{{#Wiki_filter:}} | {{#Wiki_filter:From: Goetz, Sujata Sent: Thursday, October 7, 2021 10:33 AM To: Lashley, Phil H | ||
==Subject:== | |||
Beaver Valley Acceptance Review for LAR regarding TS 3.1.7.2 to correct a logic error ( L-2021-LLA-0160) | |||
Dear Mr. Lashley By {{letter dated|date=September 15, 2021|text=letter dated September 15, 2021}} (Agencywide Document and Access Management System Accession No. ML21259A090, Energy Harbor Nuclear Corp submitted a license amendment request for Beaver Valley Power Station Unit 2. The proposed amendment would remove a required action that currently has a logic error in Technical Specification 3.1.7.2, Unit 2 Rod Position Indication and renumbers another required action. | |||
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. | |||
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence. | |||
Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 120 hours to complete. The NRC staff expects to complete this review in approximately 12 months which would be October 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager. | |||
These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications. | |||
If you have any questions, please contact me. | |||
Sujata Goetz Project Manager, Beaver Valley | |||
Nuclear Regulatory Commission 11555 Rockville Pike Office of the Nuclear Reactor Regulation NRC/NRR/DORL/LPL3 Office O8F2 Mailroom O8-B1A Rockville, MD 20852-2738 Washington, DC 20555-0001 (o) 301.415.8004 (f) 301.415.3313 | |||
Hearing Identifier: NRR_DRMA Email Number: 1377 Mail Envelope Properties (MN2PR09MB5467A8388061CD973978864D80B19) | |||
==Subject:== | |||
Beaver Valley Acceptance Review for LAR regarding TS 3.1.7.2 to correct a logic error ( L-2021-LLA-0160) | |||
Sent Date: 10/7/2021 10:32:46 AM Received Date: 10/7/2021 10:32:00 AM From: Goetz, Sujata Created By: Sujata.Goetz@nrc.gov Recipients: | |||
"Lashley, Phil H" <phlashley@energyharbor.com> | |||
Tracking Status: None Post Office: MN2PR09MB5467.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3130 10/7/2021 10:32:00 AM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:}} |
Latest revision as of 13:33, 18 January 2022
ML21286A789 | |
Person / Time | |
---|---|
Site: | Beaver Valley |
Issue date: | 10/07/2021 |
From: | Sujata Goetz NRC/NRR/DORL/LPL1 |
To: | Lashley P Energy Harbor Nuclear Corp |
References | |
L-2021-LLA-0160 | |
Download: ML21286A789 (3) | |
Text
From: Goetz, Sujata Sent: Thursday, October 7, 2021 10:33 AM To: Lashley, Phil H
Subject:
Beaver Valley Acceptance Review for LAR regarding TS 3.1.7.2 to correct a logic error ( L-2021-LLA-0160)
Dear Mr. Lashley By letter dated September 15, 2021 (Agencywide Document and Access Management System Accession No. ML21259A090, Energy Harbor Nuclear Corp submitted a license amendment request for Beaver Valley Power Station Unit 2. The proposed amendment would remove a required action that currently has a logic error in Technical Specification 3.1.7.2, Unit 2 Rod Position Indication and renumbers another required action.
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 120 hours0.00139 days <br />0.0333 hours <br />1.984127e-4 weeks <br />4.566e-5 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months which would be October 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.
If you have any questions, please contact me.
Sujata Goetz Project Manager, Beaver Valley
Nuclear Regulatory Commission 11555 Rockville Pike Office of the Nuclear Reactor Regulation NRC/NRR/DORL/LPL3 Office O8F2 Mailroom O8-B1A Rockville, MD 20852-2738 Washington, DC 20555-0001 (o) 301.415.8004 (f) 301.415.3313
Hearing Identifier: NRR_DRMA Email Number: 1377 Mail Envelope Properties (MN2PR09MB5467A8388061CD973978864D80B19)
Subject:
Beaver Valley Acceptance Review for LAR regarding TS 3.1.7.2 to correct a logic error ( L-2021-LLA-0160)
Sent Date: 10/7/2021 10:32:46 AM Received Date: 10/7/2021 10:32:00 AM From: Goetz, Sujata Created By: Sujata.Goetz@nrc.gov Recipients:
"Lashley, Phil H" <phlashley@energyharbor.com>
Tracking Status: None Post Office: MN2PR09MB5467.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3130 10/7/2021 10:32:00 AM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: