2015 Point Beach Nuclear Plant Initial License Examination Form ES-201-1
ML15083A059
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 03/06/2015
From: McNeil D R
NRC/RGN-III/DRS/OLB
To:
Florida Power & Light Energy Point Beach
References
Download: ML15083A059 (1)


Text

ES-201, Rev. 9 Examination Preparation Checklist Form ES-201-1 Facility:

Point Beach Nuclear Power Plant Date of Examination:

0 3/04/20 1 5 Developed by: Written

- Facility NRC // Operating

- Facility NRC n/a Target Date* Task Description (Reference)

Chief Examiner=s Initials -180 1. Examination administration date confirmed (C.1.a; C.2.a and b) dm -120 2. NRC examiners and facility contact assigned (C.1.d; C.2.e) dm -120 3. Facility contact briefed on security and other requirements (C.2.c) dm -120 4. Corporate notification letter sent (C.2.d) dm [-90] [5. Reference material due (C.1.e; C.3.c; Attachment 2)]

dm {-75} 6. Integrated examination outline(s) due, including Forms ES

-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and ES-401-4, as applicable (C.1.e and f; C.3.d) dm {-70} {7. Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e)}

dm {-45} 8. Proposed examinations (including written, walk

-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, and any Form ES-201-3 updates), and reference materials due (C.1.e, f, g and h; C.3.d) dm -30 9. Preliminary license applications (NRC Form 398s) due (C.1.l; C.2.g; ES-202) dm -14 10. Final license applications due and Form ES

-201-4 prepared (C.1.l; C.2.i; ES-202) dm -14 11. Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f) dm -14 12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) dm -7 13. Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h) dm -7 14. Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; Attachment 4; ES

-202, C.2.e; ES

-204) dm -7 15. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k) dm -7 16. Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i) dm

  • Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case

-by-case basis in coordination with the facility licensee.

[Applies only] {Does not apply} to examinations prepared by the NRC.