|
|
Line 3: |
Line 3: |
| | issue date = 06/15/2011 | | | issue date = 06/15/2011 |
| | title = in the Matter of Pacific Gas and Electric Co., (Diablo Canyon, Units 1 & 2) NRC Staff, Submittal of Updated Hearing File for Proceeding and Made Available to the Parties | | | title = in the Matter of Pacific Gas and Electric Co., (Diablo Canyon, Units 1 & 2) NRC Staff, Submittal of Updated Hearing File for Proceeding and Made Available to the Parties |
| | author name = Subin L B | | | author name = Subin L |
| | author affiliation = NRC/OGC | | | author affiliation = NRC/OGC |
| | addressee name = Abramson P B, Karlin A S, Trikouros N G | | | addressee name = Abramson P, Karlin A, Trikouros N |
| | addressee affiliation = NRC/ASLBP | | | addressee affiliation = NRC/ASLBP |
| | docket = 05000275, 05000323 | | | docket = 05000275, 05000323 |
|
---|
Category:Legal-Hearing File
MONTHYEARML15288A0962015-10-15015 October 2015 October 2015 Hearing File Update ML15258A0412015-09-15015 September 2015 Staff September 2015 Hearing File Update ML15229A1572015-08-17017 August 2015 Staff August 2015 Hearing File Update ML15196A3982015-07-15015 July 2015 Notice of July 2015 Hearing File Update ML15166A4042015-06-15015 June 2015 June 2015 Staff Hearing File Update ML15135A1592015-05-15015 May 2015 May 2015 Hearing File Update Notification ML15105A2242015-04-15015 April 2015 April 2015 Hearing File Update ML15075A2542015-03-16016 March 2015 Hearing File Update Letter ML15049A3122015-02-18018 February 2015 Hearing File Update Feb 2015 ML15015A6542015-01-15015 January 2015 Hearing File Update Jan 2015 ML14349A1772014-12-15015 December 2014 Hearing File Update December 2014 ML14135A3572014-05-15015 May 2014 NRC Staff May 2014 Hearing File Update Letter ML14077A0212014-03-18018 March 2014 March 2014 Hearing File Update Letter in the Matter of Pacific Gas and Electric Company, Diablo Canyon, Units 1 and 2, License Renewal ML14049A0092014-02-18018 February 2014 NRC Staff February 2014 Hearing File Update Letter ML14015A0072014-01-15015 January 2014 NRC Staff January 2014 Hearing File Update Letter in the Matter of Diablo Canyon, Units 1 and 2 License Renewal ML13350A0622013-12-16016 December 2013 NRC Staff Notice of Update of Hearing File for Diablo Canyon Nuclear, Units 1 and 2 ML13325A2802013-11-21021 November 2013 NRC Staff November 2013 Schedule Update Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Diablo Canyon, Units 1 and 2 ML13318A0662013-11-14014 November 2013 NRC Staff November 2013 Hearing File Update in the Matter of Diablo Canyon, Units 1 and 2 ML13294A0492013-10-21021 October 2013 NRC Staff October 2013 Hearing File Update Letter in the Matter of Diablo Canyon, Units 1 and 2 ML13260A2932013-09-16016 September 2013 NRC Staff Notice of Update of Hearing File for Diablo Canyon Nuclear, Units 1 and 2 ML13227A1302013-08-15015 August 2013 NRC Staff Projected Schedule for Completion of the Safety and Environmental Evaluations, in the Matter of Pacific Gas and Electric Company (Diablo Canyon Power Plant, Units 1 and 2) ML13227A1232013-08-15015 August 2013 NRC Staff Hearing File Update Letter in the Matter of Pacific Gas and Electric Company (Diablo Canyon Power Plant, Units 1 and 2) ML13192A2272013-07-11011 July 2013 NRC Staff Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Diablo Canyon, Units 1 and 2 ML13192A2002013-07-11011 July 2013 NRC Staff Hearing File Update in the Matter of Diablo Canyon, Units 1 and 2 ML13171A1592013-06-20020 June 2013 Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Diablo Canyon, Units 1 and 2 ML13168A1582013-06-17017 June 2013 Hearing File Update ML13137A2112013-05-17017 May 2013 Projected Schedule for Completion of the Safety and Environmental Evaluations ML13134A3652013-05-14014 May 2013 NRC Staff Notice of Update to Hearing File in the Matter of Diablo Canyon, Units 1 and 2 ML13108A1502013-04-18018 April 2013 NRC Staff Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Diablo Canyon Power Plant, Units 1 and 2 ML13105A2412013-04-15015 April 2013 NRC Staff Hearing File Update Letter ML13080A0852013-03-21021 March 2013 Projected Schedule for Completion of the Safety and Environmental Evaluations ML13073A1372013-03-14014 March 2013 Hearing File Update Letter ML13052A8252013-02-21021 February 2013 Staff Status Update Projected Schedule for Completion of the Safety and Environmental Evaluations ML13045A2532013-02-14014 February 2013 NRC Staff Is Providing Notice That It Has Updated the Hearing File for Section 2.1203 and Section 2.336 Proceeding and Has Made It Available to the Parties ML13017A0762013-01-17017 January 2013 Letter to Board from NRC Staff Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Diablo Canyon, Units 1 and 2 ML13015A1062013-01-15015 January 2013 NRC Staff Notification of Update to Hearing File in the Matter of Diablo Canyon, Units 1 and 2 ML12355A1762012-12-20020 December 2012 Projected Schedule for Completion