MONTHYEARRS-23-120, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information RS-23-103, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor RS-23-084, Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis2023-07-24024 July 2023 Response to Request for Additional Information Regarding the Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-048, Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements2023-03-0707 March 2023 Exigent Amendment Request to Revise Design Basis Related to Seismic Requirements RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-037, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station2023-02-22022 February 2023 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-22-085, Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis2023-01-12012 January 2023 Application to Revise Design Basis to Allow Use of Plastic Section Properties in Lower Downcomer Braces Analysis RS-23-006, Supplemental Information Regarding License Amendment Request Relocation of Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report2023-01-10010 January 2023 Supplemental Information Regarding License Amendment Request Relocation of Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-109, Response to Request for Additional Information License Amendments Related to Fuel Storage2022-10-12012 October 2022 Response to Request for Additional Information License Amendments Related to Fuel Storage RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-083, Response to Request for Additional Information Related to the License Amendment Request to Change New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies, with Proposed Changes to Technical2022-06-17017 June 2022 Response to Request for Additional Information Related to the License Amendment Request to Change New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies, with Proposed Changes to Technical RS-22-051, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-04-12012 April 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-049, Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for2022-04-0404 April 2022 Constellation Energy Generation, LLC, Supplemental Information to Correct Typographical Errors in Constellation'S Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for V RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations RS-22-035, Supplemental Information Regarding Relief Request I4R-13 Relief from Code Examinations for 1B33-F060A and 1B33-F060B Repairs2022-03-0404 March 2022 Supplemental Information Regarding Relief Request I4R-13 Relief from Code Examinations for 1B33-F060A and 1B33-F060B Repairs RS-22-033, Response to Request for Additional Information Regarding Relief Request I4R-13 Relief from Code Examinations for 1B33-F060A and 1B33-F060B Repairs2022-03-0303 March 2022 Response to Request for Additional Information Regarding Relief Request I4R-13 Relief from Code Examinations for 1B33-F060A and 1B33-F060B Repairs RS-22-032, Relief Request I4R-13 Relief from Code Examinations for 1B33-F060A and 1B33-F060B Repairs2022-03-0202 March 2022 Relief Request I4R-13 Relief from Code Examinations for 1B33-F060A and 1B33-F060B Repairs RS-22-023, Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement2022-02-23023 February 2022 Constellation Energy Generation, LLC, Executed Trust Fund Agreement Amendment and Subordinate Trust Agreement RS-22-027, Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated2022-02-23023 February 2022 Constellation, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated P RS-22-018, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station2022-02-22022 February 2022 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for LaSalle County Station RS-22-019, Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists2022-02-16016 February 2022 Constellation Energy Generation, LLC - Update to Correspondence Addressees and Service Lists RS-22-015, Notification of Completion of License Transfer and Request to Continue Processing Pending NRC Actions Previously Requested by Exelon Generation Company, LLC2022-02-0101 February 2022 Notification of Completion of License Transfer and Request to Continue Processing Pending NRC Actions Previously Requested by Exelon Generation Company, LLC RS-22-004, Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2022-01-0404 January 2022 Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RS-21-121, Proposed Changes to Decommissioning Trust Agreements and Master Terms2021-12-15015 December 2021 Proposed Changes to Decommissioning Trust Agreements and Master Terms RS-21-115, Supplemental Information for License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies, with Proposed Changes to Technical Specifications 4.3.1 and 5.6.52021-11-0404 November 2021 Supplemental Information for License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies, with Proposed Changes to Technical Specifications 4.3.1 and 5.6.5 RS-21-109, Request to Withhold Meeting Materials for the Non-Public Meeting Held on September 2, 20212021-10-14014 October 2021 Request to Withhold Meeting Materials for the Non-Public Meeting Held on September 2, 2021 RS-21-091, Implementation of Insider Threat Program Requirements Associated with the Voluntary Security Clearance Program and Advisement of Leadership Changes2021-09-13013 September 2021 Implementation of Insider Threat Program Requirements Associated with the Voluntary Security Clearance Program and Advisement of Leadership Changes RS-21-078, Response to Request for Additional Information for Application to Revise Technical Specification to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements, and TSTF-583-T, TSTF-582 Diesel2021-08-19019 August 2021 Response to Request for