Letter Sequence Other |
---|
|
|
MONTHYEARML18096A9362018-04-0404 April 2018 License Amendment Request to Adopt NFPA-805 Performance Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) Project stage: Request ML18096A9552018-04-0404 April 2018 License Amendment Request to Adopt NFPA-805 Performance Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) Project stage: Other NL-17-1962, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors.2018-06-0707 June 2018 Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. Project stage: Request ML18228A8352018-08-22022 August 2018 Online Reference Portal for License Amendment Request to Adopt National Fire Protection Association Standard 805 Project stage: Other ML19029B3402019-01-23023 January 2019 Southern Nuclear Operating Company, Edwin I. Hatch Nuclear Plant, Unit Nos. 1 and 2 Draft Request for Additional Information for the License Amendment Requests to Adopt the Risk-Informed Provisions of Title 10 of the Code of Federal Regulat Project stage: Draft RAI ML19018A2312019-01-23023 January 2019 Edwin Hatch 1 & 2 - Regulatory Audit in Support of the License Amendment Requests to Implement a Risk-Informed, Performance-based, Fire Protection Program Project stage: Other ML19088A0092019-03-29029 March 2019 NRR E-mail Capture - Hatch 1 and 2 - LAR to Adopt NFPA 805 Fire Protection Standard, EPID L-2018-LLA-0107, Request for Additional Information Project stage: RAI ML19220A0362019-08-0808 August 2019 NRR E-mail Capture - RAI - Edwin I. Hatch Nuclear Plant, LAR Regarding Adoption of NFPA 805, Request for Additional Information, EPID L-2018-LLA-0107 Project stage: RAI NL-19-1203, Response to Request to Additional Information Regarding Application to Adopt National Fire Protection Association Standard 8052019-10-0707 October 2019 Response to Request to Additional Information Regarding Application to Adopt National Fire Protection Association Standard 805 Project stage: Request ML20066F5922020-06-11011 June 2020 Issuance of Amendments Nos. 304 and 249, Regarding License Amendment Request to Adopt NFPA-805 Performance Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition) Project stage: Approval ML20167A0132020-06-17017 June 2020 Correction of Amendments Nos. 304 & 249 License Amendment Request to Adopt NFPA-805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 EPID L-2018-LLA-0107 Project stage: Other 2019-10-07
[Table View] |
Similar Documents at Hatch |
---|
Category:Letter
MONTHYEARML24292A1602024-10-22022 October 2024 Request for Withholding Information from Public Disclosure License Amendment Request to Revise Technical Specification Surveillance Requirements to Increase Safety/Relief Valve Setpoints ML24290A0792024-10-18018 October 2024 SLR Environmental Preapplication Meeting Summary IR 05000321/20244012024-10-10010 October 2024 Security Baseline Inspection Report 05000321-2024401 and 05000366-2024401 ML24256A0282024-09-12012 September 2024 2024 Hatch Requal Inspection Corporate Notification Letter NL-23-0930, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-09-11011 September 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 NL-24-0334, 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc2024-09-0303 September 2024 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc IR 05000321/20240912024-08-27027 August 2024 NRC Investigation Report 2-2023-003 and NOV - NRC Inspection Report 05000321/2024091 and 05000366/2024091 IR 05000321/20240052024-08-26026 August 2024 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 and 2 - Report 05000321/2024005 and 05000366/2024005 NL-24-0313, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information2024-08-23023 August 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information IR 05000321/20240022024-08-0808 August 2024 Edwin I Hatch Nuclear Plants, Units 1 and 2 – Integrated Inspection Report 05000321-2024002 and 05000366-2024002 NL-24-0290, Response to Request for Additional Information Related to Request for Specific Exemption2024-07-26026 July 2024 Response to Request for Additional Information Related to Request for Specific Exemption NL-24-0276, Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-07-26026 July 2024 Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 ML24198A1252024-07-16016 July 2024 Edwin I Hatch Nuclear Plant Units 1 - 2 Notification of Conduct of Title 10 of the Code of Federal Regulations 50 NL-24-0260, Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R312024-07-0909 July 2024 Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R31 NL-24-0240, Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link2024-07-0303 July 2024 Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link NL-24-0237, Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications2024-07-0303 July 2024 Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0239, Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-1392024-06-17017 June 2024 Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-139 ML24163A0532024-06-14014 June 2024 Audit Plan - Alternative Seismic Method LAR ML24149A0492024-06-0404 June 2024 SNC Fleet - Regulatory Audit in Support of Review of the License Amendment Request to Revise TS 1.1, Use and Application Definitions, and Add New Technical Specification 5.5.21 and 5.5.17, Online Monitoring Program, NL-24-0148, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-06-0404 June 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations IR 05000321/20240902024-05-15015 May 2024 NRC Inspection Report 05000321-2024090 and 05000366-2024090, Investigation Report 2-2023-003; and Apparent Violation NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 NL-24-0166, Manual Reactor Trip Due to Loss of Feedwater2024-05-0909 May 2024 Manual Reactor Trip Due to Loss of Feedwater NL-24-0195, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water.2024-05-0707 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water. NL-24-0064, Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.52024-05-0303 May 2024 Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.5 NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 IR 05000032/20240112024-04-25025 April 2024 Notification of Edwin I. Hatch Nuclear Plant - Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 0500032/2024011 and 05000366/2024011 NL-24-0157, Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications2024-04-24024 April 2024 Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications IR 05000321/20240012024-04-22022 April 2024 Integrated Inspection Report 05000321/2024001 and 05000366/2024001 NL-24-0026, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint2024-04-19019 April 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint NL-24-0144, Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La)2024-04-0909 April 2024 Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La) NL-24-0115, Response to Request for Additional Information Exemption Requests for Physical.2024-04-0404 April 2024 Response to Request for Additional Information Exemption Requests for Physical. NL-24-0116, Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred.2024-03-29029 March 2024 Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred. NL-24-0062, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-03-12012 March 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML24069A0012024-03-0909 March 2024 – Correction of Amendment No. 266 Regarding License Amendment Request Regarding Relocation of Specific Surveillance Frequencies to a Licensee-Controlled Program (TSTF-425, Revision 3) NL-24-0089, Correction of Technical Specification Omission2024-03-0909 March 2024 Correction of Technical Specification Omission ML24047A0362024-03-0404 March 2024 Response to Hatch and Vogtle FOF Dates Change Request (2025) NL-24-0061, Cycle 32 Core Operating Limits Report Version 12024-03-0101 March 2024 Cycle 32 Core Operating Limits Report Version 1 IR 05000321/20230062024-02-28028 February 2024 Annual Assessment Letter Edwin I. Hatch Nuclear Plant Units 1 and 2 - Nrc Inspection Report 05000321/2023006 and 05000366/2023006 NL-24-0067, 10 CFR 72.48(d)(2) Biennial Report2024-02-26026 February 2024 10 CFR 72.48(d)(2) Biennial Report NL-24-0051, License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-02-20020 February 2024 License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0042, Response to Request for Additional Information Exemption Requests for Physical Barriers2024-02-13013 February 2024 Response to Request for Additional Information Exemption Requests for Physical Barriers NL-24-0033, Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers2024-02-0505 February 2024 Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers IR 05000321/20230042024-01-31031 January 2024 Integrated Inspection Report 05000321/2023004 and 05000366/2023004 NL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. 2024-09-09
[Table view] |
Text
Ms. Cheryl A. Gayheart Regulatory Affairs Director UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 22, 2018 Southern Nuclear Operating Company, Inc. P. 0. Box 1295, Bin 038 Birmingham, AL 35201-1295
SUBJECT:
EDWIN I. HATCH NUCLEAR PLANT, UNIT NOS. 1 AND 2 -ONLINE REFERENCE PORTAL FOR LICENSE AMENDMENT REQUEST TO ADOPT NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 (EPID L-2018-LLA-0107)
Dear Ms. Gayheart:
By application dated April 4, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18096A936), Southern Nuclear Operating Company (SNC or the licensee) submitted a license amendment request for the Edwin I. Hatch Nuclear Plant, Unit Nos. 1 and 2. In the license amendment request, SNC proposes to adopt National Fire Protection Association Standard 805 (NFPA 805), "Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants," 2001 Edition (ADAMS Accession No. ML010800360), as an alternative to compliance with existing fire protection program requirements.
