| | number = ML090260632 | | | number = ML090260632 |
| | issue date = 03/26/2009 | | | issue date = 03/26/2009 |
| | title = Cover Letter: Final Safety Evaluation for NEI Topical Report (TR) WCAP-16308-NP, Revision 0, Pressurized Water Reactor Owners Group 10 CFR [Title 10 of the Code of Federal Regulations] 50.69 Pilot Program - Categorization Process - Wolf Cre | | | title = Cover Letter: Final Safety Evaluation for NEI Topical Report (TR) WCAP-16308-NP, Revision 0, Pressurized Water Reactor Owners Group 10 CFR (Title 10 of the Code of Federal Regulations) 50.69 Pilot Program - Categorization Process - Wolf Cre |
| | author name = Blount T B | | | author name = Blount T B |
| | author affiliation = NRC/NRR/DPR | | | author affiliation = NRC/NRR/DPR |
Letter Sequence Approval |
---|
|
|
MONTHYEARML0708105062007-04-0303 April 2007 Acceptance for Review of Pressurized Water Reactor Owners Group Topical Report WCAP-16308-NP, 10 CFR 50.69 Pilot Program - Categorization Process - Wolf Creek Generating Station Project stage: Acceptance Review ML0821408632008-09-16016 September 2008 Transmittal Letter for Nuclear Energy Institute Topical Report (TR) WCAP-16308-NP, Revision 0, Pressurized Water Reactor Owners Group 10 CFR 50.69 Pilot Program - Categorization Process - Wolf Creek Generating Station. Project stage: Other ML0829803852008-10-14014 October 2008 Draft Safety Evaluation for Nuclear Energy Institute Topical Report WCAP-16308-NP, Revision 0, Pressurized Water Reactor Owners Group 10 CFR 50369 Pilot Program - Categorization Process - Wolf Creek Generating Station. Project stage: Draft Other ML0902606742009-03-26026 March 2009 Safety Evaluation, Topical Report WCAP-16308-NP, Revision 0, Pressurized Water Reactor Owners Group 10 CFR 50.69 Pilot Program - Categorization Process. Project stage: Approval ML0902606322009-03-26026 March 2009 Cover Letter: Final Safety Evaluation for NEI Topical Report (TR) WCAP-16308-NP, Revision 0, Pressurized Water Reactor Owners Group 10 CFR (Title 10 of the Code of Federal Regulations) 50.69 Pilot Program - Categorization Process - Wolf Cre Project stage: Approval 2008-10-14
[Table View] |
|
---|
Category:Letter
MONTHYEARML24204A2082024-07-22022 July 2024 07-22-24_NRC_NEI Withdrawal of Fee Exemption Request for Wp Selection of Seismic Scenario for EPZ Determination ML24204A2162024-07-22022 July 2024 Withdrawal of Fee Exemption Request for Endorsement of NEI White Paper, Selection of a Seismic Scenario for an EPZ Boundary Determination ML24187A0552024-07-0303 July 2024 Fee Exemption Request for NEI White Paper Selection of Seismic Scenario for EPZ Determination ML24184C1212024-07-0202 July 2024 NEI - Request for NRC Endorsement of NEI 24-05 Revision 0, an Approach for Risk-Informed Performance-Based Emergency Planning ML24173A2712024-06-14014 June 2024 NEI - Proposed Changes to Inspection Procedure (IP) 71130.10, Cybersecurity ML24165A0852024-06-13013 June 2024 NEI White Paper - Impact of Higher Source Term Fractions on EQ Doses ML24165A0862024-06-13013 June 2024 NEI White Paper - Proposed Control Room Dose Acceptance Criteria Supporting RG 1.183 R2 ML24165A0872024-06-12012 June 2024 NEI White Papers Supporting NRC Workshop Discussions Regarding Nuclear Regulatory Commissions (NRC) Potential Changes to Regulatory Guide 1.183 ML24152A3242024-05-31031 May 2024 NEI Concept Paper: Regulation of Rapid High-Volume Deployable Reactors in Remote Locations ML24159A7312024-05-23023 May 2024 05-23-24 Nuclear Energy Institute Letter to the U.S. Nuclear Regulatory Commission Re Industry Comments on Buildings as Items Relied on for Safety ML24135A1982024-04-23023 April 2024 SFAQ No 2022-02, SAE Program Requirements - NEI Withdrawal Letter ML24078A2212024-03-15015 March 2024 3-15-24 NEI Letter Aveil from Juhle on Pur ML24061A0572024-02-29029 February 2024 Endorsement of NEI 08-09, Revision 7, Changes to NEI 08-09 Cyber Security Plan for Nuclear Power Reactors ML24023A0392024-01-22022 January 2024 NEI Comments on the Information Collection Renewal for Domestic Licensing of Special Nuclear Material, Docket Id NRC-2023-0118 ML23355A1972023-12-14014 December 2023 NEI, Comments on NRC Draft Resolution of SFAQ 2022-02, SAE Program Requirements ML23219A1672023-10-25025 October 2023 Response Letter to Fee Exemption Request for Pre-Submittal Activities, Review, and Endorsement of NEI 20-07 ML23270B9002023-09-27027 September 2023 NEI Letter Request for an Extension of Comment Period on Proposed Revision to Standard Review Plan Section 15.0, Introduction - Transient and Accident Analyses, Docket Id NRC 2023 0079 ML23268A0102023-09-22022 September 2023 NEI, Fee Exemption Request for Endorsement, Review and Meeting to Discuss Draft Nuclear Energy Institute Technical Report NEI 23-01, Operator Cold License Training Plan for Advanced Nuclear