{{#Wiki_filter:SUPPLEMENT NO. 2 TO AEC REGULATORY STAFF SAFETY EVALUATION IN THE MATTER OF CONSOLIDATED EDISON COMPANY INDIAN POINT NUCLEAR GENERATING PLANT UNIT 2 DOCKET NO. 50-247 July, 1971 Prepared by Division of Compliance U. S. Atomic Energy Commission I. INTRODUCTION This supplement updates the Division of Compliance Supplement No. 1, dated November 20, 1970, to the Safety Evaluation dated November 16, 1970, prepared by the Division of Reactor Licensing of the Atomic Energy Commission in connection with its review of the application of the Consolidated Edison Company for an operating license for Unit 2 of the Indian Point Nuclear Generating Station located in Buchanan, New York.The paragraph titles and numbers used in this supplement correspond to those in Supplement No. 1. The page references in parenthesis iden-tify the page in Supplement No. I where the updated information super-sedes that stated in Supplement No. 1.II. RESULTS OF CONSTRUCTION INSPECTIONS A. Reactor Coolant System 1. Reactor Coolant Pressure Piping (page 8)Certain cast valve discs (7) had not been radiographed.
{{#Wiki_filter:SUPPLEMENT NO. 2 TO AEC REGULATORY STAFF SAFETY EVALUATION IN THE MATTER OF CONSOLIDATED EDISON COMPANY INDIAN POINT NUCLEAR GENERATING PLANT UNIT 2 DOCKET NO. 50-247 July, 1971 Prepared by Division of Compliance U. S. Atomic Energy Commission
The necessity for radiographing these valve discs was evalu-ated by Compliance Headquarters and the Division of Reactor Licensing.
 
This review resulted in an agreement that none of the subject valves is contained within the reactor coolant pressure boundary and therefore the discs do not require radiographic examination. 3. Steam Generators Ultrasonic examination of the steam generator cladding revealed evidence of tube sheet cladding separation in the vicinity of the divider plate.Completion Status: The steam generator cladding problem .is presently being evaluated by the applicant.
                                        -2  -
Satisfactory resolution, including any required repairs, is necessary before an operating license is issued.5. Pressurizer (Page 11 and 12)Pre-service ultrasonic examination of the pressurizer welds revealed the presence of non-metallic inclusions in the base plate material.
I. INTRODUCTION This supplement updates the Division of Compliance Supplement No. 1, dated November 20,   1970,   to the Safety Evaluation dated November 16,   1970, prepared by the Division of Reactor Licensing of the Atomic Energy Commission in     connection with its   review of the application of the Consolidated Edison Company for an operating license for Unit 2 of the Indian Point Nuclear Generating Station located in Buchanan,   New York.
The applicant submitted a report to the Division of Reactor Licensing on this subject. The condition was evaluated and considered to be acceptable.
The paragraph titles and numbers used in       this supplement correspond to those in   Supplement No. 1. The page references   in parenthesis iden-tify the page in   Supplement No. I where the updated information super-sedes that stated in   Supplement No. 1.
The in-service ultrasonic examination requirements were expanded for the area in question, and the item is con-sidered satisfactorily resolved.Completion Status: Construction of the pressurizer has been completed.
II. RESULTS OF CONSTRUCTION INSPECTIONS A. Reactor Coolant System
: 1. Reactor Coolant Pressure Piping (page 8)
Certain cast valve discs (7)     had not been radiographed.
The necessity for radiographing     these valve discs was evalu-ated by Compliance Headquarters     and the Division of Reactor Licensing. This review resulted in     an agreement that none of the subject valves is     contained within the reactor coolant pressure boundary and therefore the discs do not require radiographic examination.
: 3. Steam Generators Ultrasonic examination of the steam generator cladding revealed evidence of tube sheet cladding separation in     the vicinity of the divider plate.
Completion Status:   The steam generator cladding problem .is presently being evaluated by the applicant.     Satisfactory resolution, including any required repairs,   is necessary before an operating license is   issued.
: 5. Pressurizer (Page 11 and 12)
Pre-service ultrasonic examination of the pressurizer welds revealed the presence of non-metallic inclusions in the base plate material. The applicant submitted a report to the Division of Reactor Licensing on this subject.       The condition was evaluated and considered to be acceptable.
The in-service ultrasonic examination requirements were expanded for the area in question, and the item is     con-sidered satisfactorily resolved.
Completion Status:   Construction of the pressurizer has been completed.