Additional Information for Application to Revise Technical Specification to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements, and TSTF-583-T, TSTF-582 Diesel RS-21-085, Response to Request for Additional Information Regarding License Amendment Request to Incorporate Licensing Topical Report NEDE-33885PA, Revision 1, GNF CRDA Application Methodology (EPID-L-2021-LLA-0016)2021-08-17017 August 2021 Response to Request for Additional Information Regarding License Amendment Request to Incorporate Licensing Topical Report NEDE-33885PA, Revision 1, GNF CRDA Application Methodology (EPID-L-2021-LLA-0016) RS-21-063, Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2021-06-30030 June 2021 Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RS-21-064, License Amendment Request Re New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies - Cover Letter2021-06-30030 June 2021 License Amendment Request Re New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies - Cover Letter RS-21-070, Proposed Alternative to Utilize Code Case N-8932021-06-30030 June 2021 Proposed Alternative to Utilize Code Case N-893 RS-21-055, Response to Third Round Request for Additional Information (Rals) for LaSalle License Amendment Request to Adopt Risk Informed Completion Times TSTF- 505, Revision 2, Provide Risk-Informed Extended.2021-05-10010 May 2021 Response to Third Round Request for Additional Information (Rals) for LaSalle License Amendment Request to Adopt Risk Informed Completion Times TSTF- 505, Revision 2, Provide Risk-Informed Extended. RS-21-054, Response to NRC Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations2021-04-29029 April 2021 Response to NRC Regulatory Issue Summary 2021-01, Preparation and Scheduling of Operator Licensing Examinations RS-21-050, Response to Request for Additional Information (RAI) Regarding Request for License Amendment Regarding Ultimate Heat Sink (EPID-L-2020-LLA-0165)2021-04-16016 April 2021 Response to Request for Additional Information (RAI) Regarding Request for License Amendment Regarding Ultimate Heat Sink (EPID-L-2020-LLA-0165) RS-21-045, Response to Request for Additional Information (RAI) Regarding Request for License Amendment Regarding Ultimate Heat Sink (EPID-L-2020-LLA-0165)2021-04-0707 April 2021 Response to Request for Additional Information (RAI) Regarding Request for License Amendment Regarding Ultimate Heat Sink (EPID-L-2020-LLA-0165) RS-21-040, Response to Second Round Request for Additional Information (Rais) for License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2021-03-31031 March 2021 Response to Second Round Request for Additional Information (Rais) for License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b RS-21-043, Supplemental Information Regarding Relief Request I4R-12 Relief from Code Examinations for 2B33-F060A and 2B33-F060B Repairs, Revision 22021-03-26026 March 2021 Supplemental Information Regarding Relief Request I4R-12 Relief from Code Examinations for 2B33-F060A and 2B33-F060B Repairs, Revision 2 RS-21-042, Relief Request I4R-12 Relief from Code Examinations for 2B33-F060A and 2B33-F060B Repairs, Revision 22021-03-26026 March 2021 Relief Request I4R-12 Relief from Code Examinations for 2B33-F060A and 2B33-F060B Repairs, Revision 2 RS-21-039, Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments2021-03-25025 March 2021 Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments RS-21-035, Relief Request I4R-12 Relief from Code Examinations for 2B33-F060A and 2B33-F060B Repairs2021-03-0909 March 2021 Relief Request I4R-12 Relief from Code Examinations for 2B33-F060A and 2B33-F060B Repairs 2023-08-04
[Table view] |
Text
RS-05-172 10 CFR 50.90 December 22, 2005 U. S . Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C . 20555 LaSalle County Station, Units 1 and 2 Facility Operating License Nos . NPF-1 1 and NPF-1 8 NRC Docket Nos . 50-373 and 50-374 Subject : Additional Information Supporting the License Amendment Request to Extend the Completion Times Related to Technical Specifications associated with Residual Heat Removal Service Water, Diesel Generator Cooling Water and the Opposite Unit Division 2 Diesel Generator References : 1. Letter from J . A. Bauer (Exelon Generation Corporation, LLC) to U.S. NRC, "Request for a License Amendment to Extend the Completion Times Related to Technical Specifications associated with Residual Heat Removal Service Water, Diesel Generator Cooling Water and the Opposite Unit Division 2 Diesel Generator,"' dated April 13, 2005
- 2. Letter from U .S . NRC to C. M . Crane (Exelon Generation Corporation, LLC), "LaSalle County Power Station, Units 1 and 2 - Request for Additional Information Related to Amendment Request," dated December 7, 2005 In Reference 1, Exelon Generation Company, LLC, (EGC), requested an amendment to Appendix A, Technical Specifications {TS), of Facility Operating License Nos . NPF-1 1 and NPF-18 for LaSalle County Station Units 1 and 2 respectively . Specifically, the proposed changes modify the Completion Time for TS Sections 3.7.1, "Residual Heat Removal Service Water (RHRSW) System," 3 .7.2, "Diesel Generator Cooling Water (DGCW) System," and 3.8.1, "AC Sources - Operating ." The proposed extensions of the Completion Times will only be used during the specified unit refueling outages .
In Reference 2, the NRC requested additional information to complete the review of the license amendment the . This request pertained to what functions would be affected during each phase of repairs, what compensatory measures would be in place during each phase of the repairs including any regulatory commitments established to implement the compensatory actions, and why the proposed change was not requested on a permanent basis .
