MONTHYEARNRC-24-0007, Report of Changes to Quality Assurance Program for Radioactive Material Packages2024-01-12012 January 2024 Report of Changes to Quality Assurance Program for Radioactive Material Packages NRC-24-0002, Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122024-01-12012 January 2024 Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0079, Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 222023-12-14014 December 2023 Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 22 NRC-23-0077, Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan2023-12-0404 December 2023 Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-23-0073, Guarantee of Payment of Deferred Premiums2023-11-29029 November 2023 Guarantee of Payment of Deferred Premiums NRC-23-0071, Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-10-13013 October 2023 Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0062, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-10-12012 October 2023 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0068, Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-09-28028 September 2023 Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0064, Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-09-11011 September 2023 Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0057, Independent Spent Fuel Storage Installation Cask Registration2023-08-31031 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0054, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 20232023-08-31031 August 2023 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 2023 NRC-23-0056, Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval2023-08-31031 August 2023 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval NRC-23-0061, Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water..2023-08-30030 August 2023 Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water.. NRC-23-0059, Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0060, Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0053, Independent Spent Fuel Storage Installation Cask Registration2023-08-23023 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0050, Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-10010 August 2023 Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0048, Independent Spent Fuel Storage Installation Cask Registration2023-08-0101 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0049, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-07-24024 July 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0043, Independent Spent Fuel Storage Installation, Cask Registration2023-06-27027 June 2023 Independent Spent Fuel Storage Installation, Cask Registration NRC-23-0020, License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance2023-06-13013 June 2023 License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance NRC-23-0039, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-06-0606 June 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0030, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2023-06-0505 June 2023 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-23-0029, Snubber Program for the Fourth 10-Year Testing Interval2023-06-0505 June 2023 Snubber Program for the Fourth 10-Year Testing Interval NRC-23-0037, 56542-EN 56542 - Fermi2023-05-26026 May 2023 56542-EN 56542 - Fermi NRC-23-0031, Response to NRC Request from Audit of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources -Operating,' Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2023-05-16016 May 2023 Response to NRC Request from Audit of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources -Operating,' Emergency Diesel Generator Voltage and Frequency Surveillance Requirements NRC-23-0002, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-05-0505 May 2023 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0010, License Amendment Request to Correct Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage2023-05-0505 May 2023 License Amendment Request to Correct Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage NRC-23-0017, Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report2023-04-28028 April 2023 Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report NRC-23-0025, Submittal of 2022 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2023-04-28028 April 2023 Submittal of 2022 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-23-0018, Annual Non-Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Non-Radiological Environmental Operating Report NRC-23-0024, Levels and Sources of Property Insurance Coverage2023-04-0303 April 2023 Levels and Sources of Property Insurance Coverage NRC-23-0021, ISFSI, Decommissioning Funding Plan Update2023-03-30030 March 2023 ISFSI, Decommissioning Funding Plan Update NRC-23-0016, Decommissioning Funding Status Report2023-03-30030 March 2023 Decommissioning Funding Status Report NRC-23-0015, Decommissioning Funding Status Report for Fermi 12023-03-30030 March 2023 Decommissioning Funding Status Report for Fermi 1 NRC-23-0011, License Renewal Commitment 7c: Transmittal of Core Plate Hold-Down Bolt Analysis2023-03-0707 March 2023 License Renewal Commitment 