Letter Sequence Response to RAI |
---|
|
|
MONTHYEARML12319A2782012-11-0101 November 2012 ASME Section XI Inservice Inspection Program Relief Request N1-I4-LMT-001 - Fourth Interval Period 1 Limited Examinations Project stage: Request ML12326A6172012-11-20020 November 2012 NRR E-mail Capture - Acceptance Review - North Anna 1 - Relief Request N1-I4-LMT-001-4th Interval Period 1 Limited Examinations Project stage: Acceptance Review ML13102A2982013-04-0505 April 2013 Response to Request for Additional Information ASME Section XI Inservice Inspection Program Relief Request N1-14-LMT-001 - Fourth Interval Period 1 Limited Examinations Project stage: Response to RAI ML13198A0912013-07-12012 July 2013 Response to Request for Additional Information ASME Section Xl Inservice Inspection Program Relief Request NI-14-LMT-001 - Fourth Interval Period 1 Limited Examinations Project stage: Response to RAI ML13226A3682013-07-17017 July 2013 NRR E-mail Capture - Clarification of Examination History of Weld SW-12 Project stage: Request ML13220A0562013-08-0707 August 2013 NRR E-mail Capture - Relief Request RAI from NRC Conference Call August 2 2013 Project stage: Request ML13234A3532013-08-30030 August 2013 Relief Request (RR) N1-I4-LMT-001, Limited Examinations for the Fourth Ten-Year Inspection Interval Period 1 Project stage: Other 2013-07-12
[Table View] |
|
---|
Category:Letter
MONTHYEARML24032A1112024-02-0101 February 2024 Owner'S Activity Report for North Anna, Unit 2, Refueling Outage N2R29 - First Period of the Fifth ISI Interval ML24032A4662024-01-16016 January 2024 Response to Comments on Draft Vpdes Permit No. VA0052451 ML24017A0802024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000338/2024301 and 05000339/2024301 ML24003A8372024-01-0909 January 2024 Letter to Elizabeth Toombs, Thpo, Cherokee Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8412024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8502024-01-0909 January 2024 Letter to Wenonah Haire, Thpo, Catawba Indian Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A7272024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8382024-01-0909 January 2024 Letter to G. Anne Richardson, Chief, Rappahannock Tribe, Inc., Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8482024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8392024-01-0909 January 2024 Letter to Gerald Stewart, Chief, Chickahominy Indian Tribe, Eastern Division Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8472024-01-0909 January 2024 Letter to Tom Jonathan, Chief, Tuscarora Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8492024-01-0909 January 2024 Letter to W. Frank Adams, Chief, Upper Mattaponi Tribe Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8462024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8352024-01-0909 January 2024 Letter to Acee Watt, Thpo, United Keetoowah Band of Cherokee Indians in Oklahoma Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8422024-01-0909 January 2024 Letter to Paul Barton, Thpo, Eastern Shawnee Tribe of Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8432024-01-0909 January 2024 Letter to Robert Gray, Chief, Pamunkey Indian Tribe, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8362024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8442024-01-0909 January 2024 Letter to Russell Townsend, Thpo, Eastern Band of Cherokee Indians ML24003A8402024-01-0909 January 2024 Letter to Katelyn Lucas, Thpo, Delaware Nation, Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8452024-01-0909 January 2024 Letter to Stephen Adkins, Chief, Chickahominy Indian Tribe, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML23332A1852024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A0872024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23360A6352024-01-0404 January 2024 Letter to Dominion Availability for North Anna Units 1 and 2 Draft Site Specific Environmental Impact Statement ML23332A1472023-12-21021 December 2023 Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23346A0972023-12-11011 December 2023 License Amendment Request to Revise the Emergency Plan Relocation of the Technical Support Center - Response to NRC Request for Additional Information ML23346A1022023-12-11011 December 2023 2024 North Anna Power Station Brq Inspection Notification Letter ML24012A0942023-12-0707 December 2023 GL Report from Dominion Virginia Power Regarding Transfer of Devices ML24012A0892023-12-0707 December 2023 GL Registration from Dominion Virginia Power ML23334A2432023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23362A0602023-11-29029 November 2023 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000339/20234022023-11-27027 November 2023 Security Baseline Inspection Report 05000338 and 05000339/2023402 IR 05000338/20230032023-11-13013 November 2023 Integrated Inspection Report 05000338/2023003 and 05000339/2023003 ML23311A2042023-10-0909 October 2023 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.d IR 05000338/20234032023-10-0505 October 2023 Reissue - North Anna Power Station - Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 (Cover Letter) ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23275A0992023-09-28028 September 2023 Subsequent License Renewal Application Third 10 CFR 54.21(b) Annual Amendment IR 05000338/20230112023-09-26026 September 2023 Quadrennial Focused Engineering Inspection Commercial Grade Dedication Report 05000338/2023011 and 05000339/2023011 ML23242A3482023-09-11011 September 2023 Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 - Cover ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23249A2592023-09-0606 September 2023 Core Operating Limits Report Cycle 30, Pattern Ukr, Revision 0 ML23214A2022023-09-0505 September 2023 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-02-01
[Table view] |
Text
10 CFR 50.55aVIRGINIA ELECTRIC AND POWER COMPANYRICHMOND, VIRGINIA 23261July 12, 2013United States Nuclear Regulatory Commission Serial No. 13-393Attention:
Document Control Desk NAPS/JHL ROWashington, D.C. 20555 Docket No. 50-338License No. NPF-4VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
NORTH ANNA POWER STATION UNIT 1RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION ASME SECTION Xl INSERVICE INSPECTION PROGRAMRELIEF REQUEST NI-14-LMT-001
-FOURTH INTERVALPERIOD 1 LIMITED EXAMINATIONS By letter dated November 1, 2012 (Serial No.12-660),
Virginia Electric and PowerCompany (Dominion) submitted a relief request for limited examination coverage (i.e.,less than 90% weld coverage
- achieved, due to physical interferences that prohibited attaining full weld coverage) obtained during the inservice inspection (ISI) examinations at North Anna Power Station Unit 1 during the fourth ten-year ISI interval.
