2, Third 10 Year ISI Interval from 10CFR50.55a Requirements for Reactor Vessel Hot Leg Nozzle Weld Examinations (Third ISI Interval Start Date August 13, 2010) CP-201200879, Relief Request No. V-1 for Unit 1 and Unit 2 Inservice Testing Plan for Pumps and Valves (ASME OM Code 2004 Edition, Through 2006 Addenda; Third Interval Start Date: August 3, 2013)2012-09-0606 September 2012 Relief Request No. V-1 for Unit 1 and Unit 2 Inservice Testing Plan for Pumps and Valves (ASME OM Code 2004 Edition, Through 2006 Addenda; Third Interval Start Date: August 3, 2013) CP-201200045, Submittal of Unit 1 Fifteenth Refueling Outage (1RF15) Inservice Inspection (ISI) Summary Report (Unit 1: 1998 Edition of ASME Code Section XI Through 2000 Addenda, Interval Start Date - August 13, 2010, Third Interval)2012-01-17017 January 2012 Submittal of Unit 1 Fifteenth Refueling Outage (1RF15) Inservice Inspection (ISI) Summary Report (Unit 1: 1998 Edition of ASME Code Section XI Through 2000 Addenda, Interval Start Date - August 13, 2010, Third Interval) CP-201101429, Twelfth Refueling Outage (2RF12) Steam Generator 180 Day Report2011-10-12012 October 2011 Twelfth Refueling Outage (2RF12) Steam Generator 180 Day Report CP-201101031, Transmittal of Unit 1 Inservice Inspection Program Plan, Revision 0 (Unit 1: ASME Code XI 1998 Edition, 1999 and 2000 Addenda, Interval Start - August 13, 2010, Third Interval)2011-08-0202 August 2011 Transmittal of Unit 1 Inservice Inspection Program Plan, Revision 0 (Unit 1: ASME Code XI 1998 Edition, 1999 and 2000 Addenda, Interval Start - August 13, 2010, Third Interval) CP-201100852, Submittal of 12th Refueling Outage (2RF12) Inservice Inspection (ISI) Summary Report (1998 Edition of ASME Code Section XI Through 2000 Addenda, Interval Start Date - August 4,2004, Second Interval)2011-07-21021 July 2011 Submittal of 12th Refueling Outage (2RF12) Inservice Inspection (ISI) Summary Report (1998 Edition of ASME Code Section XI Through 2000 Addenda, Interval Start Date - August 4,2004, Second Interval) CP-201001545, Relief Request No. B-10 for the Unit 1 Second 10 Years ISI Interval from 10 CFR 50.55a Inspection Requirements Due to Physical Interferences (Second Interval Start Date: August 13, 2000)2010-12-15015 December 2010 Relief Request No. B-10 for the Unit 1 Second 10 Years ISI Interval from 10 CFR 50.55a Inspection Requirements Due to Physical Interferences (Second Interval Start Date: August 13, 2000) CP-201000889, Relief Request No. C-6 for Unit 1 Second 10 Year ISI Interval from 10 CFR 50.55a Inspection Requirements Due to Physical Interferences (Second Interval Start Date: August 13, 2000)2010-12-15015 December 2010 Relief Request No. C-6 for Unit 1 Second 10 Year ISI Interval from 10 CFR 50.55a Inspection Requirements Due to Physical Interferences (Second Interval Start Date: August 13, 2000) CP-201000888, Submittal of Unit 1 Fourteenth Refueling Outage Inservice Inspection Summary Report (Unit 1: 1998 Edition of ASME Code Section XI Through 2000 Addenda, Interval Start Date - August 13, 2000, Second Interval)2010-07-22022 July 2010 Submittal of Unit 1 Fourteenth Refueling Outage Inservice Inspection Summary Report (Unit 1: 1998 Edition of ASME Code Section XI Through 2000 Addenda, Interval Start Date - August 13, 2000, Second Interval) CP-200900707, Revision to Relief Request No. P-2 for the Units 1 & 2 Inservice Testing Plan for Pumps and Valves (ASME OM Code 1998 Edition, Through 2000 Addenda; Interval Start Date: August 3, 2004, Second Interval)2009-05-14014 May 2009 Revision to Relief Request No. P-2 for the Units 1 & 2 Inservice Testing Plan for Pumps and Valves (ASME OM Code 1998 Edition, Through 2000 Addenda; Interval Start Date: August 3, 2004, Second Interval) CP-200900009, Request for Relief to Extend the Unit 1 & 2 Inservice Inspection Interval for the Reactor Vessel Weld Examination and License Amendment Request 09-004 to Add License Condition for Submittal