MONTHYEARML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24122C6922024-05-0101 May 2024 NextEra Fleet EP Amendment - Demonstration Drill ML23109A1862023-04-19019 April 2023 And Turkey Point – Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML22067A0922022-03-0303 March 2022 State Consultation - Duane Arnold ISFSI-Only EP License Amendment ML22040A1162022-02-0808 February 2022 Email to G. Van Noordennen Zion and La Crosse Review Schedule Changes ML22027A3582022-01-26026 January 2022 DAEC: CY2022 Inspection Plan, Docket No: 05000331, License No: DPR-49 ML22007A3102022-01-0505 January 2022 State Consultation - Draft No Significant Hazards Determination Regarding a LAR for NextEra Energy Duane Arnold, LLC, Duane Arnold Energy Center ISFSI in Palo, Iowa ML22005A0992022-01-0404 January 2022 Email from a Snyder to a Leek Re State Consultation - Draft No Significant Hazards Determination - License Amend. Req. for NextEra Energy, LLC, DAEC ISFSI in Palo, Iowa ML22005A0862022-01-0404 January 2022 1-4-2022 Email Communication to Duane Arnold Regarding Its ISFSI Related Exemption Request on Supplemental Information Needed ML22005A1012022-01-0404 January 2022 Email from a Leek to a Snyder Re State Consultation - Draft No Significant Hazards Determination - License Amend. Req. for NextEra Energy, LLC, DAEC ISFSI in Palo Iowa ML22004A0122022-01-0303 January 2022 E-mail from M. Davis, NextEra, to A. Snyder, NRC, - Duane Arnold Energy Center - Supplement Information to Technical Specification Amendment Application ML21354A6722021-12-17017 December 2021 Email to State of Iowa - Draft EA on Duane Arnold Exemption ML21214A0502021-08-0101 August 2021 Acceptance of License Amendment Request to Adopt an ISFSI-Only Physical Security Plan ML21214A0482021-08-0101 August 2021 Acceptance of License Amendment Request to Adopt an ISFSI-Only Emergency Plan ML21165A1212021-06-10010 June 2021 E-mail from M. Davis, Duane Arnold, to M. Doell and R. Edwards, NRC - Duane Arnold Defueled Emergency Plan Implementation Confirmation ML21117A2752021-04-26026 April 2021 Acceptance of Updated Spent Fuel Management Plan ML21089A2092021-03-19019 March 2021 Spent Fuel Pattern Procedure ML21068A3352021-03-0707 March 2021 Acceptance of License Amendment Request to Adopt ISFSI-Only Technical Specifications ML21056A2172021-02-17017 February 2021 Acceptance of License Amendment Request to Revise the Physical Security Plan Requirements ML21032A1852021-02-0101 February 2021 Daec_ CY2021 Inspection Plan ML21006A4052021-01-0606 January 2021 NRR E-mail Capture - Final RAI - Duane Arnold - Post-Shutdown Decommissioning Activities Report ML20338A0032020-12-0101 December 2020 Letter from EPRI to Mr. Scott Wall, BWRVIP 2020-100, 288 Surveillance Capsule Test Results Report ML20316A0212020-11-10010 November 2020 NRR E-mail Capture - Final RAI - Duane Arnold - Duane Arnold Amendment for Proposed Defueled EP and EAL Scheme ML20289A3522020-10-14014 October 2020 NRR E-mail Capture - Duane Arnold Energy Center -Acceptance of Requested Licensing Action, One-Time Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Pandemic (EPID No. L-2020-LLE-01 ML20153A3772020-05-28028 May 2020 NRR E-mail Capture - Request for Additional Information - Duane Arnold Energy Center Quality Assurance Topical Report (FPL-3) - EPID L-2020-LLQ-0002) ML20154K6202020-05-27027 May 2020 COVID-19 Preparedness Assessments for FEMA Region VII Duane Arnold Energy Center (DAEC) and Quad Cities Generating Station (Qcgs) ML20141L8132020-05-19019 May 2020 NRR E-mail Capture - Request for Additional Information - Duane Arnold Energy Center (DAEC) - Exemption Request for Security Training Requirements Due to COVID-19 Pandemic - EPID L-2020-LLE-0042 to 45, L-2020-LLE-0051 ML20129J8282020-05-0606 May 2020 NRR E-mail Capture - LIC-109 Acceptance Review of Duane Arnold Request for Exemption from Portions of 10 CFR 50.47 and Appendix E - EPID L-2020-LLE-0023 ML20127H8662020-05-0505 May 2020 NRR E-mail Capture - Duane Arnold Energy Center (DAEC) - Request for Additional Information (RAI) - Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 1O CFR 50.75(h)(1)(iv) - EPID L-2020-LLE-0011 ML20122A1152020-04-30030 April 2020 NRR E-mail Capture - Duane Arnold Energy Center -Acceptance of Post-Shutdown Decommissioning Activities Report ML20087F2872020-03-26026 March 2020 NRR E-mail Capture - LIC-109 Acceptance Review of Duane Arnold Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 1O CFR 50.75(h)(1)(iv) - EPID L-2020-LLE-0011 ML20129J8322020-03-19019 March 2020 NRR E-mail Capture - (External_Sender) Teleconference with Nextra Energy - Duane Arnold Physical Security Plan LIC-109 Review Status ML20022A3602020-01-22022 January 2020 NRR E-mail Capture - Duane Arnold Energy Center - Acceptance of Requested Licensing Action, Proposed Partial Exemption from Record Retention Requirements ML19352G6872019-12-11011 December 2019 12-11-19 Email to FEMA: Response to FEMA Questions on Proposed DAEC Emergency Plan ML19302G9732019-10-29029 October 2019 NRR E-mail Capture - LIC-109 Acceptance of Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR- 186): Removal of License Condition 2.C.(3), Fire Protection Program - EPID L-2019-LLA-0211 ML19302G3212019-10-29029 October 2019 LIC-109 Acceptance of Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR- 186) - Removal of License Condition 2.C.(3), Fire Protection Program - EPID L-2019-LLA-0211 ML19280A0352019-10-0404 October 2019 NRR E-mail Capture - Final - RAI Related to License Amendment Request (TSCR-182) for Proposed Changes to the Emergency Plan for Permanently Defueled Conditions at Duane Arnold Energy Center (DAEC) - L-2019-LLA-0075 ML19206A2182019-07-25025 July 2019 NRR E-mail Capture - LIC-109 Acceptance of Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR-183) - Application to Revise Operating License and TS for Permanently Defueled Condition - EPID L-2019-LLA-0130 ML19183A0172019-06-26026 June 2019 NRR E-mail Capture - LIC-109 Acceptance of Request for Change in the BWRVIP Integrated Surveillance Program Test Schedule to Accommodate Early Closure of the Duane Arnold Energy Center - EPID L-2019-LRO-0042 ML19122A4882019-04-29029 April 2019 NRR E-mail Capture - LIC-109 Acceptance of License Amendment Request (TSCR-182) for Duane Arnold Energy Center (DAEC) - Proposed Changes to the Emergency Plan for Permanently Defueled Condition - EPID L-2019-LLA-0075 ML19086A3502019-03-27027 March 2019 NRR E-mail Capture - LIC-109 Acceptance of the Request for Exemption from 10 CFR 73.55(p)(1)(I) and 10 CFR 73.55(p)(1)(ii) for Duane Arnold Energy Center - EPID L-2019-LLE-0003 ML19064A2032019-03-0404 March 2019 NRR E-mail Capture - Results of LIC-109 Acceptance Review - Duane Arnold Energy Center - Request for Approval of Certified Fuel Handler Training Program, EPID L-2019-LLL-0003 ML18283B0522018-10-0909 October 2018 NRR E-mail Capture - Final Second Round - Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - LAR TSCR-166, Adoption