Theseexaminations were performed to meet the requirements of the 2004 Edition of ASMESection Xl with No Addenda and the Risk-Informed/Safety-Based Inservice Inspection (RIS B) Program Plan based on Code Case N-716. In an E-mail from Dr. V. Sreenivas, dated March 4, 2013, the NRC requested additional information to complete the reviewof the limited examination relief request.
This information was provided in a letter datedApril 5, 2013 (Serial No.13-141).
In a subsequent E-mail from Dr. V. Sreenivas datedJuly 2, 2013, the NRC requested further clarification of the information provided in theoriginal relief. This information is provided in the attachment to this letter.If you have any questions or require additional information regarding the information provided in the attachment, please contact Mr. Thomas Shaub at (804) 273-2763.
Very truly yours,E. S. GrecheckVice President
-Nuclear Engineering and Development
Attachment:
Response to Request for Additional Information
-ASME Section Xl Inspection Program Relief Request Nl-14-LMT-001 Fourth Interval Period Limited Examinations Commitments made in this letter: None Serial No. 13-393Docket No. 50-338Response to Request for Additional Information Fourth Interval Period 1 ISI Limited Exam Relief RequestPage 2 of 2cc: U.S. Nuclear Regulatory Commission Region IISam Nunn Atlanta Federal Center61 Forsyth Street, SWSuite 23T85Atlanta, Georgia 30303Mr. J. E. Reasor, Jr.Old Dominion Electric Cooperative Innsbrook Corporate Center4201 Dominion Blvd.Suite 300Glen Allen, Virginia 23060NRC Senior Resident Inspector North Anna Power StationMs. K. R. Cotton GrossNRC Project ManagerU. S. Nuclear Regulatory Commission One White Flint NorthMail Stop 0-8 G9A11555 Rockville PikeRockville, Maryland 20852Dr. V. Sreenivas NRC Project ManagerU. S. Nuclear Regulatory Commission One White Flint NorthMail Stop 0-8 G9A11555 Rockville PikeRockville, Maryland 20852 Serial No. 13-393Docket No. 50-338Attachment Response to Request for Additional Information ASME Section XI Inservice Inspection ProgramRelief Request NI-14-LMT-001
-Fourth IntervalPeriod 1 Limited Examinations North Anna Power Station Unit IVirginia Electric and Power Company(Dominion)
Serial No. 13-393Docket No. 50-338Page 1 of 1REQUEST FOR ADDITIONAL INFORMATION (RAI)VIRGINIA ELECTRIC AND POWER COMPANYNORTH ANNA POWER STATION UNIT 1BACKGROUND By letter dated November 1, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12319A278),
Virginia Electric and Power Company(Dominion) submitted Relief Request (RR) Nl-14-LMT-001 for U.S. Nuclear Regulatory Commission (NRC) review and approval.
Dominion requested relief from certainrequirements of the American Society of Mechanical Engineers Boiler and PressureVessel Code (ASME Code), Section Xl, specifically related to examination coverage.
RR Nl-14-LMT-001 is applicable to the fourth 10-year inservice inspection (ISI) intervalfor the North Anna Power Station (NAPS) Unit 1, which commenced on May 1, 2009and will end on April 30, 2019. On March 4, 2013, the NRC sent Dominion a request foradditional information (RAI) concerning this relief request.
The response to the RAI wasprovided on April 5, 2013. In a subsequent e-mail dated July 2, 2013, the NRCrequested further clarification of the information provided in the original relief. The NRCRAI and the Dominion responses are provided below.NRC INFORMATION REQUESTNRC QuestionThe relief request stated that the volumetric examination identified indications in Welds8 (12"-SI-67) and SW-12 (32"-SHP-58) that were determined to be root geometry.
Please provide the detail:* How did the licensee determine that these indications were root geometry?
- Were these root geometries also detected by the previous examinations in thesewelds?Dominion ResponseBeam plots, profiles, along with UT signals were used to characterize the geometrical condition of Weld SW-12 on line 32"-SHP-58.
The indications were evaluated using theIndication Classification guidance of the Appendix VIII qualified procedure utilized forthe examination.
This weld had been examined three previous times with intermittent geometry noted in previous reports.Beam plots, profiles, along with UT signals were also used to characterize thegeometrical condition of Weld 8 on line 12"-SI-67.
The indications were evaluated usingthe Indication Classification guidance of the appendix VIII qualified procedure utilized forthe examination.
This location was not previously examined.