ENS 57813: Difference between revisions
Jump to navigation
Jump to search
StriderTol (talk | contribs) (StriderTol Bot insert) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 22: | Line 22: | ||
Due to the reactor protection system actuation while critical, this event is being reported as a four-hour, non-emergency notification per 10 CFR 50.72 (b)(2)(iv)(B). The expected actuation of the auxiliary feed water system (an engineered safety feature) is being reported as an eight-hour report under 10 CFR 50.72 (b)(3)(iv)(A). | Due to the reactor protection system actuation while critical, this event is being reported as a four-hour, non-emergency notification per 10 CFR 50.72 (b)(2)(iv)(B). The expected actuation of the auxiliary feed water system (an engineered safety feature) is being reported as an eight-hour report under 10 CFR 50.72 (b)(3)(iv)(A). | ||
There was no impact to the health and safety of the public or plant personnel. The NRC Senior Resident Inspector has been notified. | There was no impact to the health and safety of the public or plant personnel. The NRC Senior Resident Inspector has been notified. | ||
| URL = https://www.nrc.gov/reading-rm/doc-collections/event-status/event/2025/ | | URL = https://www.nrc.gov/reading-rm/doc-collections/event-status/event/2025/20250718en.html#en57813 | ||
}}{{unit info | }}{{unit info | ||
| Unit = 1 | | Unit = 1 | ||
Latest revision as of 06:20, 18 July 2025
| Where | |
|---|---|
| Prairie Island Minnesota (NRC Region 3) | |
| Reporting | |
| 10 CFR 50.72(b)(2)(iv)(B), RPS Actuation 10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
| Time - Person (Reporting Time:+-1.03 h-0.0429 days <br />-0.00613 weeks <br />-0.00141 months <br />) | |
| Opened: | Jason Rhody 13:57 Jul 16, 2025 |
| NRC Officer: | Josue Ramirez |
| Last Updated: | Jul 16, 2025 |
| 57813 - NRC Website
| |