To improve the efficiency of the U.S. Nuclear Regulatory Commission (NRC) reviews, the NRC staff and SNC staff have discussed the use of an online reference portal that would allow the NRC staff and contractors limited read-only access to the basis documents and other reference materials cited in the application.
In a meeting summary dated December 20, 2011 (ADAMS Accession No. ML113340218), the NRC staff described the portal process for NFPA 805 reviews. The online reference portal would allow the NRC staff to audit basis documents to determine whether the information included in the documents support the application.
Documents identified as necessary for analysis of the application will be identified by the NRC staff. The licensee will be formally requested to submit those documents on the NRC docket. Use of the online reference portal is acceptable, as long as the following conditions are met:
- The online reference portal will be password-protected and passwords will be assigned to those directly involved in the review on a need-to-know basis;
- The online reference portal will be sufficiently secure to prevent staff from printing, saving, or downloading any documents; and
- Conditions of use of the online reference portal will be displayed on the login screen and will require concurrence by each user. The NRC staff requests that the portal be populated with the documents listed in the enclosure to this letter. This will help the NRC staff in preparing for any site audits and will enhance the effectiveness of the staff's review of the application.
C. Gayheart A list of the NRC staff and contractors requiring portal access will be transmitted separately.
Please provide access to the portal, including usernames and passwords, to the designated NRC staff and contractors as soon as possible upon receipt of the list. The conditions associated with the online reference portal must be maintained throughout the duration of the review process. Please also provide written confirmation that SNC agrees to the terms and conditions set forth in this letter. If you have any questions, please contact me at (301) 415-4032.
Docket Nos. 50-321 and 50-366
Enclosure:
Generic List of SharePoint Portal Requested Documents for NFPA 805 cc: Listserv Sincerely, >>~;?./~ emes R. Hall, Senior Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation GENERIC LIST OF SHAREPOINT PORTAL REQUESTED DOCUMENTS FOR NFPA 805 1. National Fire Protection Association (NFPA) Code Deviations and Justifications
- 2. All applicable Probabilistic Risk Assessment (PRA) Peer Review Reports 3. All site calculations referenced in the License Amendment Request 4. Credited Fire Protection (FP) System and Feature Drawings a. Layout Drawings:
fire barriers, installed fire detection and suppression systems, fire areas, fire zones, stairwells, fire doors, fire dampers, etc. b. Piping and Instrumentation Diagrams (P&IDs): FP Water System c. System Descriptions for Fire Suppression, Water Supply, and Detection (including incipient or very early warning fire detection)
- d. Hydraulic Calculations for Fire Service and Fire Suppression System Water Demand (if used to support non-fire water use in Title 1 O of the Code of Federal Regulations, paragraph 50.48(c)(2)(vii))
- 5. Drawings related to systems credited in the Nuclear Safety Capability Assessment (NSCA) as well as those required to fully understand plant response:
- a. P&IDs: Reactor Coolant System, Main Steam, Main Feedwater, Circulating Water, Service Water, etc. b. Safe Shutdown/NSCA Logic Diagrams (if used) c. Electrical Distribution System One-Lines (alternating current and direct current) 6. Those documents that fulfill the NFPA 805 requirement for "Design Basis Document (DBD)" a. Fire Area Calculations (e.g. Fire Safety Analyses, Fire Risk Analyses, Plant Change Evaluations, Fire Risk Evaluations)