of EAL Scheme Pursuant to NEI 99-01 - EPID L-2017-LLA-0420 ML18255A2922018-09-11011 September 2018 NRR E-mail Capture - Draft Second Round - Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - LAR TSCR-166, Adoption of EAL Scheme Pursuant to NEI 99-01 - EPID L-2017-LLA-0420 ML18166A2982018-06-15015 June 2018 NRR E-mail Capture - Draft Request for Additional Information (RAI) - Duane Arnold Energy Center (DAEC) - LAR TSCR-166, Adoption of EAL Scheme Pursuant to NEI 99-01 - EPID L-2017-LLA-0420 ML18108A3102018-04-12012 April 2018 NRR E-mail Capture - Audit at NextEra Headquarters, Juno Beach, Florida - April 24, 2018 Through April 26, 2018 - 50.69 LARs for Duane Arnold Energy Center (Daec), and Point Beach Nuclear Plant (Pbnp), Units 1 and 2 - EPIDs L-2017-LLA-0283/ ML18088A0102018-03-28028 March 2018 NRR E-mail Capture - Final RAI for Duane Arnold (DAEC) 5th-10 Year ISI (RR-05) ML18037B0032018-02-0606 February 2018 NRR E-mail Capture - Draft Request for Additional Information - Duane Arnold Energy Center (DAEC) - License Amendment Request (TSCR-170), Revision to Technical Specification 3.5.1, ECCS-Operating - EPID L-2017-LLA-0288 ML18025A2362018-01-24024 January 2018 NRR E-mail Capture - Resent - LIC-109 Acceptance - Duane Arnold LAR (TSCR-166) - Adoption of Emergency Action Level (EAL) Scheme Pursuant to NEI 99-01, Revision 6, Development of EALs for Non-Passive Reactors ML18023A0752018-01-22022 January 2018 NRR E-mail Capture - LIC-109 Acceptance - Duane Arnold License Amendment Request (LAR) (TSCR-179) - Application to Add Technical Specification 3.2.3, Linear Heat Generation Rate - EPID: L-2017-LLA-0436 2024-09-04
[Table view] |
Text
1 NRR-PMDAPEm Resource From:Feintuch, Karl Sent: Friday, June 14, 2013 5:21 PM To: Bob.Murrell@nexteraenergy.com; Swenzinski, Laura Cc: Faria-Ocasio, Carolyn
Subject:
ME6818-DAEC- Adoption of NFPA 805- Request fo r Additional Information (RAI) FPE 14 Follow Up Flag:
Follow up Due By: Monday, July 01, 2013 1:30 PM Flag Status:
FlaggedBy letter to the U.S. Nuclear Regulatory Commission (NRC) dated August 5, 2011 (Agencywide Documents Access and Management System Accession No. ML11221A280), NextEra Energy Duane Arnold, LLC (the Licensee) submitted a license amendment request (LAR). The licensee requested to transition their fire protection licensing basis at the Duane Arnold Energy Center (DAEC), from Title 10 of the Code of Federal Regulations (CFR), Section 50.48(b), to 10CFR50.48(c), National Fire Protection Association Standard 805 (NFPA 805).
The NRC staff is reviewing your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed below. A clarification call was held with your staff on June 10, 2013.
Attending the June 10, 2013 conference call were:
- For DAEC - Laura Swenzinski, William Cross, Jeff Kuehl, Roy Hanson, Thomas Carmody, and Mike Saunders (ERIN Eng)
Fire Protection Request for Additional Information (RAI) FPE 14 With regards to how DAEC complies with the requirements of NFPA 805 Section 3.11.5:
- 1. There appears to be discrepancies between LAR Attachment A, Table 4-3 and Attachment C with regard to Electrical Raceway Fire Barrier Systems (ERFBS) credited at DAEC. Attachment A, Element 3.11.5, Electrical Raceway Fire Barrier Systems (ERFBS) (page 138 of 138), states that DAEC complies with the requirement and states that "Limited amounts of Darmat KM1 are utilized for ERFBS at DAEC". This product was tested to meet Generic Letter 86-10 Supplement 1". No other ERFBS is discussed.