December 22, 2005 U. S . Nuclear Regulatory Commission Page 2 Attachment 1 of this letter provides the requested information.
EGC has reviewed the information supporting a finding of no significant hazards consideration that was previously provided to the NRC in Attachment 1 of Reference 1 . The supplemental information provided in this submittal does not affect the bases for concluding that the proposed license amendment does not involve a significant hazards consideration .
Regulatory commitments are documented in Attachment 2 of this letter. Should you have any questions concerning this letter, please contact Ms. Alison Mackellar at (630) 657-2817 .
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 22nd day of December 2005.
Respectfully, Joseph A. Bauer Manager, Licensing and Regulatory Affairs : Response to Request for Additional Information : Regulatory Commitments for LaSalle County Station
ATTACHMENT I Response to Request for Additional Information Question No. 1 Provide a complete description of what functions will be affected during each phase of repair .
(a) What compensatory measures will be taken during each phase of the repair in order to maintain the capability to perform the function that is affected, and (b) what regulatory commitments will be established to implement the compensatory actions that are being credited?
Response
- 1. Provide a complete description of what functions will be affected during each phase of repair.
When Division 1 valves are replaced during Unit 1 Refueling Outage 11 (1-1 R11), the following systems will be inoperable ; (note that the current affected Technical Specification (TS) are also identified):
0 U-2 Division 1 Residual Heat Removal Service Water (RHRSW), TS 3.7.1
U-2 Division 1 Emergency Fuel Pool Makeup Pump, (no TS associated with this component) 1 of 5
ATTACHMENT I Response to Request for Additional Information
- U-1 Division 1 RHR Shutdown Cooling System, TS 3.4.10, 3.9.8, 3.9.9 When Division 2 valves are replaced during the Unit 2 Refueling Outage 11 (L2R1 1),
the following systems will be inoperable; (note that the current affected TS are also identified) :
0 U-1 Division 2 RHRSW, TS 3.7 .1 U-1 Division 2 DGCW, TS 3 .7.2 U-1 Division 2 Diesel Generator, TS 3.8.1 U-2 Division 2 Diesel Generator, TS 3 .8 .2 0 U-1 Division 2 RHR Suppression Pool Cooling Subsystem, TS 3.6.2.3 a U-1 Division 2 RHR Suppression Pool Spray Subsystem, TS 3.6.2.4 U-1 Division 2 ECCS, TS 3.5.1
- U-2 Division 2 ECCS, TS 3 .5.2 9 U-1 Hydrogen Recombiner for U-1, (no TS associated with this component)
U-1 Division 2 Emergency Fuel Pool Makeup Pump, (no TS associated with this component)
U-2 Division 2 Emergency Fuel Pool Makeup Pump, (no TS associated with this component) 0 U-2 Division 2 RHR Shutdown Cooling System, TS 3 .4.10, 3 .9 .8, 3.9.9 When Division 2 valves are replaced during the Unit 1 Refueling Outage 12 (L1 R12},
the following systems will be inoperable ; (note that the current affected TS are also identified) :
U-2 Division 2 RHRSW, TS 3.7.1 U-2 Division 2 DGCW, TS 3.7 .2 U-1 Division 2 Diesel Generator, TS 3.8 .2 U-2 Division 2 Diesel Generator, TS 3.8.1 U-2 Division 2 RHR Suppression Pool Cooling Subsystem, TS 3.6.2.3 2 of 5
ATTACHMENT I Response to Request for Additional Information 0 U-2 Division 2 RHR Suppression Pool Spray Subsystem, TS 3.6 .2 .4
" U-1 Division 2 ECCS, TS 3 .5.2
" U-2 Division 2 ECCS, TS 3.5 .1 0 U-2 Hydrogen Recombiner for U-2, (no TS associated with this component)
U-1 Division 2 Emergency Fuel Pool Makeup Pump, (no TS associated with this component)
U-2 Division 2 Emergency Fuel Pool Makeup Pump, (no TS associated with this component) 0 U-1 Division 2 RHR Shutdown Cooling System, TS 3 .4.10, 3 .9 .8, 3.9.9 (a) What compensatory measures will be taken during each phase of the repair in order to maintain the capability to perform the function that is affected?
When Division 1 valves are replaced during Ll R1 1, the following list of protected equipment will not be scheduled for maintenance, (i.e ., will remain available), during the extended completion times:
Unit 2 Division 2 4kv Bus 242Y Unit 2 Division 2 Emergency Diesel Generator Unit 2 Division 2 Main Battery Charger Unit 2 Division 2 Core Standby Cooling System (CSCS)
Unit 2 Division 2 RHR Unit 2 Division 3 HPCS Unit 2 Motor Driven Reactor Feedwater Pump To minimize the impact on fire risk, a fire watch will be posted at the Unit 2 Division 2 Essential Switchgear Room during L 1 R11 .