- b. NSCA Calculation (Safe Shutdown/Circuit Analysis)
- c. Multiple Spurious Operation Expert Panel Report d. Thermo-hydraulic Analysis serving as the basis for Variance from Deterministic Requirements (VFDR) and recovery action timing e. Evaluation of Recovery Actions for feasibility
- f. Fire Hazards Analysis (if separate from the fire area calculations) g. Non-Power Operation Calculation(s)
- h. Radioactive Release Calculation(s)
- i. Pre-fire Plans 7. Fire PRA Calculations
- a. Plant Boundary/Partitioning Methods and Results (TASK 1) b. Component Selection Calculation (TASK 2) c. Cable Selection and Circuit Analysis (TASKS 3, 9, and 10) d. Ignition Frequency Calculation (TASK 6) e. Fire PRA Quantification Calculations (TASK 5) including:
- i. Seismic Fire Interactions (TASK 13) Methodologies and results (including assumptions) ii. Screening Methodologies and Results (TASKS 4 and 7) (including assumptions) iii. Fire Risk Quantifications (TASK 14) Methodologies and Results (including assumptions) iv. Multi-compartment Screening and Analysis v. Post-fire Human Reliability Analysis Methodologies and Results (including assumptions) (TASK 12) vi. Detailed proposed modification descriptions (Engineering Change Requests/Records) sufficient to comprehend potential impact/improvement to Fire PRA f. NFPA 805 Application Calculation (provides all the delta risk calculations for VFDRs) g. Control Room Risk Calculation
- h. Uncertainty and Sensitivity Calculations (TASK 15) i. Fire Modeling Calculations used to support the Fire PRA (zone of influence (ZOI), hot gas layer, bounding, detailed fire modeling, etc.) ii Plant Specific Verification and Validation (V&V) Analysis iii. Non-public V&V References (e.g., Electric Power Research Institute (EPRI) Fire Modeling, Generic Treatment) iv. Fire Modeling Assumptions and Calculations performed to support target selection (e.g.; ZOI, secondary fires, transient combustible/ignition sources) including those that deviate from NUREG/CR-6850 (TASKS 8 and 11) 8. Fire Modeling used in the Fire Modeling Performance-based Approach a. Plant Specific V&V Analysis performed
- b. Non-public V&V References (e.g., EPRI Fire Modeling, Generic Treatments)
- c. Fire Modeling Assumptions and Calculations performed to support Based Evaluations (e.g., ZOI, secondary fires, transient combustible/ignition sources) considered outside NUREG/CR 6850 Assumptions and Parameters (TASKS 8 and 11) d. Hot Gas Layer Determination Calculations (including assumptions)
- 9. Fire Protection Program Manual 10. Fire Protection Quality Assurance Program (including FP Structure System Components and FP Features)
- 11. NFPA 805 Monitoring Program Calculations and Procedures
- 12. Technical Requirements Manual 13. Updated Final Safety Analysis Report (UFSAR) Changes (including current UFSAR Section 9.5.1, "Fire Protection Program," and Section 7.4, "Systems Required for Safe Shutdown")
C. Gayheart
SUBJECT:
EDWIN I. HATCH NUCLEAR PLANT, UNIT NOS. 1 AND 2 -ONLINE REFERENCE PORTAL FOR LICENSE AMENDMENT REQUEST TO ADOPT NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 (EPID L-2018-LLA-0107)
DATED AUGUST 22, 2018 DISTRIBUTION:
PUBLIC RidsNrrDraAplb Resource RidsACRS_MailCTR Resource RidsNrrDorlLpl2-1 Resource RidsNrrLAKGoldstein Resource RidsNrrPMHatch Resource RidsRgn2Mail Center Resource BMetzger SDinsmore RidsNrrDraApla Resource RidsNrrDssStsb Resource RidsNrrDraArcb Resource JRobinson JHyslop AWu Nlqbal MSmith TDinh ADAMS Accession No. ML18228A835
- via e-mail OFFICE DORULPL2-1/PM DORULPL2-1
/LA DRA/APLB/BC*
DORL/LPL2-1
/BC NAME JHall KGoldstein GCasto MMarkley DATE 8/20/18 08/20/18 8/21/18 8/22/18 OFFICIAL RECORD COPY DORULPL2-1
/PM JHall 8/22/18