7c: Transmittal of Core Plate Hold-Down Bolt Analysis NRC-22-0026, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2022-12-16016 December 2022 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements NRC-22-0051, DTE Electric Company - Guarantee of Payment of Deferred Premiums2022-11-29029 November 2022 DTE Electric Company - Guarantee of Payment of Deferred Premiums NRC-22-0052, Replacement Files for Submittal of Revision 24 to the Fermi 2 Updated Final Safety Analysis Report (UFSAR) Through EIE on November 9, 20222022-11-17017 November 2022 Replacement Files for Submittal of Revision 24 to the Fermi 2 Updated Final Safety Analysis Report (UFSAR) Through EIE on November 9, 2022 NRC-22-0046, Submittal of Biennial Review of the Fermi 1 Safety Analysis Report2022-11-14014 November 2022 Submittal of Biennial Review of the Fermi 1 Safety Analysis Report NRC-22-0041, Evacuation Time Estimate Report2022-10-0505 October 2022 Evacuation Time Estimate Report NRC-22-0033, Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 20222022-08-29029 August 2022 Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 2022 NRC-22-0030, Inservice Inspection Summary Report2022-08-10010 August 2022 Inservice Inspection Summary Report NRC-22-0023, Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2022-08-0404 August 2022 Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements NRC-22-0022, Annual Non-Radiological Environmental Operating Report2022-04-29029 April 2022 Annual Non-Radiological Environmental Operating Report NRC-22-0021, Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report2022-04-29029 April 2022 Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report NRC-22-0020, Enrico Fermi Atomic Power Plant, Unit No. 1 & Fermi 2 Power Plant - 10 CFR 20.2206 Report of Individual Monitoring2022-04-28028 April 2022 Enrico Fermi Atomic Power Plant, Unit No. 1 & Fermi 2 Power Plant - 10 CFR 20.2206 Report of Individual Monitoring NRC-22-0003, Submittal of 2021 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2022-04-26026 April 2022 Submittal of 2021 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-22-0019, Submittal of the National Pollutant Discharge Elimination System Permit Application for Reissuance2022-04-0404 April 2022 Submittal of the National Pollutant Discharge Elimination System Permit Application for Reissuance NRC-22-0011, Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report2022-03-31031 March 2022 Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report 2024-01-12
[Table view] |
Text
Donald K. Cobb Assistant Vice President, Nuclear Generation Fermi 2 6400 North Dixie Hwy., Newport, MI 48166 Tel: 734.586.5201 Fax: 734.586.4172 DTE Energy-7 February 5, 2006 10 CFR 50.90 NRC-06-0011 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington D C 20555-0001
References:
- 1) Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
- 2) Detroit Edison Letter to NRC, "Emergency License Amendment Request for One-Time Extension of Allowed Outage Time for the Fermi 2 Emergency Diesel Generator 12"
Subject:
Response to Request for Additional Information Regarding Emergency License Amendment Request for One-Time Extension of Allowed Outage Time for the Fermi 2 Emergency Diesel Generator 12 In Reference 2, Detroit Edison requested NRC approval of a proposed license amendment that requests a one-time extension of allowed outage time for the Fermi 2 Emergency Diesel Generator 12 from 7 to 14 days. The NRC asked that the Operation and Maintenance Restrictions discussed in Reference 2 be explicitly described as regulatory commitments. Enclosure 1 provides a detailed description of the commitments contained in Reference 2 and additional information requested during a conference call on February 5, 2006.
If you have any questions regarding this submittal, please contact Ronald W. Gaston at (734) 586-5197.
Sincerely,
USNRC NRC-06-001 1 Page 2
Enclosures:
- 1. Response to Request for Additional Information cc: D. H. Jaffe T. J. Kozak NRC Resident Office Regional Administrator, Region I[I Supervisor, Electric Operators, Michigan Public Service Commission 2
USNRC NRC-06-001 1 Page 3 I, Donald K. Cobb, do hereby affirm that the foregoing statements are based on facts and circumstances which are true and accurate to the best of my knowledge and belief.
D. K. Cobb Assistant Vice President Nuclear Generation On this By day of .J;6^tj , 2006 before me personally appeared Donald K. Cobb, being first duly sworn and says that he executed the foregoing as his free act and deed.
Notar Public NORMAN K. PETERSON actARY PUBUC MONROE CO., Ml S ClOWMON EXPIRES Jul 24, 2Ox 3
USNRC NRC-06-001 1 Page 4 bcc: G. D. Cerullo D. K. Cobb W. A. Colonnello R. W. Gaston R. W. Libra M. A. Philippon P. W. Smith S. Stasek Electronic Licensing Library (ELL) (200 TAC)
Information Management (140 NOC)
Michigan Department of Environmental Quality Radiological Protection and Medical Waste Section NSRG Administrator (200 TAC)
NRR Chron File 4
ENCLOSURE 1 to NRC-06-0011 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATON to NRC-06-001 1 Page 2
- 1. Commitments The following identifies those actions committed to by Detroit Edison in Reference 2.
