==Dear Ms. Pederson,== | ==Dear Ms. Pederson,== | ||
ZS-2013-0005 In our first meeting in November you made a number of commitments regarding the Independent Spent Fuel Storage Installation (ISFSI) at Zion with respect to review and turnaround times for completing the final licensing requirements. | ZS-2013-0005 In our first meeting in November you made a number of commitments regarding the Independent Spent Fuel Storage Installation (ISFSI) at Zion with respect to review and turnaround times for completing the final licensing requirements. | ||
On December 31st, we received word from headquarters that the Zion ISFSI was licensed for use and we could proceed with moving fuel from our pool to the pad. You were able to coordinate Region III resources as well as the program office at headquarters and NSER personnel such that many players from different departments focused on delivering a fully inspected and licensed facility on a timeline you established. | On December 31st, we received word from headquarters that the Zion ISFSI was licensed for use and we could proceed with moving fuel from our pool to the pad. You were able to coordinate Region III resources as well as the program office at headquarters and NSER personnel such that many players from different departments focused on delivering a fully inspected and licensed facility on a timeline you established. | ||
What stands out the most was your willingness to be accountable for delivering a regulatory solution that was timely and fully in compliance with regulations. | What stands out the most was your willingness to be accountable for delivering a regulatory solution that was timely and fully in compliance with regulations. | ||
Thank-you. | Thank-you. | ||
Please pass along my thanks and acknowledgement to yours and the headquarters staff that worked through a busy holiday period to support the Zion Project. | Please pass along my thanks and acknowledgement to yours and the headquarters staff that worked through a busy holiday period to support the Zion Project. Sauger ral Manager ZionSolutions, LLC 101 Shiloh Boulevard, Zion | ||
Sauger ral Manager ZionSolutions, LLC 101 Shiloh Boulevard, Zion | |||
* IL 60099 \.Z C C [ \ '-/ \J (224) 789-4016 | * IL 60099 \.Z C C [ \ '-/ \J (224) 789-4016 | ||
* Fax: (224) 789-4008 | * Fax: (224) 789-4008 | ||
* www.zionsolutionscompany.com}} | * www.zionsolutionscompany.com}} |
Revision as of 17:34, 13 July 2018
ML14009A279 | |
Person / Time | |
---|---|
Site: | Zion File:ZionSolutions icon.png |
Issue date: | 01/06/2014 |
From: | Sauger J ZionSolutions |
To: | Pederson C D Region 3 Administrator |
LaFranzo M M | |
References | |
ZS-2013-0005 | |
Download: ML14009A279 (1) | |
Text
January 6, 2014 Cynthia Pederson Regional Administrator U.S. NRC Region III 2443 Warrenville Road, Suite 210 Lisle, Illinois 60532-4352 All E1181VYSolutionoCompany Zion Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-39 and DPR-48 NRC Docket Nos. 50-295 and 50-304
Dear Ms. Pederson,
ZS-2013-0005 In our first meeting in November you made a number of commitments regarding the Independent Spent Fuel Storage Installation (ISFSI) at Zion with respect to review and turnaround times for completing the final licensing requirements.
On December 31st, we received word from headquarters that the Zion ISFSI was licensed for use and we could proceed with moving fuel from our pool to the pad. You were able to coordinate Region III resources as well as the program office at headquarters and NSER personnel such that many players from different departments focused on delivering a fully inspected and licensed facility on a timeline you established.
What stands out the most was your willingness to be accountable for delivering a regulatory solution that was timely and fully in compliance with regulations.
Thank-you.
Please pass along my thanks and acknowledgement to yours and the headquarters staff that worked through a busy holiday period to support the Zion Project. Sauger ral Manager ZionSolutions, LLC 101 Shiloh Boulevard, Zion