MONTHYEARIR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 ML24009A1022024-01-26026 January 2024 Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 LR-N23-0055, Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days2023-08-0303 August 2023 Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 LR-N23-0054, In-Service Inspection Activities2023-07-26026 July 2023 In-Service Inspection Activities LR-N23-0046, Emergency Plan Document Revisions Implemented June 28, 20232023-07-10010 July 2023 Emergency Plan Document Revisions Implemented June 28, 2023 LR-N23-0005, License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-06-23023 June 2023 License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML23139A1472023-06-0505 June 2023 Relief Request Associated with Fourth Interval In-service Inspection Limited Examinations of Weld Coverage ML23096A1842023-05-0909 May 2023 Issuance of Amendment No. 328 Revise and Relocate Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report IR 05000272/20230012023-05-0303 May 2023 Integrated Inspection Report 05000272/2023001 and 05000311/2023001 ML23081A4662023-05-0202 May 2023 Issuance of Amendment Nos. 346 and 327 Revise Technical Specifications to Extend Allowable Outage Time for Inoperable Emergency Diesel Generator IR 05000272/20233012023-05-0101 May 2023 Initial Operator Licensing Examination Report 05000272/2023301 and 05000311/2023301 LR-N23-0034, 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station2023-04-27027 April 2023 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station LR-N23-0035, 2022 Annual Radioactive Effluent Release Report (ARERR)2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report (ARERR) LR-N23-0033, Core Operating Limits Report Cycle 272023-04-26026 April 2023 Core Operating Limits Report Cycle 27 LR-N23-0010, License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location2023-04-21021 April 2023 License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location ML23089A0942023-04-17017 April 2023 NRC to PSEG Hope Creek, Transmittal of the National Marine Fisheries Service'S March 24, 2023, Biological Opinion GAR-2020-02842 Concerning Salem and Hope Creek ML23087A1492023-04-17017 April 2023 NRC to PSEG Salem, Transmittal of the National Marine Fisheries Service'S March 24, 2023, Biological Opinion GAR-2020-02842 Concerning Salem and Hope Creek ML23103A3232023-04-13013 April 2023 Submittal of Updated Final Safety Analysis Report, Rev. 26, Summary of Revised Regulatory Commitments for Hope Creek, Summary of Changes to PSEG Nuclear LLC, Quality Assurance Topical Report, NO-AA-10, Rev. 89 ML23095A3682023-04-12012 April 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Threshold Determination for Proposed Transfer of Land Ownership LR-N23-0006, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-24024 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23086A0912023-03-24024 March 2023 NMFS to NRC, Transmittal of Biological Opinion for Continued Operations of Salem and Hope Creek Nuclear Generating Stations RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations LR-N23-0019, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2023-03-21021 March 2023 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums ML23044A1052023-03-13013 March 2023 Issuance of Amendment Nos. 345 and 326 Relocate Technical Specifications Requirements for Reactor Head Vents to Technical Requirements Manual ML23037A9712023-03-0909 March 2023 and Salem Nuclear, Unit Nos. 1 and 2 Issuance of Amendment Nos. 233, 344, and 325 Relocate Technical Specification Staff Qualification Requirements to the PSEG Quality Assurance Topical Report IR 05000272/20230112023-03-0707 March 2023 Comprehensive Engineering Team Inspection Report 05000272/2023011 and 05000311/2023011 IR 05000272/20220062023-03-0101 March 2023 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022006 and 05000311/2022006) LR-N23-0016, and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments2023-02-28028 February 2023 and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments LR-N23-0012, Annual Property Insurance Status Report2023-02-24024 February 2023 Annual Property Insurance Status Report LR-N23-0014, Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.7172023-02-23023 February 2023 Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.717 ML23034A1532023-02-0909 February 2023 Operator Licensing Examination Approval ML23019A3482023-02-0202 February 2023 Issuance of Relief Request No. SC-I5R-221 for the Alternative Repair for Service Water System Piping LR-N23-0003, Response to Requests for Additional Information Salem Unit 2 Relief Request S2-I4R-2112023-02-0101 February 2023 Response to Requests for Additional Information Salem Unit 2 Relief Request S2-I4R-211 2024-02-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC P.O. Box 236, N09 Hancocks Bridge, NJ 08038 September 15, 2014