==
==
Conclusions:==
Conclusions:==
(page 12) Based on the results of pfevious inspection and corrective actions take. by the applicant and contractor to date, we conclude that there is reasonable assurance that the reactor coolant system will have been completed in accordance with AEC regulatory requirements.
(page 12) Based on the results of pfevious inspection and corrective actions take. by the applicant and contractor to date, we conclude that there is   reasonable
B. Containment and Class I Structure 1. Primary Containment (Pages 13 and 14)Problems identified by the applicant during construc-tion included lack of full traceability of documentation on pipe penetration materials.
 
The applicant reviewed the available documentation and performed additional field testing to verify that the penetrations did meet the intent of the requirements described in the applica-tion. The penetrations are continuously pressurized by the penetration and weld channel pressurization system and if leaks should develop the leakage could be detected.Based on the results of the applicant's evaluations and testing, Compliance considers the subject to be resolved.The containment leak rate test has been performed and preliminary calculations indicate that the leak rate is within the proposed Technical Specifications limit.Completion Status: The concrete placement has been completed, the penetration bellows question has been resolved, and the containment leak rate test has been performed.
assurance that the reactor coolant system will have been completed in accordance with AEC regulatory requirements.
This system will be crnsidered complete following the installation of the reactor coolant system leak detection equipment and upon a determination from the final calculations that the integrated leak rate is within Technical Specifications limits.C. Engineered Safety Features 1. Emergency Core Cooling System (ECCS) (Pages 15-18).Results of our inspection included the following:
B. Containment and Class I Structure
: 1. Primary Containment (Pages 13 and 14)
Problems identified by the applicant during construc-tion included lack of full traceability of documentation on pipe penetration materials. The applicant reviewed the available documentation and performed additional field testing to verify that the penetrations did meet the intent of the requirements described in the applica-tion. The penetrations are continuously pressurized by the penetration and weld channel pressurization system and if leaks should develop the leakage could be detected.
Based on the results of the applicant's evaluations and testing, Compliance considers the subject to be resolved.
The containment leak rate test has been performed and preliminary calculations indicate that the leak rate is within the proposed Technical Specifications limit.
Completion Status:     The concrete placement has been completed, the penetration bellows question has been resolved, and the containment leak rate test has been performed. This system will be crnsidered complete following the installation of the reactor coolant system
 
leak detection equipment and upon a determination from the final calculations that the integrated leak rate is within Technical Specifications limits.
C. Engineered Safety Features
: 1. Emergency Core Cooling System (ECCS)     (Pages 15-18).
Results of our inspection included the following:
: a. Welding quality control records were incomplete.
: a. Welding quality control records were incomplete.
: b. Visual inspection indicated a weakness in first line quality control; i.e., weld splatter, arc strikes, and excessive grinding.c. Accumulator check.valves were not manufactured to specifications.
: b. Visual inspection indicated a weakness   in   first line quality control; i.e.,   weld splatter, arc strikes, and excessive grinding.
The applicant initiated a program for verification of proper record keeping. Our review of independent record checks which were performed by the licensee satisfied our concerns in this area and item a. above is considered satisfactorily resolved.The applicant similarly initiated a final mechanical surface cleanup program. The inspection and cleaning were performed just prior to application of insulation.
: c. Accumulator check.valves were not manufactured to specifications.
Our review in the field did not identify additional deficiencies.
The applicant initiated a program for verification of proper record keeping. Our review of independent record checks which were performed by the licensee satisfied our concerns in this area and item a. above is considered satisfactorily resolved.
This program is considered to resolve weakness in first line quality control as indicated in item b. above. The applicant initiated a program for evaluation of the acceptability of the accumulator check valves and concluded that the valves were adequate for the intended use. Our subsequent evaluations of this subject provided a satisfactory resolution for the item c. above.Completion Status: (Page 16) Construction of the ECCS system is essentially complete.
The applicant similarly initiated a final mechanical surface cleanup program. The inspection and cleaning were performed just prior to application of insulation.         Our review in   the field did not identify additional deficiencies.
Remaining work to be accomplished includes:
This program is   considered to resolve weakness in     first line quality control as indicated in   item b. above.
(1) finish surface cleanup, (2)completion of hanger and support installation.
 
