==Dear Mr. Fowler:==
==Dear Mr. Fowler:==


By letter dated September 9, 2020 (Agencywide Documents Access and Management System Package Accession No. ML20266G182), NAC International (NAC) submitted an application for approval of the Model No. OPTIMUS-L transport package. The application is for a new package design for shipment of transuranic waste and irradiated fuel waste. Staff performed an acceptance review of your application to determine whether it contains sufficient technical information in scope and depth to allow the staff to complete a detailed technical review.
By {{letter dated|date=September 9, 2020|text=letter dated September 9, 2020}} (Agencywide Documents Access and Management System Package Accession No. ML20266G182), NAC International (NAC) submitted an application for approval of the Model No. OPTIMUS-L transport package. The application is for a new package design for shipment of transuranic waste and irradiated fuel waste. Staff performed an acceptance review of your application to determine whether it contains sufficient technical information in scope and depth to allow the staff to complete a detailed technical review.
Observations from our acceptance review are included in the enclosure to this letter. However, the application appears to contain the necessary information to begin our detailed technical review. The schedule allows for the staff to issue a possible request for additional information by the first week of April 2021, and, if no additional information is needed, issuance of a certificate of compliance by the end of September 2021, based on you responding to the request for additional information by the end of May 2021. The staff estimates that completing the safety review of this application will require approximately 850 staff hours.
Observations from our acceptance review are included in the enclosure to this letter. However, the application appears to contain the necessary information to begin our detailed technical review. The schedule allows for the staff to issue a possible request for additional information by the first week of April 2021, and, if no additional information is needed, issuance of a certificate of compliance by the end of September 2021, based on you responding to the request for additional information by the end of May 2021. The staff estimates that completing the safety review of this application will require approximately 850 staff hours.
Upon removal of Enclosure 2, this document is uncontrolled OFFICIAL USE ONLY - PROPRIETARY INFORMATION
Upon removal of Enclosure 2, this document is uncontrolled OFFICIAL USE ONLY - PROPRIETARY INFORMATION

Latest revision as of 20:27, 7 March 2021

OPTIMUS-L Acceptance Letter
ML20321A196
Person / Time
Site: OPTIMUS-L
Issue date: 12/01/2020
From: Bernie White
Division of Fuel Management
To: Fowler W
NAC International
BHWhite-NMSS/DFM/STLB-301.415.6577
Shared Package
ML20321A195 List:
References
EPID L-2020-LLA-0202
Download: ML20321A196 (3)


Text

OFFICIAL USE ONLY - PROPRIETARY INFORMATION December 1, 2020 Mr. Wren Fowler Director, Licensing Engineering NAC International 3930 East Jones Bridge Road, Suite 200 Norcross, GA 30092

SUBJECT:

APPLICATION FOR THE MODEL NO. OPTIMUS-L TRANSPORT PACKAGE -

ACCEPTANCE LETTER

Dear Mr. Fowler:

By letter dated September 9, 2020 (Agencywide Documents Access and Management System Package Accession No. ML20266G182), NAC International (NAC) submitted an application for approval of the Model No. OPTIMUS-L transport package. The application is for a new package design for shipment of transuranic waste and irradiated fuel waste. Staff performed an acceptance review of your application to determine whether it contains sufficient technical information in scope and depth to allow the staff to complete a detailed technical review.

Observations from our acceptance review are included in the enclosure to this letter. However, the application appears to contain the necessary information to begin our detailed technical review. The schedule allows for the staff to issue a possible request for additional information by the first week of April 2021, and, if no additional information is needed, issuance of a certificate of compliance by the end of September 2021, based on you responding to the request for additional information by the end of May 2021. The staff estimates that completing the safety review of this application will require approximately 850 staff hours.

Upon removal of Enclosure 2, this document is uncontrolled OFFICIAL USE ONLY - PROPRIETARY INFORMATION

OFFICIAL USE ONLY - PROPRIETARY INFORMATION W. Fowler Please reference Docket No. 71-9390 and Enterprise Project Identifier (EPID) No.

L-2020-LLA-0202 in future correspondence related to this request.

Sincerely, Bernard H. Digitally signed by Bernard H.

White White Date: 2020.12.01 10:27:04 -05'00' Bernard H. White IV, Senior Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards

Enclosures:

1. Non-proprietary Observations
2. Proprietary Observations Docket No. 71-9390 EPID No. L-2020-LLA-0202 OFFICIAL USE ONLY - PROPRIETARY INFORMATION

ML20321A195 (Pkg) ML20321A196 (Ltr) *via email OFFICE DFM DFM DFM DFM NAME BWhite WWheatley* PPravin* JChang*

DATE 11/9/2020 11/18/2020 11/9/2020 11/10/2020 OFFICE DFM DFM DFM NAME MDiaz-Maldonado* TBoyce* JMcKirgan*

DATE 11/24/2020 11/19/2020 11/24/2020