of the Safety and Environmental Evaluations ML12352A0432012-12-17017 December 2012 NRC Staff Hearing File Update in the Matter of Pacific Gas and Electric Company (Diablo Canyon Power Plant, Units 1 and 2) ML12320A6652012-11-15015 November 2012 NRC Staff Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Diablo Canyon, Units 1 and 2 ML12320A6622012-11-15015 November 2012 NRC Staff Notification of Update to Hearing File in the Matter of Diablo Canyon, Units 1 and 2 ML12292A0912012-10-18018 October 2012 NRC Staff Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Diablo Canyon, Units 1 and 2 ML12289A8712012-10-15015 October 2012 NRC Staff Notification of Update to Hearing File in the Matter of Diablo Canyon, Units 1 and 2 ML12264A3642012-09-20020 September 2012 Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Diablo Canyon, Units 1 and 2 ML12258A0482012-09-14014 September 2012 NRC Staff Notification of Update of Hearing File for Diablo Canyon, Units 1 and 2 ML12229A3202012-08-16016 August 2012 Projected Schedule for Completion of the Safety and Environmental Evaluations ML12228A4062012-08-15015 August 2012 NRC Staff Notice That Its Updated the Hearing File for Diablo Canyon, Units 1 and 2 ML12201A1842012-07-19019 July 2012 Update to Staff Schedule ML12198A4572012-07-16016 July 2012 NRC Staff Notification of Updated Hearing File for Diablo Canyon, Units 1 and 2 ML12177A3532012-06-25025 June 2012 NRC Staff'S Notification to Board of Current Milestone Schedule for the Diablo Canyon Units 1 and 2 License Renewal Safety Evaluation and Environmental Review ML12138A1082012-05-17017 May 2012 Projected Schedule for Completion of the Safety and Environmental Evaluations 2015-09-15
[Table view] |
Text
June 15, 2011 In the Matter of PACIFIC GAS AND ELECTRIC COMPANY (Diablo Canyon Power Plant, Units 1 and 2) Docket Nos. 50-275-LR and 50-323-LR
Dear Administrative Judges:
In accordance with the Board's September 15, 2010, Memorandum, and Section 2.1203(a), the NRC staff is providing notice t hat it has updated the hearing file for this proceeding and has made it available to the parties. For any member of the public that wishes to inspect the hearing file, the Staff has created a separate folder in the agency's Electronic Hearing Docket ("EHD") associated with this proceeding entitled "Diablo Hearing File," and the updated documents, along with an index listing the documents, will be published in that folder.
Respectfully submitted, /signed (electronically) by/
Lloyd B. Subin Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Mail Stop O-15 D21 Washington, DC 20555-0001 (301) 415-1988 Lloyd.Subin@nrc.gov UNITED STATESNUCLEAR REGULATORY COMMISSIONWASHINGTON, DC 20555 - 0001 Administrative Judge
Alex S. Karlin, Chair Atomic Safety and Licensing Board Panel
Mail Stop: T-3F23 Washington, DC 20555-001
Administrative Judge Paul B. Abramson Atomic Safety and Licensing Board Panel
Mail Stop: T-3F23 Washington, DC 20555-0001
Administrative Judge Nicholas G. Trikouros Atomic Safety and Licensing Board Panel
Mail Stop: T-3F23 Washington, DC 20555-0001
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD
In the Matter of ) ) PACIFIC GAS AND ELECTRIC COMPANY ) Docket Nos. 50-275-LR/ 50-323-LR ) (Diablo Canyon Nuclear Power Plant, ) ASLBP No. 10-900-01-LR-BD01 Units 1 and 2) )
CERTIFICATE OF SERVICE
I hereby certify that copies of the foregoing NRC Staff letter dated June 15, 2011, have been served upon the following by the Electronic Information Exchange, this 15th day of June, 2011:
Administrative Judge
Alex S. Karlin, Chair Atomic Safety and Licensing Board Panel
Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
E-mail: ask2@nrc.gov
Administrative Judge Nicholas G. Trikouros Atomic Safety and Licensing Board Panel
Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: ngt@nrc.gov
Administrative Judge
Paul B. Abramson Atomic Safety and Licensing Board Panel Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
E-mail: pba@nrc.gov
Office of Commission Appellate Adjudication U.S. Nuclear Regulatory Commission Mail Stop - O-16G4 Washington, DC 20555-0001
E-mail: ocaamail@nrc.gov
Office of the Secretary Attn: Rulemakings and Adjudications Staff Mail Stop: O-16G4 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: HEARINGDOCKET@nrc.gov
David A. Repka, Esq.
Tyson Smith, Esq.
Carlos Sisco Winston & Strawn LLP
101 California Street
San Francisco, CA 94111-5802
E-mail: drepka@winston.com trsmith@winston.com CSisco@winston.com
Jill ZamEk, Esq. San Luis Obispo Mothers for Peace 1123 Flora Road Arroyo Grande, CA 93420 E-mail: jzk@charter.net
Diane Curran, Esq. Harmon, Curran, Spielberg, and Eisenberg 1726 M Street NW Suite 600 Washington, DC 20036
E-mail: dcurran@harmoncurran.com
Signed (electronically) by
_______________________________ Lloyd B. Subin Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 415-1988 E-mail: Lloyd.Subin@nrc.gov Date of signature: June 15, 2011