: 2. Containment Spray and Fan Cooling Systems (Page 17)Containment spray pump #21 was returned to the vendor shop due to excessive vibrations noted during the performance of preoperational testing.Completion Status: Construction of the containment spray and fan cooling systems is nearing completion.
The applicant initiated a program for evaluation of the acceptability of the accumulator check valves and concluded that the valves were adequate for the intended use. Our subsequent evaluations of this subject provided a satisfactory resolution for the item c. above.
Work remain-ing includes filter testing, satisfactory repair of contain-ment spray pump No. 21 and functional testing.3. Post Accident Hydrogen Control System (Page 17)The post accident hydrogen control system has been installed.
Completion Status:   (Page 16) Construction of the ECCS system is essentially complete. Remaining work to be accomplished includes:     (1) finish surface cleanup, (2) completion of hanger and support installation.
Completion Status: Installation of the required hydrogen control system has been completed. D. Instrumentation, Control and Power Systems (Pages 18-20)2. Our initial observation was that independent quality control of cable installation was lacking. Subsequently, the appli-cant performed an audit program relating to cable installation conformance to pulling schedules.
: 2. Containment Spray and Fan Cooling Systems (Page 17)
This audit included about 80 percent of the protection and safeguards cabling. This audit provided confidence that the cable installation con-formed to the pulling schedule.
Containment spray pump #21 was returned to the vendor shop due to excessive vibrations noted during the performance of preoperational testing.
Our review of this audit resolved our previous concerns.4. Our inspection program revealed items which required additional design consideration.
Completion Status:   Construction of the containment spray and fan cooling systems is     nearing completion. Work remain-ing includes filter   testing, satisfactory repair of contain-ment spray pump No. 21 and functional testing.
Each of these items has been reviewed, corrective actions identified, and the necessary revisions are nearing completion.
: 3. Post Accident Hydrogen Control System (Page 17)
Completion Status: Redundant cables for the tunnel fans have been installed and the cable surveillance program is considered to be complete.
The post accident hydrogen control system has been installed.
Items remaining to be completed include: 1. Installation of remainder of separation barriers and fire stops.3. Installation of transite barriers at the single penetration area. E. Radioactive Waste Control (Page 20)A further review.of the radioactive waste control system revealed that the radiation monitoring installation was essentially complete; however, the following items require resolution:  
Completion Status:   Installation of the required hydrogen control system has been completed.
;1. Adequacy of the stack monitoring sample probe location.2. Lack of continuous monitoring for stack halogens and particulates.
 
: 3. Adequacy of the liquid waste disposal system capacity.4. Adequacy of liquid sampling probes.5. Need for charcoal filters in the containment building purge line.Completion Status: The radioactive waste control system is essentially complete with the exception of the satisfactory resolution of items 1 through 5 above.Conclusion:
D. Instrumentation, Control and Power Systems (Pages 18-20)
: 2. Our initial observation was that independent quality control of cable installation was lacking. Subsequently, the appli-cant performed an audit program relating to cable installation conformance to pulling schedules. This audit included about 80 percent of the protection and safeguards cabling. This audit provided confidence that the cable installation con-formed to the pulling schedule. Our review of this audit resolved our previous concerns.
: 4. Our inspection program revealed items which required additional design consideration. Each of these items has been reviewed,   corrective actions identified, and the necessary revisions are nearing completion.
Completion Status:   Redundant cables for the tunnel fans have been installed and the cable surveillance program is considered to be complete. Items remaining to be completed include:
: 1. Installation of remainder of separation barriers and fire stops.
: 3. Installation of transite barriers at the single penetration area.
 
E. Radioactive Waste Control (Page 20)
A further review.of the radioactive waste control system revealed that the radiation monitoring installation was essentially complete; however,   the following items require resolution:;
: 1. Adequacy of the stack monitoring sample probe location.
: 2. Lack of continuous monitoring for stack halogens and particulates.
: 3. Adequacy of the liquid waste disposal system capacity.
: 4. Adequacy of liquid sampling probes.
: 5. Need for charcoal filters in the containment building purge line.
Completion Status:   The radioactive waste control system is essentially complete with the exception of the satisfactory resolution of items 1 through 5 above.
 
== Conclusion:==
Based on inspections to date and the applicant's planned actions, we conclude that there is reasonable assurance that the radioactive waste disposal system will be completed in accordance with AEC regulatory requirements.
Based on inspections to date and the applicant's planned actions, we conclude that there is reasonable assurance that the radioactive waste disposal system will be completed in accordance with AEC regulatory requirements.
G. Conauct of Operation (Pages 21-22)Conduct of operation as used here includes organization and staffing, preparation and review of procedures, and the administrative directives which the applicant has developed to conduct the functional testing program and subsequent operation of the Unit 2 facility.
G. Conauct of Operation (Pages 21-22)
We have verified that--the applicant has established operational review and audit co-m-ittees which are actively engaged in activities relating to plant startup. We have verified that the applicant has developed a program for functional testing of equipment and systems.1. Procedure Preparation-The proposed functional test procedures have been approved for use by the applicant.
Conduct of operation as used here includes organization and staffing, preparation and review of procedures,   and the administrative directives which the applicant has developed
We have examined these procedures on a selective basis. We have completed an examination of the program and procedures-associated with fuel loading and have initiated our review of power ascension testing outlines and available'procedures.
 
