| document type = Fuel Cycle Reload Report, Letter | | document type = Fuel Cycle Reload Report, Letter | ||
| page count = 15 | | page count = 15 | ||
}} | }} |
Revision as of 04:36, 26 February 2018
Letter Sequence Request | |
---|---|
EPID:L-2017-LRO-0029, Generator Tube Inspection Report (Approved, Closed) | |
MONTHYEARML17276A3482017-09-26026 September 2017
[Table View]Generator Tube Inspection Report Project stage: Request ML18137A1152018-05-30030 May 2018 Review of Spring 2017 Steam Generator Tube Inspection Report for Refueling Outage 39 Project stage: Approval 2017-09-26 |
ML17276A348 | |
Person / Time | |
---|---|
Site: | Ginna ![]() |
Issue date: | 09/26/2017 |
From: | Wilson D F Exelon Generation Co, Ginna |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
Download: ML17276A348 (15) | |
Similar Documents at Ginna | |
---|---|
Category:Fuel Cycle Reload Report
MONTHYEARML23121A0482023-05-0101 May 2023
[Table view]R. E. Ginna Nuclear Power Plant Core Operating Limits Report Cycle 44, Revision 0 ML22264A0842022-09-20020 September 2022 R. E. Ginna Nuclear Power Plant - Clarification Letter to the Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML22160A4162022-06-0909 June 2022 R. E. Ginna Nuclear Power Plant, Core Operating Limits Report Cycle 43, Revision 1 ML21287A0122021-10-13013 October 2021 Core Operating Limits Report Cycle 43, Revision ML20134H8402020-05-12012 May 2020 Core Operating Limits Report Cycle 42, Revision 0 ML18331A1652018-11-21021 November 2018 R. E. Ginna Nuclear Power Plant Core Operating Limits Report(Colr) Cycle 41 ML18142A2312018-05-16016 May 2018 Core Operating Limits Report Cycle 40, Revision 2 ML17276A3482017-09-26026 September 2017 Generator Tube Inspection Report ML17142A3062017-05-0909 May 2017 Submittal of Core Operating Limits Report Cycle 40, Revision 1 ML15308A1022015-10-29029 October 2015 Cycle 39 Core Operating Limits Report, Revision 0 ML14141A0322014-05-13013 May 2014 Transmittal of Core Operating Limits Report (COLR) for Cycle 38 ML12314A3752012-11-0808 November 2012 R. E. Ginna Nuclear Power Plant, Transmittal of Core Operating Limits Report (COLR) ML11325A1182011-11-15015 November 2011 2011 Steam Generator Tube Inspection Report ML11143A0142011-05-17017 May 2011 Transmittal of Core Operating Limits Report (COLR) ML0926800612009-09-18018 September 2009 R. E. Ginna - Transmittal of Core Operating Limits Report (COLR) ML0828102572008-09-30030 September 2008 R. E. Ginna Nuclear Power Plant Transmittal of Core Operating Limits Report (COLR) ML0819801222008-07-10010 July 2008 R. E. Ginna Nuclear Power Plant - Transmittal of Core Operating Limits Report (COLR) Cycle 34, Revision 1 ML0812905122008-05-0404 May 2008 R. E. Ginna - Transmittal of Core Operating Limits Report (Colr), Cycle 34, Revision 0 ML0631802262006-11-0303 November 2006 Transmittal of Core Operating Limits Report ML0527702432005-09-26026 September 2005 Transmittal of Core Operating Limits Report (COLR) ML0403305712004-01-23023 January 2004 Transmittal of Core Operating Limits Report (COLR) for R.E. Ginna Nuclear Power Plant ML0328203402003-10-0606 October 2003 Transmittal of Core Operating Limits Report, Cycle 31, Revision 0 ML0209900512002-04-0303 April 2002 Core Operating Limits Report (Colr), Revision 0, Cycle 30 ML18143A4471978-08-0707 August 1978 Transmittal of Non-Proprietary Revised Version of Additional Information Re Cycle 8 Fuel Reload 2023-05-01 Category:Letter MONTHYEARIR 05000244/20230042024-02-0505 February 2024
[Table view]LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of B Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23258A1382023-09-18018 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000244/2023010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23235A1722023-08-23023 August 2023 Re. Ginna Nuclear Power Plant, Transmittal of 2023 Owner'S Activity Report IR 05000244/20234012023-08-15015 August 2023 LLC - Material Control and Accounting Program Inspection Report 05000244/2023401 (Cover Letter Only) IR 05000244/20230022023-08-0303 August 2023 LLC - Integrated Inspection Report 05000244/2023002 ML23191A0592023-07-21021 July 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 155 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 IR 05000244/20234022023-07-19019 July 2023 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2023402 (Cover Letter Only) RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-050, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube.2023-05-22022 May 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube. ML23135A0412023-05-15015 May 2023 2022 Annual Radioactive Effluent Release Report and 2022 Annual Radiological Environmental Operating Report ML23121A0482023-05-0101 May 2023 R. E. Ginna Nuclear Power Plant Core Operating Limits Report Cycle 44, Revision 0 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI IR 05000244/20230012023-04-26026 April 2023 LLC - Integrated Inspection Report 05000244/2023001 ML23100A0302023-04-10010 April 2023 2023 10 CFR 50.46 Annual Report ML23114A1152023-03-29029 March 2023 Electronic Reporting of Exposure Data for 2022 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23075A0872023-03-15015 March 2023 R. E. Ginna Nuclear Power Plant - Project Manager Assignment ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) ML22364A0242023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant Issuance of Amendments Nos. 231, 231, 232, 232, and 154 Regarding Adoption of TSTF-246 ML23060A1622023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 ML23005A1762023-02-23023 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 153 Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes ML23005A1222023-02-22022 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No 152 Adopt TSTF-315-Revise Technical Specification 3.1.8, Physics Tests Exceptions - Mode 2 RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators ML22287A0692023-02-0808 February 2023 R. E. Ginna Station - Forward Fit Analysis (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and 0094) ML23031A2992023-02-0707 February 2023 R. E. Ginna Nuclear Power Plant - Withdrawal of an Amendment Request ML23010A0112023-02-0101 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Inservice Testing of Refueling Water Storage Tank Outlet Value RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000244/20223012023-01-20020 January 2023 Initial Operator Licensing Examination Report 05000244/2022301 IR 05000244/20220122023-01-12012 January 2023 LLC - Design Basis Assurance Inspection (Teams) Inspection Report 05000244/2022012 ML22362A0382022-12-28028 December 2022 R. E. Ginna Nuclear Power Plant - Letter to Withdraw Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML22348A2062022-12-14014 December 2022 Re. Ginna Nuclear Power Plant - Annual Commitment Change Notification RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator 2024-02-05 |