When Division 2 valves are replaced during L2R1 1 and Ll R12, no compensatory measures are needed during the proposed work . The use of the non-code line stops will maintain the availability of the online unit's Division 2 systems.
In addition, the Division 1 and 2 maintenance will be performed with a number of controls in place (i.e., consistent with LaSalle County Station (LSCS) procedures and practices) to reduce errors and minimize risk . These controls are summarized in Section 4.3.2 of Reference 1 .
LSCS Special Procedure (LLP 2005-005), "Unit One - Division One CSCS Draining,"
has been developed for Ll R11 and specifically documents the required 3 of 5
ATTACHMENT I Response to Request for Additional Information compensatory measures listed above . Attachment D of this procedure, (also given in Table 4 of Reference 1), specifies the protected equipment during the Division 1 CSCS work .
(b) What regulatory commitments will be established to implement the compensatory actions that are being credited?
Exelon Generation Corporation, LLC, (EGC) is making a regulatory commitment to implement the below administrative controls and actions and will annotate these specific procedure steps as regulatory commitments. The regulatory commitments are described below and summarized in Attachment 2.
The administrative controls/actions that are to be in place in accordance with Reference 1 are documented in the steps below from LLP 2005-005 for Division 1 during Ll R11 .
Additional administrative controls/actions to protect equipment listed on Attachment D of LLP 2005-005, (also given in Table 4 of Reference 1), will be taken in accordance with station risk management procedures while Division 1 CSCS remains inoperable . The administrative actions include physical barricades to segregate protected equipment, posted signs and enhanced plant personnel awareness through pre-job briefings and outage communication bulletins.
A qualified fire watch will be posted in the Unit 2 Division 2 Essential Switchgear Room while Division 1 CSCS remains inoperable .
ECG is also making a regulatory commitment to install the non-code line stops required to isolate the Unit 1 portion of the common discharge header from the Unit 2 portion of the header. The non-code line stops are designed to the same pressure rating and seismic requirements as the CSCS piping and will maintain the availability of the online unit's Division 2 CSCS system. The regulatory commitment for installation of the non-code line stops for Ll R12 and L2R1 1 will be documented in LLP 2006-001, "Unit One - Division Two CSCS Draining," for Unit 1 Division 2 and LLP 2006-002, "Unit Two - Division Two CSCS Draining,"
for Unit 2 Division 2 .
Question No. 2 Provide an explanation, on the docket, why the proposed changes cannot be proposed as permanent changes to the Technical Specification requirements, or (a) why such permanent changes would otherwise be inappropriate; and (b) why continuing "one-time" changes of this nature will not be required in the future .
4 of 5
ATTACHMENT I Response to Request for Additional Information
Response
The proposed change was not requested on a permanent basis because it was determined that the current situation has a low probability of recurrence and a permanent change is considered unnecessary. The failure mode is well understood and is being mitigated by the replacement valves that are constructed of material that is less susceptible to the extensive corrosion currently experienced. The existing Completion Times have proven to be adequate for other necessary maintenance, and it is only due to our desire to correct the degraded condition as expeditiously as possible that this request is being made . The current preventive maintenance practices, coupled with the more resilient material of the replacement valves, are expected to preclude future degradation that is currently being experienced . Additionally, the risk assessment performed to support this request assumed a one-time evolution, and did not consider a permanent extension of the Completion Time for each of the three refueling outages as documented in Reference 1 .
ATTACHMENT 2 Response to Request for Additional Information REGULATORY COMMITMENTS FOR LASALLE COUNTY STATION The following table identifies those actions committed to by Exelon Generation Company, LLC (EGC) in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.
Please direct questions regarding these commitments to Alison Mackellar at (630) 657-2817 .
Regulatory Commitments Due Date / Event Additional administrative controls/actions to protect Implemented by procedure equipment listed on Attachment D of LLP 2005-005, while Division 1 CSCS (also given in Table 4 of Reference 1), will be taken in remains inoperable during accordance with station risk management procedures L1 R11 while Division 1 CSCS remains inoperable . The administrative actions include physical barricades to segregate protected equipment, poked signs and enhanced plant personnel awareness through pre-job briefings and outage communication bulletins A qualified fire watch will be posted in the Unit 2 Implemented by procedure Division 2 Essential Switchgear Room while Division 1 CSCS remains inoperable during L1R11 Installation of non-code line stops to isolate the Unit 1 The regulatory commitments portion of the common discharge header from the Unit for installation of the non-code 2 portion of the header. The non-code line stops are line stops for Ll R12 and designed to the same pressure rating and seismic L2R1 1 will be documented by requirements as the CSCS piping and will maintain the specific procedures for Unit 1 availability of the online unit's Division 2 CSCS system . Division 2 and Unit 2 Division 2 CSCS maintenance