to conduct the functional testing program and subsequent operation of the Unit 2 facility. We have verified that--
the applicant has established operational review and audit co-m-ittees which are actively engaged in activities relating to plant startup. We have verified that the applicant has developed a program for functional testing of equipment and systems.
: 1. Procedure Preparation-The proposed functional test procedures have been approved for use by the applicant. We have examined these procedures on a selective basis. We have completed an examination of the program and procedures-associated with fuel loading and have initiated our review of power ascension testing outlines and available'procedures.
We have reviewed the index for proposed plant operating procedures and a selected number of key procedures.
We have reviewed the index for proposed plant operating procedures and a selected number of key procedures.
Completion Status: The proposed functional testing pro-cedures have been approved for use by the applicant.
Completion Status:   The proposed functional testing pro-cedures have been approved for use by the applicant.
Items have been identified to the applicant for additional test coverage consideration. The fuel loading procedures have been completed.
Items have been identified to the applicant for additional test coverage consideration.
Eighty percent of the proposed power ascension test procedures have been approved by the applicant.
 
The remaining procedures are.receiving a final review by the applicant.
The fuel loading procedures have been completed.
The review of the plant operating procedures index indicated that it was not broad enough in scope and the selected procedures examined did not contain an acceptable degree of detail. Specifically, the index did not contain surveillance, response to alarms, or maintenance procedures, and operating procedures were not provided for all systems involved in nuclear safety. The individual procedures contained nonspecific terms such as "normal," "appropriate,""as necessary," and-"as required." The applicant subse-quently initiated a program for expanding and upgrading the operating procedure scope and detail coverage.Compliance will reexamine these areas.Preparation of functional testing, power ascension and operating procedures-is-scheduled to be completed prior to licensing.
Eighty percent of the proposed power ascension test procedures have been approved by the applicant. The remaining procedures are.receiving a final review by the applicant.
: 2. Functional Testing We have witnessed the performance of portions of the reactor coolant system hydrostatic, hot functional,  containment leak rate, containment overpressure and high pressure safety injection tests. We have also selectively examined the results of tests which have been completed.
The review of the plant operating procedures index indicated that it was not broad enough in scope and the selected procedures examined did not contain an acceptable degree of detail. Specifically, the index did not contain surveillance, response to alarms, or maintenance procedures, and operating procedures were not provided for all systems involved in nuclear safety. The individual procedures contained nonspecific terms such as "normal," "appropriate,"
Completion Status: Functional testing has progressed through the hot functional testing program and about 80 percent of the testing requirements for operating licensing have been completed.
  "as necessary," and-"as required."   The applicant subse-quently initiated a program for expanding and upgrading the operating procedure scope and detail coverage.
Compliance will reexamine these areas.
Preparation of functional testing, power ascension and operating procedures-is-scheduled to be completed prior to licensing.
: 2. Functional Testing We have witnessed the performance of portions of the reactor coolant system hydrostatic, hot functional,
 
                        -  11 -
containment leak rate,     containment overpressure and high pressure safety injection tests.       We have also selectively examined the results of tests which have been completed.
Completion Status:     Functional testing has progressed through the hot functional testing program and about 80 percent of the testing requirements for operating licensing have been completed.
Evaluation of functional test results by the applicant and our confirmation of the testing program completion is scheduled prior to licensing.
Evaluation of functional test results by the applicant and our confirmation of the testing program completion is scheduled prior to licensing.
: 3. Plant Security A review of plant security construction revealed that the following has not been completed.
: 3. Plant Security A review of plant security construction revealed that the following has not been completed.
: a. Erection of the restricted area fence.b. Construction of the controlled access passageways to the containment, fuel storage, primary auxiliary and emergency diesel buildings.
: a. Erection of the restricted area fence.
: c. Doors and associated alarm systems.Completion Status: Plant security construction is scheduled to be completed prior to plant licensing.
: b. Construction of the controlled access passageways to the containment,     fuel storage, primary auxiliary and emergency diesel buildings.
: c. Doors and associated alarm systems.
Completion Status:     Plant security construction is   scheduled to be completed prior to plant licensing.