However , Table 4-3, NFPA 805 Ch 4 Required FP Systems/Features and Attachment C, NEI 04-02 Table B Fire Area Transition both discuss an additional 3-hour ERFBS.
- Table 4-3, Fire Area TB1, Turbine Building, Fire Zones ID 07C (page 64) and 07H (page 66) list "Concrete Chase - Separation Required to protect cables for RHR Service Water, River Water, ESW and Division 2 AC Power."
- Attachment C, Fire Area TB1 (page 154 of 165), under Performance Goal 4, Vital Auxiliaries - Mechanical, includes a Comment "Feeders and control power to portions of the Div 2 electrical distribution credit a 3 hr ERFBS."
2* Attachment C, Fire Area TB1 (page 154 of 165), under Performance Goal 4, Vital Auxiliaries - Electrical includes a Comment "Div 2 RHRSW pumps, Div 2 River Water pumps and Div 2 ESW pump credit a 3 hr ERFBS."
- Attachment C, Fire Area TB1 (page 163 of 165), Required Fire Protection Systems and Features table lists "Passive, Concrete Chase, Separati on, Required to protect cables for RHR Service Water, River Water, ESW and Division 2 AC Power." Any ERFBS credited to meet NFPA 805 separation requirements using either a deterministic approach under NFPA 805 Section 4.2.3 or a performance-based approach under NFPA 805 Section 4.2.4 must meet the ERFBS requirements of NFPA 805 Section 3.11.5.
Provide additional information regarding the compliance status of the "concrete chase" used as an ERFBS in the Turbine Building with regard to NFPA 805 Section 3.11.5. Discuss the testing performed on this ERFBS, including the test rating obtained.
- 2. Attachment A, Element 3.11.5, Electrical Raceway Fire Barrier Systems (ERFBS), states that DAEC complies with the requirement and states that "Limited amounts of Darmat KM1 are utilized for ERFBS at DAEC. This product was tested to meet Generic Letter 86-10 Supplement 1." There is no discussion regarding the results of the testing. NFPA 805 Section 3.11.5 states that "TheERFBS needs to adequately address the design requirements and limitations of supports and intervening items and their impact on the fire barrier system rating. The fire barrier's ability to maintain the required nuclear safety circuits free of fire damage for a specific thermal exposure, barrier design, raceway size and type, cable size, fill and type shall be demonstrated."
Provide a discussion on the results of the fire barrier testing performed in accordance with Generic Letter 86-10, Supplement 1 to meet NFPA 805 Section 3.11.5.
It was agreed that you would provide a response by July 3, 2013. The NRC considers that timely responses to requests for additional information help ensure sufficient time is available for the NRC staff review and contribute toward the NRC's goal of efficient and effective use of staff resources. Please contact Carolyn Faría at (301) 415-4050, if you have any questions.
Sincerely, Karl Feintuch
Project Manager USNRC Hearing Identifier: NRR_PMDA Email Number: 725 Mail Envelope Properties (26E42474DB238C408C94990815A02F09CAC511BA41)
Subject:
ME6818-DAEC- Adoption of NFPA 805- Request for Additional Information (RAI) FPE 14 Sent Date: 6/14/2013 5:21:10 PM Received Date: 6/14/2013 5:21:12 PM From: Feintuch, Karl Created By: Karl.Feintuch@nrc.gov Recipients: "Faria-Ocasio, Carolyn" <Carolyn.Faria-Ocasio@nrc.gov> Tracking Status: None "Bob.Murrell@nexteraenergy.com" <Bob.Murrell@nexteraenergy.com> Tracking Status: None "Swenzinski, Laura" <Laura.Swenzinski@fpl.com> Tracking Status: None Post Office: HQCLSTR01.nrc.gov
Files Size Date & Time MESSAGE 4894 6/14/2013 5:21:12 PM
Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: Follow up By 7/1/2013 1:30:00 PM