NRC Staff Projected Schedule for Completion of the Safety and Environmental Evaluations in the Matter of Diablo Canyon, Units 1 and 2
ML12320A665
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 11/15/2012
From: Subin L
NRC/OGC
To: Abramson P, Karlin A, Nicholas Trikouros
Atomic Safety and Licensing Board Panel
SECY RAS
References
RAS 23759, 50-275-LR, 50-323-LR, ASLBP 10-900-01-LR-BD01
Download: ML12320A665 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 November 15, 2012 Administrative Judge Administrative Judge Alex S. Karlin, Chair Paul B. Abramson Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 Mail Stop: T-3F23 Washington, DC 20555-001 Washington, DC 20555-0001 Administrative Judge Nicholas G. Trikouros Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 Washington, DC 20555-0001 In the Matter of PACIFIC GAS AND ELECTRIC COMPANY (Diablo Canyon Power Plant, Units 1 and 2)

Docket Nos. 50-275-LR and 50-323-LR RE: Projected Schedule for Completion of the Safety and Environmental Evaluations

Dear Administrative Judges:

Pursuant to the Boards Order of August 5, 2010 (Scheduling Initial Scheduling Conference), this letter informs the Board of the NRC Staffs current milestone schedule for the Diablo Canyon Units 1 and 2 license renewal safety evaluation and environmental review. In light of PG&Es status report filed with the Board on November 13, 2012, the Staff expects to issue the DSEIS in January of 2015. Subsequent to issuing the DSEIS, the Staff expects to finalize its safety and environmental reviews, to include issuance of the supplemental environmental impact statement (SEIS) and any necessary supplements to the safety evaluation report by the end of June 2015. This estimate is based on the applicant issuing its final report on the seismic studies by September 2014, as stated in PG&Es Updated Best Estimate Schedule for Seismic Studies attached to PG&Es November 13, 2012 update to the Board.

Sincerely, Signed (electronically) by Lloyd B. Subin Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 415-1988 E-mail: Lloyd.Subin@nrc.gov Date of signature: November 15, 2012

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE COMMISSION In the Matter of )

)

PACIFIC GAS AND ELECTRIC COMPANY ) Docket Nos. 50-275-LR/ 50-323-LR

)

(Diablo Canyon Nuclear Power Plant, ) ASLBP No. 10-900-01-LR-BD01 Units 1 and 2) )

CERTIFICATE OF SERVICE Pursuant to 10 C.F.R § 2.305 (revised), I hereby certify that copies of the foregoing letter regarding the Projected Schedule for Completion of the Safety and Environmental Evaluations, dated November 15, 2012 have been served upon the following by the Electronic Information Exchange, the NRCs E-Filing System, in the above captioned proceeding, this 15th day of November, 2012:

Signed (electronically) by Lloyd B. Subin Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 415-1988 E-mail: Lloyd.Subin@nrc.gov Date of signature: November 15, 2012