==
==
Conclusions:==
Conclusions:==
Based on the results of our inspection to date and responsive action taken by the applicant previously, we conclude that the administrative organization is      in conformance with the application and that testing will be completed in accordance with AEC regulatory requirements.
APPENDIX A CHRONOLOGY OF COMPLIANCE DIVISION INSPECTIONS CONSOLIDATED EDISON COMPANY INDIAN POINT NUCLEAR GENERATING STATION UNIT 2 Date            Type of Inspection              Scope of Inspection 11/4, 5,        Site                      Continued inspections of preop-24,  25/70                                erational test program, mechanical system cleanup, containment closure and pipe support installation.
Resolved six previously identified items of concern.
12/2/70        Management meeting        Discussed views relating to a sample review of IP-2 preopera-tional procedures and reviewed the proposed guidance for preop-erational testing programs.
12/16/70 &      Site-inspection          Continued inspections on preop-1/6, 7/71                                erational testing and mechanical system cleanup. Reviewed core loading and the available portions of power ascension program.
Obtained resolution for nine previously identified items of concern.
12/7 -          Site                      Reviewed construction log books 10/70                                    maintained by applicant and contractors. Eighty-five questions were presented to the applicant for resolution.
1/12 &          Corporate Management      Discussed apparent deficiencies 15/71                                      in the preoperational testing, power ascension program, and operating procedures.
1/20  -        Site                      Reviewed pipe design analysis 21/71                                    and pipe support installation.
Date          T)rpe of Inspection        Scope of Inspection 1/20, 21,      Site                Continued inspection activity 22, 28, 29 &                        relating to preoperational 2/3/71                              testing, and power ascension pro-grams and operating procedures.
Reviewed programs relating to operator involvement and check-out of operating procedures during hot functional testing.
Inspected final results of-field weld documentation verification program.
2/5/71        Corporate Management Discussed resolution status relating to previously identified deficiencies in the preoperational test program.
2/10-11/71    Site and Engineering Continued inspection efforts in offices              the areas of preoperational testing, power ascension pro-grams and operating procedures.
2/17/71        Engineering offices  Reviewed the results of evalua-tions relating to pressurizer base plate and discussed the need for an expanded inservice inspection.
2/23,  24/71  Site                Continued review of preopera-tional test, pipe support installation and resolution of outstanding items. Discussed reactor coolant pump repairs, circulating water pump testing, and loss of off-site power.
3/5,  6,  8/71                      Witnessed portions of the con-tainment overpressure and leak rate tests.
3/10-12/71                          Continued inspection efforts, relating to preoperational test-ing, operating procedures and pipe supports. Reviewed electrical jumper and termination control program.


Based on the results of our inspection to date and responsive action taken by the applicant previously, we conclude that the administrative organization is in conformance with the application and that testing will be completed in accordance with AEC regulatory requirements.
Date       Type of Inspection       Sco e of Inspection 3/15/71     Site               Review damage to polar crane pedestal and witness a portion of the high pressure safety injection testing.
APPENDIX A CHRONOLOGY OF COMPLIANCE DIVISION INSPECTIONS CONSOLIDATED EDISON COMPANY INDIAN POINT NUCLEAR GENERATING STATION UNIT 2 Date Type of Inspection Scope of Inspection 11/4, 5, 24, 25/70 Site 12/2/70 12/16/70 &1/6, 7/71 Management meeting Site-inspection Continued inspections of preop-erational test program, mechanical system cleanup, containment closure and pipe support installation.
3/16/71    Engineering Office Review status and progress of operating procedure revisions.
Resolved six previously identified items of concern.Discussed views relating to a sample review of IP-2 preopera-tional procedures and reviewed the proposed guidance for preop-erational testing programs.Continued inspections on preop-erational testing and mechanical system cleanup. Reviewed core loading and the available portions of power ascension program.Obtained resolution for nine previously identified items of concern.Reviewed construction log books maintained by applicant and contractors.
3/19, 23,  Site              Review resolution of construc-25/71                          tion log book review questions.
Eighty-five questions were presented to the applicant for resolution.
4/6, 7, 8,  Site              Review preoperational testing, 21, 22/71                      power ascension program, pipe support installation, polar crane repairs, organizational coverage and resolution of pre-viously identified items.
Discussed apparent deficiencies in the preoperational testing, power ascension program, and operating procedures.
5/4, 5, 14, Site              Review preoperational testing, 26, 27/71                      power ascension programs, operating procedure preparation, implementation of security and emergency plan and resolution of previously identified items.}}
Reviewed pipe design analysis and pipe support installation.
12/7 -10/70 Site 1/12 &15/71 1/20 -21/71 Corporate Management Site Date T)rpe of Inspection Scope of Inspection 1/20, 21, 22, 28, 29 &2/3/71 Site 2/5/71 2/10-11/71 2/17/71 Corporate Management Site and Engineering offices Engineering offices Continued inspection activity relating to preoperational testing, and power ascension pro-grams and operating procedures.
Reviewed programs relating to operator involvement and check-out of operating procedures during hot functional testing.Inspected final results of-field weld documentation verification program.Discussed resolution status relating to previously identified deficiencies in the preoperational test program.Continued inspection efforts in the areas of preoperational testing, power ascension pro-grams and operating procedures.
Reviewed the results of evalua-tions relating to pressurizer base plate and discussed the need for an expanded inservice inspection.
Continued review of preopera-tional test, pipe support installation and resolution of outstanding items. Discussed reactor coolant pump repairs, circulating water pump testing, and loss of off-site power.Witnessed portions of the con-tainment overpressure and leak rate tests.Continued inspection efforts, relating to preoperational test-ing, operating procedures and pipe supports.
Reviewed electrical jumper and termination control program.2/23, 24/71 Site 3/5, 6, 8/71 3/10-12/71 Date Type of Inspection Sco e of Inspection 3/15/71 Site 3/16/71 Engineering Office 3/19, 23, 25/71 4/6, 7, 8, 21, 22/71 5/4, 5, 14, 26, 27/71 Site Site Site Review damage to polar crane pedestal and witness a portion of the high pressure safety injection testing.Review status and progress of operating procedure revisions.
Review resolution of construc-tion log book review questions.
Review preoperational testing, power ascension program, pipe support installation, polar crane repairs, organizational coverage and resolution of pre-viously identified items.Review preoperational testing, power ascension programs, operating procedure preparation, implementation of security and emergency plan and resolution of previously identified items.}}

