MONTHYEARIR 05000321/20230042024-01-31031 January 2024 Integrated Inspection Report 05000321/2023004 and 05000366/2023004 NL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. ML24012A0652024-01-30030 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000321/20233012024-01-17017 January 2024 NRC Operator License Examination Report 05000321/2023301 and 05000366/2023301 ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) NL-23-0889, Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems2023-12-0606 December 2023 Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems IR 05000321/20234022023-11-29029 November 2023 Security Baseline Inspection Report 05000321/2023402, 05000366/2023402, and 07200036/2023401 NL-23-0879, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0841, Update to Notice of Intent to Pursue Subsequent License Renewal2023-11-20020 November 2023 Update to Notice of Intent to Pursue Subsequent License Renewal IR 05000321/20230112023-11-17017 November 2023 Biennial Problem Identification and Resolution Inspection Report 050003212023011 and 050003662023011 ML23324A4472023-11-14014 November 2023 302 Exam Approval Letter IR 05000321/20230032023-11-0202 November 2023 Integrated Inspection Report 05000321/2023003, and 05000366/2023003 IR 05000321/20234032023-10-26026 October 2023 Cyber Security Inspection Report 05000321/2023403 and 05000366/2023403 IR 05000321/20234012023-10-17017 October 2023 Security Baseline Inspection Report 05000321 2023401 and 05000366 2023401 ML23250A0472023-09-20020 September 2023 Request for Additional Information Regarding License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts in Technical Specifications Table 1.1-1, Modes ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report IR 05000321/20230052023-08-27027 August 2023 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 & 2 - Report 05000321/2023005 and 05000366/2023005 NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 IR 05000321/20230022023-08-0808 August 2023 Integrated Inspection Report 07200036/2023001, 05000321/2023002, and 05000366/2023002 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML23202A1122023-08-0202 August 2023 Units, 1 and 2; and Vogtle Units 1 and 2 - Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23201A0292023-07-20020 July 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement ML23178A0012023-06-27027 June 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000321 2023403 and 05000366 2023403 NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use IR 05000321/20230102023-06-0909 June 2023 Focused Engineering Inspection Report 05000321 2023010 and 05000366 2023010 NL-23-0422, Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R272023-05-30030 May 2023 Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R27 NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. ML23136B2942023-05-19019 May 2023 Summary of May 02, 2023, Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a LAR for the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plant, Units 1 and 2 NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 ML23123A2222023-05-0101 May 2023 Notification of Licensed Operator Initial Examination 05000321/2023301, and 05000366/2023301 IR 05000321/20230012023-04-26026 April 2023 Integrated Inspection Report 05000321/2023001 and 05000366/2023001 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 NL-23-0019, GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2023-04-12012 April 2023 GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI NL-23-0263, Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report2023-04-0505 April 2023 Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report NL-23-0014, Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding2023-03-29029 March 2023 Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding NL-23-0208, Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update2023-03-29029 March 2023 Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update NL-23-0228, Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21)2023-03-20020 March 2023 Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21) NL-23-0179, National Pollutant Discharge Elimination System (NPDES) Permit Renewal2023-03-13013 March 2023 National Pollutant Discharge Elimination System (NPDES) Permit Renewal ML23065A1092023-03-0808 March 2023 Correction of Relief Request HNP-ISI-RR-05-02 Allowing to Continue Operation with a Flaw Indication on One Reactor Pressure Vessel Closure Bolt Until December 31, 2025 ML23053A2182023-03-0303 March 2023 Correction of Amendment Nos. 321 and 266 Regarding License Amendment Request to Revise the (National Fire Protection Association) NFPA-805 Fire Protection Program IR 05000321/20220062023-03-0101 March 2023 Annual Assessment Letter Edwin I. Hatch Nuclear Plant, Units 1 and 2 - NRC Inspection Report 05000321/2022006 and 05000366/2022006 NL-23-0101, Cycle 28 Core Operating Limits Report Version 12023-02-23023 February 2023 Cycle 28 Core Operating Limits Report Version 1 ML23034A2462023-02-21021 February 2023 Audit Summary for License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs ML22363A3932023-02-15015 February 2023 Issuance of Amendments Nos. 321 and 266, Regarding License Amendment Request to Revise the (National Fire Protection Association) NFPA-805 Fire Protection Program ML22346A1482023-02-0909 February 2023 Issuance of Amendments 320 and 265, Regarding LAR to Revise Technical Specifications to Adopt TSTF-208 and Administrative Correction for Duplicate Technical Specifications 3.4.10 2024-01-31
[Table view] |
Text
Southern Nuclear Operating Company, Inc. Post Office Box 1295 Birmingham, Alabama 35201 -1 295 August 3, 2007 Docket No.: 50-321 COMPANY Energy to Serve Your Worldsu U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant - Unit 1 Response to Request for Additional lnformation Concerning Projected Fluence Values for the Limitina Circumferential Weld Ladies and Gentlemen: Pursuant to your request for additional information of July 6, 2007 Southern Nuclear Operating Company (SNC) hereby provides its response concerning the projected fluence values for the limiting circumferential weld. ISI-ALT-8 (letter NL-07-0270, dated March 8,2007) was submitted to extend the authorization for the elimination of the RPV circumferential shell weld examinations required by ASME Code through the renewed license period of extended operation (PEO) at Plant Hatch-Unit
- 1. NRC's request for additional information and SNC's response are provided in the enclosure to this letter. This letter contains no NRC commitments.