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNIT NO. 1 -RELAXATION OF THE SCHEDULE REQUIREMENTS FOR ORDER EA-12-049 "ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS"
Dear Mr. Joyce:
By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 12054A735), the U.S. Nuclear Regulatory Commission (NRC) ordered PSEG Nuclear LLC (PSEG, the licensee) to take certain actions at Salem Nuclear Generating Station, Unit No. 1 (Salem), associated with the Fukushima Near-Term Task Force Recommendations. Order EA-12-049 directed that actions be taken by licensees to develop and implement strategies to maintain or restore core cooling, reactor coolant system inventory, containment cooling, and spent fuel pool (SFP) cooling capabilities during beyond design basis external events.Section IV of the order states that licensees proposing to deviate from requirements contained in NRC Order EA-12-049 may request that the Director, Office of Nuclear Reactor Regulation, relax or rescind certain requirements. By letter dated July 31, 2014 (ADAMS Accession No. ML 14212A355), the licensee informed the NRC of its request for an extension of one additional refueling cycle to carry out the order requirement of Condition IV.A.2, which requires full implementation of the order requirements no later than two refueling cycles after submittal of the overall integrated plan, or December 31, 2016, whichever comes first. The licensee stated that its strategy is dependent on having a maximum reactor coolant pump (RCP) seal leakage rate of 21 gallons per minute (gpm) per RCP. Recent Westinghouse evaluations of RCP seal leakage in response to Westinghouse Nuclear Safety Advisory Letter (NSAL) 14-1 indicate that the generic leak rates previously used by the licensee for its mitigation strategy do not envelope calculated leakage rates applicable to the Salem design. PSEG is in the process of evaluating options to reduce RCP seal leakage rates, which are part of the technical bases for demonstrating Salem compliance with the requirements of NRC Order EA-12-049. To allow the time to determine the best option and to complete any necessary plant modifications, the licensee requests to move the order implementation date from the completion of the fall 2014 refueling outage to the completion of the spring 2016 refueling outage. In light of the facts presented in the licensee's July 31, 2014 letter, the NRC staff has determined that the licensee has presented good cause for a relaxation of the order implementation date. Any plant modifications needed to increase the resistance of the seal T. Joyce leakoff line and thereby reduce the calculated seal leakoff rate is a significant endeavor and will improve the safety of the plant. Such a project requires detailed design work, an allowance for the time needed to specify and procure materials, and an appropriate plant outage which would permit the installation of the plant modification. The NRC staff also considered that, following the accident at Fukushima Dai-ichi, the NRC concluded that a sequence of events such as the Fukushima Dai-ichi accident is unlikely to occur in the United States based on the current regulatory requirements and existing plant capabilities. Given the plant-specific circumstances at Salem, completion before December 2016 is consistent with the intent of the order. The NRC staff approves the relaxation of the order implementation date. Accordingly, based upon the authority granted to the Director, Office of Nuclear Reactor Regulation, the requirement of the order for full order implementation is relaxed until the completion of the spring 2016 refueling outage to allow the licensee sufficient time to select and implement a method to reduce the RCP seal leakage rate to within the limits determined by the licensee to be necessary. If you have any questions, please contact John Boska at 301-415-2901. Docket No. 50-272 cc: Listserv Sincerely, aniel H. Dorman, Acting Director Office of Nuclear Reactor Regulation
- ML 14232A030 .. !OFFICE NRR/JLD/JOMB/PM NRR/JLD/LA NRR/JLD/JOMB/BC(A) OE NAME JBoska Slent MHalter RFretz DATE 08/19/14 08/20/14 08/22/14 08/25/14 OFFICE OGC NRR/JLD/D NRR/D NAME CHair JDavis (JMcHale for) DOorman (JUhle for) DATE 09/04/14 09/15/14 09/15/14