Latest revision as of 04:33, 23 November 2019

Safety Evaluation Report, Supplement 2
ML072260453
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 07/31/1971
From:
US Atomic Energy Commission (AEC)
To:
US Atomic Energy Commission (AEC)
References
FOIA/PA-2009-0166
Download: ML072260453 (14)


Text

SUPPLEMENT NO. 2 TO AEC REGULATORY STAFF SAFETY EVALUATION IN THE MATTER OF CONSOLIDATED EDISON COMPANY INDIAN POINT NUCLEAR GENERATING PLANT UNIT 2 DOCKET NO. 50-247 July, 1971 Prepared by Division of Compliance U. S. Atomic Energy Commission

-2 -

I. INTRODUCTION This supplement updates the Division of Compliance Supplement No. 1, dated November 20, 1970, to the Safety Evaluation dated November 16, 1970, prepared by the Division of Reactor Licensing of the Atomic Energy Commission in connection with its review of the application of the Consolidated Edison Company for an operating license for Unit 2 of the Indian Point Nuclear Generating Station located in Buchanan, New York.

The paragraph titles and numbers used in this supplement correspond to those in Supplement No. 1. The page references in parenthesis iden-tify the page in Supplement No. I where the updated information super-sedes that stated in Supplement No. 1.

II. RESULTS OF CONSTRUCTION INSPECTIONS A. Reactor Coolant System

1. Reactor Coolant Pressure Piping (page 8)

Certain cast valve discs (7) had not been radiographed.

The necessity for radiographing these valve discs was evalu-ated by Compliance Headquarters and the Division of Reactor Licensing. This review resulted in an agreement that none of the subject valves is contained within the reactor coolant pressure boundary and therefore the discs do not require radiographic examination.

3. Steam Generators Ultrasonic examination of the steam generator cladding revealed evidence of tube sheet cladding separation in the vicinity of the divider plate.

Completion Status: The steam generator cladding problem .is presently being evaluated by the applicant. Satisfactory resolution, including any required repairs, is necessary before an operating license is issued.

5. Pressurizer (Page 11 and 12)

Pre-service ultrasonic examination of the pressurizer welds revealed the presence of non-metallic inclusions in the base plate material. The applicant submitted a report to the Division of Reactor Licensing on this subject. The condition was evaluated and considered to be acceptable.

The in-service ultrasonic examination requirements were expanded for the area in question, and the item is con-sidered satisfactorily resolved.

Completion Status: Construction of the pressurizer has been completed.

==

Conclusions:==

(page 12) Based on the results of pfevious inspection and corrective actions take. by the applicant and contractor to date, we conclude that there is reasonable

assurance that the reactor coolant system will have been completed in accordance with AEC regulatory requirements.

B. Containment and Class I Structure

1. Primary Containment (Pages 13 and 14)

Problems identified by the applicant during construc-tion included lack of full traceability of documentation on pipe penetration materials. The applicant reviewed the available documentation and performed additional field testing to verify that the penetrations did meet the intent of the requirements described in the applica-tion. The penetrations are continuously pressurized by the penetration and weld channel pressurization system and if leaks should develop the leakage could be detected.