If you have any questions, please advise. B. J. ~eoj~e Manager, Nuclear Licensing
Enclosure:
Restatement of NRC Request for lnformation and SNC Response for Plant Hatch - Unit 1 Concerning Projected Fluence Values for the Limiting Circumferential Weld U. S. Nuclear Regulatory Commission NL-07-1491 Page 2 cc: Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. D. R. Madison, Vice President - Hatch Mr. D. H. Jones, Vice President - Engineering RTYPE: CHA02.004 U. S. Nuclear Regulatory Commission Dr. W. D. Travers, Regional Administrator Mr. R. E. Martin, NRR Project Manager - Hatch Mr. J. A. Hickey, Senior Resident Inspector - Hatch Edwin I. Hatch Nuclear Plant - Unit 1 Response to Request for Additional lnformation Concerning Projected Fluence Values for the Limiting Circumferential Weld Enclosure Restatement of NRC Request for lnformation and SNC Response for Plant Hatch - Unit 1 Enclosure Restatement of NRC Request for lnformation and SNC Response for Plant Hatch - Unit 1 Concerning Projected Fluence Values for the Limiting Circumferential Weld Restatement of NRC Request for Additional Information Pursuant to Title 10 of the Code of Federal Regulations (1 0 CFR) 50.55a(a)(3)(i), Request for Alternative ISI-ALT-8 proposed an alternative to extend the authorization for the elimination of the Reactor Vessel (RV) circumferential shell weld examinations required by the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI through the end of the extended period of operation at Hatch 1. In its January 28, 2005 Safety Evaluation Report (SER) for your original relief request on this topic (RR-38), the NRC staff authorized the elimination of these circumferential shell weld examinations only through July 31, 2007. The staff approval of RR-38 for this limited duration was based on a finding that the neutron fluence values used in RR-38 to justify elimination of the RV circumferential weld examinations through the end of the extended period of operation were based on a fluence calculational methodology (RAMA) that had not yet been reviewed and approved by the NRC staff at that time. The use of the RAMA ,fluence methodology was subsequently reviewed and conditionally approved by the NRC in an SER dated May 13, 2005. The conditions for the application of the RAMA fluence methodology to the RV fluence calculations at Hatch 1 have been met. The staff requests that you confirm whether the projected fluence value for the limiting circumferential weld at the end of the extended period of operation at Hatch 1 (i.e., the fluence intended for use as a basis for the current request, ISI- ALT-08) is the same as that reported for Hatch 1 in Enclosure 1 of RR-38 for the period corresponding to 54 effective full power years (EFPY) of facility operation.
If the 54 EFPY fluence for Request ISI-ALT-8 is different than what was originally reported in Enclosure 1 of RR-38 for 54 EFPY, please provide an updated mean RTNDT value for the limiting Hatch 1 circumferential shell weld and compare it to the acceptance criterion for the circumferential weld RTNDT value specified for Combustion Engineering fabricated RVs in Table 2.6-5 of the July 28, 1998, NRC SER for the Boiling Water Reactor Vessel and lnternals Project (BWRVIP)-05 report, "BWR Vessel and lnternals Project, BWR Reactor Pressure Vessel Shell Weld Inspection Recommendations (BWRVIP-05)."
Enclosure Restatement of NRC Request for Information and SNC Response for Plant Hatch - Unit 1 Concerning Projected Fluence Values for the Limiting Circumferential Weld SNC Response for Plant Hatch - Unit 1 The projected fluence value calculated by RAMA for the limiting circumferential weld at the end of the period of extended operation (PEO) at Hatch 1 is higher than that previously reported for Hatch 1 in Enclosure 1 of Relief Request 38 (RR-38). As noted in the request for additional information (RAI), Relief Request RR-38, which used GE fluence methodology, was approved on a limited time basis (through July 2007) pending review and approval by the NRC of the RAMA fluence methodology. ISI-ALT-8 proposed a code alternative to examination of the circumferential welds that would extend through the PEO based on calculations using the RAMA methodology.
As shown in the table below, the fluence at the end of the PEO was previously stated in RR-38 as 0.236 x 10 n/cm2 while the RAMA calculated fluence used in ISI-ALT-8 at the end of the PEO is 0.296 x 10" n/cm2. 'The end of the PEO for Plant Hatch Unit 1 in RR-38 was based on an assumed 90% capacity factor, or 54 EFPY (effective full power years of operation).
For the RAMA calculations, a more detailed evaluation of the capacity factor was performed, which resulted in the end of the PEO being defined at 49.3 EFPY.
For comparison purposes, updated values for the limiting Hatch 1 circumferer~tial shell weld at the end of the PEO and the values specified for Combustion Engineering (CE) fabricated RVs in Table 2.6-5 of the July 28, 1998, NRC SER are shown in the below table. Also included for comparison are the values used as the basis for RR-38. As demonstrated in the table, the increase in projected fluence using the RAMA methodology has resulted in a slight increase in mean RTNDT at the end of the PEO (53.3 vs. 48.5).
However, the Hatch 1 RTNDT is still bounded by the mean RTNDT calculated using either CE(VIP) or CE(CE0G) chemistry data as provided in the 1998 NRC SER for BW RVl P-05.
Group Cu% Ni% CF Fluence (1 0 n/cm2) ARTNDT (OF) RTNDT(U) (OF) Mean RTNDT (OF) P(F/E) NRC P(F/E) BWRVIP CE(VIP) 64 EFPY (Table 2.6-5) 0.13 0.71 151.7 0.40 1 13.2 0 1 13.2 1.99E-4 --- CE(CE0G) 64 EFPY (Table 2.6-5) 0.183 0.704 172.2 0.40 128.5 0 128.5 4.38E-4 --- Hatch 1 End of PEO 54 EFPY (RR-38) (G E) 0.197 0.060 91 .O 0.236 48.5 -1 0 38.5 --- --- Hatch 1 End of PEO 49.3 EFPY (RAMA) 0.197 0.060 91 .O 0.296 53.3 -1 0 43.3 --- ---