of ISI Information and Analyses2009-03-0404 March 2009 Request for Relief to Extend the Unit 1 & 2 Inservice Inspection Interval for the Reactor Vessel Weld Examination and License Amendment Request 09-004 to Add License Condition for Submittal of ISI Information and Analyses CP-200900008, Submittal of Unit 1 Thirteenth Refueling Outage (1RF13) Inservice Inspection (ISI) Summary Report (Unit 1:1998 Edition of ASME Code Section XI Through 2000 Addenda, Interval Start Date - 08/13/2000, Second Interval2009-01-0808 January 2009 Submittal of Unit 1 Thirteenth Refueling Outage (1RF13) Inservice Inspection (ISI) Summary Report (Unit 1:1998 Edition of ASME Code Section XI Through 2000 Addenda, Interval Start Date - 08/13/2000, Second Interval 2023-09-15
[Table view] Category:Legal-Affidavit
MONTHYEARCP-202300285, Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 12023-07-12012 July 2023 Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 1 CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML19259A0212019-09-11011 September 2019 Publisher'S Affidavit for Hazardous Industrial Waste Permit ML19253A0522019-09-0303 September 2019 Publisher'S Affidavit for Water Quality Permits CP-201600117, Submittal of Fifteenth Refueling Outage (2RF15), Inservice Inspection (ISI) Summary Report (2007 Edition of ASME Code, Section XI, 2008 Addenda, Third Interval Start Date: August 3, 2014, Third Interval End Date: August 2, 2023)2016-02-0808 February 2016 Submittal of Fifteenth Refueling Outage (2RF15), Inservice Inspection (ISI) Summary Report (2007 Edition of ASME Code, Section XI, 2008 Addenda, Third Interval Start Date: August 3, 2014, Third Interval End Date: August 2, 2023) CP-201400503, Response to Requests for Additional Information on License Amendment Request 13-01 Spent Fuel Pool Criticality Analysis2014-04-17017 April 2014 Response to Requests for Additional Information on License Amendment Request 13-01 Spent Fuel Pool Criticality Analysis ML0917507802009-06-16016 June 2009 Non-Disclosure Affidavits for Karen Hadden, Eliza Brown and Robert V. Eye CP-200700016, Supplemental Information to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage.2007-10-24024 October 2007 Supplemental Information to License Amendment Request (LAR) 07-004, Revision to the Operating License and Technical Specification 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage. CPSES-200701178, Supplement to Application for Order Approving Indirect Transfer of Control of Licenses and License Amendments to Reflect Proposed Licensee Name Change (TAC Nos. MD5289 and MD5280), Enclosures 1, 4, 5, 6 & 72007-07-20020 July 2007 Supplement to Application for Order Approving Indirect Transfer of Control of Licenses and License Amendments to Reflect Proposed Licensee Name Change (TAC Nos. MD5289 and MD5280), Enclosures 1, 4, 5, 6 & 7 2023-07-12
[Table view] |
Text
Kenneth J. Peters Luminant Power Senior Vice President P0O Box 1002____& Chief Nuclear Officer (Acting) 6322 North FM 56 Kenneth.Peters@Lurninant.corn Glen Rose, TX 76043 Lumin nt T254 897 6565 C817 776 0037 F 254 897 6652 CP-201600117 Ref. # 10CFR50.55a TXX-16024 February 8, 2016 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT DOCKET NO. 50-446 SUBMITTAL OF UNIT 2 FIFTEENTH REFUELING OUTAGE (2R1F15)INSERVICE INSPECTION (ISI)
SUMMARY
REPORT (2007 EDITION OF ASME CODE, SECTION XI, 2008 ADDENDA THIRD INTERVAL START DATE: AUGUST 3, 2014 THIRD INTERVAL END DATE: AUGUST 2, 2023)
Dear Sir or Madam:
In accordance with 10CFR50.55a, Luminant Generation Company LLC (Luminant Power) transmits the Inservice Inspection Summary Report for the fifteenth refueling outage of Comanche Peak Unit 2. The enclosed report is being provided to you pursuant to the ASME Boiler and Pressure Vessel Code,Section XI, paragraph IWA-6240(b).
A copy of this report is also forwarded to the Chief Inspector in accordance with the Texas Boiler Law & Rules and Regulations, paragraph 65.100.g.4.