Based on the results of the applicant's evaluations and testing, Compliance considers the subject to be resolved.

The containment leak rate test has been performed and preliminary calculations indicate that the leak rate is within the proposed Technical Specifications limit.

Completion Status: The concrete placement has been completed, the penetration bellows question has been resolved, and the containment leak rate test has been performed. This system will be crnsidered complete following the installation of the reactor coolant system

leak detection equipment and upon a determination from the final calculations that the integrated leak rate is within Technical Specifications limits.

C. Engineered Safety Features

1. Emergency Core Cooling System (ECCS) (Pages 15-18).

Results of our inspection included the following:

a. Welding quality control records were incomplete.
b. Visual inspection indicated a weakness in first line quality control; i.e., weld splatter, arc strikes, and excessive grinding.
c. Accumulator check.valves were not manufactured to specifications.

The applicant initiated a program for verification of proper record keeping. Our review of independent record checks which were performed by the licensee satisfied our concerns in this area and item a. above is considered satisfactorily resolved.

The applicant similarly initiated a final mechanical surface cleanup program. The inspection and cleaning were performed just prior to application of insulation. Our review in the field did not identify additional deficiencies.

This program is considered to resolve weakness in first line quality control as indicated in item b. above.

The applicant initiated a program for evaluation of the acceptability of the accumulator check valves and concluded that the valves were adequate for the intended use. Our subsequent evaluations of this subject provided a satisfactory resolution for the item c. above.

Completion Status: (Page 16) Construction of the ECCS system is essentially complete. Remaining work to be accomplished includes: (1) finish surface cleanup, (2) completion of hanger and support installation.

2. Containment Spray and Fan Cooling Systems (Page 17)

Containment spray pump #21 was returned to the vendor shop due to excessive vibrations noted during the performance of preoperational testing.

Completion Status: Construction of the containment spray and fan cooling systems is nearing completion. Work remain-ing includes filter testing, satisfactory repair of contain-ment spray pump No. 21 and functional testing.

3. Post Accident Hydrogen Control System (Page 17)

The post accident hydrogen control system has been installed.

Completion Status: Installation of the required hydrogen control system has been completed.

D. Instrumentation, Control and Power Systems (Pages 18-20)

2. Our initial observation was that independent quality control of cable installation was lacking. Subsequently, the appli-cant performed an audit program relating to cable installation conformance to pulling schedules. This audit included about 80 percent of the protection and safeguards cabling. This audit provided confidence that the cable installation con-formed to the pulling schedule. Our review of this audit resolved our previous concerns.
4. Our inspection program revealed items which required additional design consideration. Each of these items has been reviewed, corrective actions identified, and the necessary revisions are nearing completion.

Completion Status: Redundant cables for the tunnel fans have been installed and the cable surveillance program is considered to be complete. Items remaining to be completed include:

1. Installation of remainder of separation barriers and fire stops.
3. Installation of transite barriers at the single penetration area.

E. Radioactive Waste Control (Page 20)

A further review.of the radioactive waste control system revealed that the radiation monitoring installation was essentially complete; however, the following items require resolution:;

1. Adequacy of the stack monitoring sample probe location.
2. Lack of continuous monitoring for stack halogens and particulates.
3. Adequacy of the liquid waste disposal system capacity.
4. Adequacy of liquid sampling probes.
5. Need for charcoal filters in the containment building purge line.

Completion Status: The radioactive waste control system is essentially complete with the exception of the satisfactory resolution of items 1 through 5 above.

Conclusion:

Based on inspections to date and the applicant's planned actions, we conclude that there is reasonable assurance that the radioactive waste disposal system will be completed in accordance with AEC regulatory requirements.

G. Conauct of Operation (Pages 21-22)

Conduct of operation as used here includes organization and staffing, preparation and review of procedures, and the administrative directives which the applicant has developed

to conduct the functional testing program and subsequent operation of the Unit 2 facility. We have verified that--

the applicant has established operational review and audit co-m-ittees which are actively engaged in activities relating to plant startup. We have verified that the applicant has developed a program for functional testing of equipment and systems.

1. Procedure Preparation-The proposed functional test procedures have been approved for use by the applicant. We have examined these procedures on a selective basis. We have completed an examination of the program and procedures-associated with fuel loading and have initiated our review of power ascension testing outlines and available'procedures.

We have reviewed the index for proposed plant operating procedures and a selected number of key procedures.

Completion Status: The proposed functional testing pro-cedures have been approved for use by the applicant.

Items have been identified to the applicant for additional test coverage consideration.

The fuel loading procedures have been completed.

Eighty percent of the proposed power ascension test procedures have been approved by the applicant. The remaining procedures are.receiving a final review by the applicant.