Any other actions discussed in Reference 2 represent intended or planned actions by Detroit Edison, and are not regulatory commitments. The compensatory measures have been entered as regulatory commitments in the Fermi 2 Commitment Management System which complies with Nuclear Energy Institute 99-04, Revision 0, "guidelines for Managing NRC Commitment Changes."
A. If any future submittals affect these license pages, Detroit Edison will coordinate the changes to the pages with the Nuclear Regulatory Commission (NRC) Project Manager to ensure proper page control when the associated license amendment requests are approved.
B. The following equipment protections will be in effect until EDG 12 is restored to an Operable status:
- 1. Elective maintenance will not be performed on EDGs 11, 13, and 14 or CTG 11-1.
- 2. Elective maintenance will not be scheduled within the 120 kV and 345 kV switchyards that would challenge the offsite power connections or offsite power unavailability.
- 3. Elective maintenance will not be performed on the opposite train Emergency Core Cooling System (ECCS) equipment.
- 4. Elective maintenance will not be performed on equipment in the Standby Feedwater (SBFW) System.
C. While in the extended EDG 12 completion time period, overall plant risk will be managed by the existing Maintenance Rule (a)(4) program. This program evaluates increases in risk posed by potential combinations of equipment out-of-service and potential increases in initiating event frequency and requires that risk recommendations be implemented as appropriate for a given plant configuration.
2 to NRC-06-001 1 Page 3 D. Maintenance and testing during the allowed outage time extension will be rescheduled for Fermi 2 as warranted to minimize aggregate risk. This will specifically include:
- 1. Work performed on safety significant systems and their applicable support systems will be reviewed and rescheduled as necessary based upon routine and emergent Maintenance Rule 10 CFR 50.65 (a)(4) evaluations.
- 2. No work will be performed that could potentially jeopardize the availability of the remaining on site emergency power sources. This will be ensured by restricting and/or controlling access to this equipment via guidance provided in MOP05 (the site procedure for control of equipment).
E. The following actions will be taken to provide an increased assurance of grid stability:
- 1. No test or maintenance activities that could reduce switchyard reliability will be performed.
- 2. At four hour intervals, the projected grid voltage following postulated unit trip will be verified to indicate a stable grid. Assuring the grid conditions are expected to remain stable ser es to reduce the grid as an initiator for loss of offsite power to the units.
- 3. Fermi 2 will contact the system dispatcher to ensure that no short-term activities adversely affecting grid stability are planned or have transpired.
- 4. Fermi 2 will confirm that the system dispatcher will notify the control room or Shift Manager in the event of severe weather, system degradation, or perturbations do occur so that an appropriate plant response can be determined.
F. Operations Briefings will be conducted on the use of CTG 11-1 and the utilization of CTG 11-2, CTG 11-3, or CTG 11-4 in conjunction with the auxiliary blackstart diesel to mitigate the consequences of a station blackout or loss of off-site power.
These briefings will include review of the associated procedures.
to NRC-06-001 1 Page 4
- 2. License Condition The License Condition discussed on page 4 of Reference 2 will be added as a footnote to Condition A.6 of Technical Specification 3.8.1.
- 3. Risk Information The following additional risk anallysis information was discussed:
- 1. A comparison of the NRC SPAR model assessment results of the August 2003 regional loss of power event (grid collapse) with the Fermi PRA model results was performed. The result of this comparison showed generally good agreement between the two analyses.
- 2. EOOS is the computer analysis tool used at Fermi for configuration risk management under 10 CFR 50.65 (a)(4).
- 3. An uncertainty analysis performed by a PRA consultant on the draft FermiV7 PRA model shows an Error Factor (EF) of approximately 3.
- 4. CTG 11-1 is the credited source of AC power at Fermi for the mitigation of Appendix R,Section III.G.3 fire scenarios.
4