This communication contains no new licensing basis commitments regarding Comanche Peak Unit 2.Should you have any questions, please contact Mr. Aaron Thomas at (254) 897-6637.Sincerely, Luminant Generation Company LLC Kenneth J. Peters ,7 ..By: Timothy A. Hope Manager, Regulatory Affairs U. S. Nuclear Regulatory Commission TXX-16024 Page 2 of 2 02/08/2016 Enclosure
-Inservice Inspection Summary for Unit 2 Fifteenth Refueling Outage c -Marc L. Dapas, Region WV Baiwant K. Singal, NRR Resident Inspectors, Comanche Peak Robert Free, TDLR Jack Ballard, ANII, Comanche Peak ENCLOSURE TO TXX-16024 INSERVICE INSPECTION
SUMMARY
REPORT FOR UNIT 2 FIFTEENTH REFUELING OUTAGE FORM OAR-I OWNER'S ACTMVTY REPORT Report Number CPNPP U2 2RF15 Comanche.Peak Nuclear Power Plant P.O. Box 1002 Glen Rose, Texas 76043 Plant Unit No. 2 Commercial service August 3, 1993 Ref ueting outage 15 Currant inspection interval Current inspection period 3 (1", 1", 3", 4~, other)1 (1", ZS 3'~)Edition and Addenda of Section Xl applicable to the inspection plan 2007 Edition, 2008 Addenda Date and revision of inspection plan CPNPP Unit 2 ISI Proaram Plan. Interval 3 Rev. 0 Auaust 3, 2014 Edition and Addenda of Section Xl applicable to repairs and replacements, if different than the Inspection plan.Same Code Cases Used N-53Z-4 (If applicable)
OF CONFORMANCE I certify that (a) the statements made In this report are correct; (b) the examinations and tests meet the inspection Plan as required by the ASIAE Code,Section IX; and (c) the repairlreplacement activities and evaluations supporting the completion of 1RF1._7 conform to the requirements of Section XI.Signed Engineerdng Programs Manager Date CERTIFICATE OF INSERVICE INSPECTION I, the undersiglned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State of Province of Texas and employed by Hartford Steam Boiler Insoection and Insurance Compoany of Connecticut, have inspected the items described in this Owner's Activity Report, and state that, to the best of my knowledge and belief, the Owner has performed all activities represented by this report in accordance with the requirements of Section XI.By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, concerningi the repair/replacement activities and evaluation described In this report. Furthermore, neither the inspector nor his employer shall be liable In any manner for any personal injury or property damage or a loss of any kind arilsing from or connected with this inspection.
Q 1§i~Y (U Commissions13162" AWT '" T'x I~rL National Board, state, Province and Endorsements
/Dote Insp~ctor's S1ignature OAR-I Page 1 of 2 TABLE 1 ITEMS WITH FLAWS OR RELEVANT CONDITIONS THAT REQUIRED EVALUATION FOR CONTINUED SERVICE Evaluation Deacttpton Examination Item Description Catogoty and 11em Number F-A F1.40 ... Loose jam nut, cotter pins not spread and CR-2015-009272 found alt issues acceptable and insufficient thread engagement on CRDM seismic, were restored to design condition during re-supports installation of CRDM seismic supports.F-A F1.20 Spding Can position indicator for pipe support CR-2015-0]09 181 found this to be not a non-TCX-2-2100-H6 found to be outside H&C settings conforming conditions 1SI re-examination not (MS-2-0O1-402-C72S) required.
Use as is.F-A F1.30 Sprdng Can position indicator CC.2-SB-O38-H3" CR-2015-008795 evaluated to use as Is.;found misaligned. (CC-2-031-407-$43S)
F-A Cotter Pin missing on pipe support TCX-2-2566-CR-2015-009112 evaluated to use as is.,H24 (St.2-306-410-C42R)
F-A F1.20 Strut TCX-2-2586-H24 found misatigned (H.SI.2- CR-2015-0091 15 evaluated to use as is.RB-010A-704-2)
F-A F1.20 Cotter Pin missing on pipe support TCX-1-4110-CR-2015-009180 evaluated to use as Is.H24 (H-CS-2-RB-037A-702-1)
TABLE 2 ABSTRACT OF REPAIRS 1 REPLACEMENTS, OR CORRECTIVE MEASURES-REQUIRED FOR CONTINUED SERVICE Code Ilem Descdptlln Dote Repolr/Class Descdptlan of Walk Completed Replacement Plan Number None OAR-i Page 2 of 2'p Kenneth J. Peters Luminant Power Senior Vice President P0O Box 1002____& Chief Nuclear Officer (Acting) 6322 North FM 56 Kenneth.Peters@Lurninant.corn Glen Rose, TX 76043 Lumin nt T254 897 6565 C817 776 0037 F 254 897 6652 CP-201600117 Ref. # 10CFR50.55a TXX-16024 February 8, 2016 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT DOCKET NO. 50-446 SUBMITTAL OF UNIT 2 FIFTEENTH REFUELING OUTAGE (2R1F15)INSERVICE INSPECTION (ISI)
SUMMARY
REPORT (2007 EDITION OF ASME CODE, SECTION XI, 2008 ADDENDA THIRD INTERVAL START DATE: AUGUST 3, 2014 THIRD INTERVAL END DATE: AUGUST 2, 2023)
Dear Sir or Madam:
In accordance with 10CFR50.55a, Luminant Generation Company LLC (Luminant Power) transmits the Inservice Inspection Summary Report for the fifteenth refueling outage of Comanche Peak Unit 2. The enclosed report is being provided to you pursuant to the ASME Boiler and Pressure Vessel Code,Section XI, paragraph IWA-6240(b).