The review of the plant operating procedures index indicated that it was not broad enough in scope and the selected procedures examined did not contain an acceptable degree of detail. Specifically, the index did not contain surveillance, response to alarms, or maintenance procedures, and operating procedures were not provided for all systems involved in nuclear safety. The individual procedures contained nonspecific terms such as "normal," "appropriate,"

"as necessary," and-"as required." The applicant subse-quently initiated a program for expanding and upgrading the operating procedure scope and detail coverage.

Compliance will reexamine these areas.

Preparation of functional testing, power ascension and operating procedures-is-scheduled to be completed prior to licensing.

2. Functional Testing We have witnessed the performance of portions of the reactor coolant system hydrostatic, hot functional,

- 11 -

containment leak rate, containment overpressure and high pressure safety injection tests. We have also selectively examined the results of tests which have been completed.

Completion Status: Functional testing has progressed through the hot functional testing program and about 80 percent of the testing requirements for operating licensing have been completed.

Evaluation of functional test results by the applicant and our confirmation of the testing program completion is scheduled prior to licensing.

3. Plant Security A review of plant security construction revealed that the following has not been completed.
a. Erection of the restricted area fence.
b. Construction of the controlled access passageways to the containment, fuel storage, primary auxiliary and emergency diesel buildings.
c. Doors and associated alarm systems.

Completion Status: Plant security construction is scheduled to be completed prior to plant licensing.

==

Conclusions:==

Based on the results of our inspection to date and responsive action taken by the applicant previously, we conclude that the administrative organization is in conformance with the application and that testing will be completed in accordance with AEC regulatory requirements.

APPENDIX A CHRONOLOGY OF COMPLIANCE DIVISION INSPECTIONS CONSOLIDATED EDISON COMPANY INDIAN POINT NUCLEAR GENERATING STATION UNIT 2 Date Type of Inspection Scope of Inspection 11/4, 5, Site Continued inspections of preop-24, 25/70 erational test program, mechanical system cleanup, containment closure and pipe support installation.

Resolved six previously identified items of concern.

12/2/70 Management meeting Discussed views relating to a sample review of IP-2 preopera-tional procedures and reviewed the proposed guidance for preop-erational testing programs.

12/16/70 & Site-inspection Continued inspections on preop-1/6, 7/71 erational testing and mechanical system cleanup. Reviewed core loading and the available portions of power ascension program.

Obtained resolution for nine previously identified items of concern.

12/7 - Site Reviewed construction log books 10/70 maintained by applicant and contractors. Eighty-five questions were presented to the applicant for resolution.

1/12 & Corporate Management Discussed apparent deficiencies 15/71 in the preoperational testing, power ascension program, and operating procedures.

1/20 - Site Reviewed pipe design analysis 21/71 and pipe support installation.

Date T)rpe of Inspection Scope of Inspection 1/20, 21, Site Continued inspection activity 22, 28, 29 & relating to preoperational 2/3/71 testing, and power ascension pro-grams and operating procedures.

Reviewed programs relating to operator involvement and check-out of operating procedures during hot functional testing.

Inspected final results of-field weld documentation verification program.

2/5/71 Corporate Management Discussed resolution status relating to previously identified deficiencies in the preoperational test program.

2/10-11/71 Site and Engineering Continued inspection efforts in offices the areas of preoperational testing, power ascension pro-grams and operating procedures.

2/17/71 Engineering offices Reviewed the results of evalua-tions relating to pressurizer base plate and discussed the need for an expanded inservice inspection.

2/23, 24/71 Site Continued review of preopera-tional test, pipe support installation and resolution of outstanding items. Discussed reactor coolant pump repairs, circulating water pump testing, and loss of off-site power.

3/5, 6, 8/71 Witnessed portions of the con-tainment overpressure and leak rate tests.

3/10-12/71 Continued inspection efforts, relating to preoperational test-ing, operating procedures and pipe supports. Reviewed electrical jumper and termination control program.

Date Type of Inspection Sco e of Inspection 3/15/71 Site Review damage to polar crane pedestal and witness a portion of the high pressure safety injection testing.

3/16/71 Engineering Office Review status and progress of operating procedure revisions.

3/19, 23, Site Review resolution of construc-25/71 tion log book review questions.

4/6, 7, 8, Site Review preoperational testing, 21, 22/71 power ascension program, pipe support installation, polar crane repairs, organizational coverage and resolution of pre-viously identified items.

5/4, 5, 14, Site Review preoperational testing, 26, 27/71 power ascension programs, operating procedure preparation, implementation of security and emergency plan and resolution of previously identified items.