A copy of this report is also forwarded to the Chief Inspector in accordance with the Texas Boiler Law & Rules and Regulations, paragraph 65.100.g.4.
This communication contains no new licensing basis commitments regarding Comanche Peak Unit 2.Should you have any questions, please contact Mr. Aaron Thomas at (254) 897-6637.Sincerely, Luminant Generation Company LLC Kenneth J. Peters ,7 ..By: Timothy A. Hope Manager, Regulatory Affairs U. S. Nuclear Regulatory Commission TXX-16024 Page 2 of 2 02/08/2016 Enclosure
-Inservice Inspection Summary for Unit 2 Fifteenth Refueling Outage c -Marc L. Dapas, Region WV Baiwant K. Singal, NRR Resident Inspectors, Comanche Peak Robert Free, TDLR Jack Ballard, ANII, Comanche Peak ENCLOSURE TO TXX-16024 INSERVICE INSPECTION
SUMMARY
REPORT FOR UNIT 2 FIFTEENTH REFUELING OUTAGE FORM OAR-I OWNER'S ACTMVTY REPORT Report Number CPNPP U2 2RF15 Comanche.Peak Nuclear Power Plant P.O. Box 1002 Glen Rose, Texas 76043 Plant Unit No. 2 Commercial service August 3, 1993 Ref ueting outage 15 Currant inspection interval Current inspection period 3 (1", 1", 3", 4~, other)1 (1", ZS 3'~)Edition and Addenda of Section Xl applicable to the inspection plan 2007 Edition, 2008 Addenda Date and revision of inspection plan CPNPP Unit 2 ISI Proaram Plan. Interval 3 Rev. 0 Auaust 3, 2014 Edition and Addenda of Section Xl applicable to repairs and replacements, if different than the Inspection plan.Same Code Cases Used N-53Z-4 (If applicable)
OF CONFORMANCE I certify that (a) the statements made In this report are correct; (b) the examinations and tests meet the inspection Plan as required by the ASIAE Code,Section IX; and (c) the repairlreplacement activities and evaluations supporting the completion of 1RF1._7 conform to the requirements of Section XI.Signed Engineerdng Programs Manager Date CERTIFICATE OF INSERVICE INSPECTION I, the undersiglned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State of Province of Texas and employed by Hartford Steam Boiler Insoection and Insurance Compoany of Connecticut, have inspected the items described in this Owner's Activity Report, and state that, to the best of my knowledge and belief, the Owner has performed all activities represented by this report in accordance with the requirements of Section XI.By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, concerningi the repair/replacement activities and evaluation described In this report. Furthermore, neither the inspector nor his employer shall be liable In any manner for any personal injury or property damage or a loss of any kind arilsing from or connected with this inspection.
Q 1§i~Y (U Commissions13162" AWT '" T'x I~rL National Board, state, Province and Endorsements
/Dote Insp~ctor's S1ignature OAR-I Page 1 of 2 TABLE 1 ITEMS WITH FLAWS OR RELEVANT CONDITIONS THAT REQUIRED EVALUATION FOR CONTINUED SERVICE Evaluation Deacttpton Examination Item Description Catogoty and 11em Number F-A F1.40 ... Loose jam nut, cotter pins not spread and CR-2015-009272 found alt issues acceptable and insufficient thread engagement on CRDM seismic, were restored to design condition during re-supports installation of CRDM seismic supports.F-A F1.20 Spding Can position indicator for pipe support CR-2015-0]09 181 found this to be not a non-TCX-2-2100-H6 found to be outside H&C settings conforming conditions 1SI re-examination not (MS-2-0O1-402-C72S) required.
Use as is.F-A F1.30 Sprdng Can position indicator CC.2-SB-O38-H3" CR-2015-008795 evaluated to use as Is.;found misaligned. (CC-2-031-407-$43S)
F-A Cotter Pin missing on pipe support TCX-2-2566-CR-2015-009112 evaluated to use as is.,H24 (St.2-306-410-C42R)
F-A F1.20 Strut TCX-2-2586-H24 found misatigned (H.SI.2- CR-2015-0091 15 evaluated to use as is.RB-010A-704-2)
F-A F1.20 Cotter Pin missing on pipe support TCX-1-4110-CR-2015-009180 evaluated to use as Is.H24 (H-CS-2-RB-037A-702-1)
TABLE 2 ABSTRACT OF REPAIRS 1 REPLACEMENTS, OR CORRECTIVE MEASURES-REQUIRED FOR CONTINUED SERVICE Code Ilem Descdptlln Dote Repolr/Class Descdptlan of Walk Completed Replacement Plan Number None OAR-i Page 2 of 2'p