Reactors ML23241A8612023-08-25025 August 2023 Consolidated Industry Comments to NRC Regulatory Issue Summary 2023-02, Scheduling Information for the Licensing of Accident Tolerant, Increased Enrichment, and Higher Burnup Fuels ML23236A4992023-08-24024 August 2023 Industry Feedback on Region II Fuel Cycle Facility Construction Oversight Workshop Held August 15, 2023, and Suggested Topics for Additional Public Meetings in Fall 2023 ML23256A1622023-08-0101 August 2023 Incoming NEI Letter Dated August 1, 2023 Regarding Increase in Fees 2023-2025 ML23206A0292023-07-24024 July 2023 Incoming Fee Exemption Request for Pre-Submittal Activities, Review, and Endorsement of NEI 20-07 ML23143A1232023-06-22022 June 2023 NRC Fee Waiver Request for Draft NEI 23-01 ML23200A1662023-05-30030 May 2023 NEI Proposed Metrics for a Performance-Based Emergency Preparedness Program ML23116A0732023-05-25025 May 2023 Letter to Hillary Lane in Response to a Request for a Fee Exemption for NEI 23-03 ML23135A7332023-05-0909 May 2023 NEI Comments on NRC Safety Culture Program Effectiveness Review ML23110A6762023-04-18018 April 2023 04-18-23_NRC_NEI 23-03 Review + Endorse ML23110A6752023-04-18018 April 2023 04-18-23_NRC_Fee Waiver for NEI 23-03 ML23110A6782023-04-18018 April 2023 Request for Review and Endorsement of NEI 23-03, Supplemental Guidance for Application of 10 CFR 50.59 to Digital Modifications at Non-Power Production or Utilization Facilities ML24120A2702023-04-0404 April 2023 Melody Rodridguez NEI Comment on Controlled Unclassified Information ML23107A2302023-03-31031 March 2023 NEI Letter, to Andrea Veil, NRC, Regarding Industry Recommendations for a 10 CFR 50.46a/c Combined Rulemaking ML23083B4622023-03-24024 March 2023 Transmittal of NEI 22-05 Revision a, Technology Inclusive Risk Informed Change Evaluation (Tirice) Guidance for the Evaluation of Changes to Facilities Utilizing NEI 18-04 and NEI 21-07 ML23138A1662023-03-24024 March 2023 Transmittal of NEI 22-05 Revision a, Technology Inclusive Risk Informed Change Evaluation (Tirice) Guidance for the Evaluation of Changes to Facilities Utilizing NEI 18-04 and NEI 21-07 ML23060A3272023-03-0101 March 2023 NEI, Wireless Cyber Security Guidance ML23060A2142023-03-0101 March 2023 NEI, Request for NRC Endorsement of NEI White Paper, Enabling a Remote Response by Members of an Emergency Response Organization, Revision 0 ML23023A2752023-01-23023 January 2023 Request for Extension of Comment Period from the Nuclear Energy Institute on PRM-50-124 - Licensing Safety Analysis for Loss-of-Coolant Accidents ML22348A1122023-01-17017 January 2023 Letter to Richard Mogavero Response to Fee Exemption NEI 08-09 Revision 7 ML22353A6082023-01-11011 January 2023 U.S. Nuclear Regulatory Commission Report of the Regulatory Audit of the NEI-Proposed Aging Management Program Revision to Selective Leaching Program (XI.M33) ML22349A1012022-12-12012 December 2022 LTR-22-0343 Ellen Ginsberg, Sr. Vice President, General Counsel and Secretary, Nuclear Energy Institute, Expresses Concerns Related to Issuance of Regulatory Issue Summary 2022-02; Operational Leakage ML22336A0372022-11-16016 November 2022 Fee Exemption Request for NEI 08-09 Revision 7 - Changes to NEI 08-09 Cyber Security Plan for Nuclear Power Reactors ML22321A3152022-11-16016 November 2022 NEI Letter with Comments on Significance Determination Process Timeliness Review ML22298A2262022-10-25025 October 2022 Endorsement of NEI 15-09, Cyber Security Event Notifications, Revision 1, Dated October 2022 ML22298A2302022-10-17017 October 2022 Submittal of NEI 22-03, Draft Revision 0, Nuclear Generation Quality Assurance Program Description ML22207B6512022-07-26026 July 2022 NEI, Full Fee Exemption Request for Industry Guidance Proposal - Weather Related Administrative Controls During Transient Outdoor Dry Cask Operations ML22195A1662022-07-14014 July 2022 NEI, Draft G of NEI 99-01, Development of Emergency Action Levels for Non-Passive Reactors, Revision 7 ML22195A0202022-07-13013 July 2022 07-13-22 NRC Fee Exemption Request for NEI 21-05 Review ML22195A0672022-07-13013 July 2022 Fee Exemption Request for Review and Meeting to Discuss Draft Nuclear Energy Institute Technical Report NEI 21-05, Reporting Guidance for Licensees with Risk-Informed Licensing Bases ML22159A2772022-06-28028 June 2022 Response Letter to Richard Mogavero for Fee Exemption for the Nuclear Regulatory Commission Review Ad Endorsement of NEI 15-09, Revision 1 ML22154A2962022-06-0202 June 2022 LTR from R. Mogavero to M. Sampson Dated Jun 2 2022 Endorsement of NEI 15-09 Cyber Security Event Notifications Rev 1 Dated May 2022 ML22153A2782022-06-0202 June 2022 Nie, Fee Exemption Request for Endorsement of NEI 15-09, Cyber Security Event Notifications, Revision 1, Dated May 2022 2024-07-03
[Table view] |
Text
March 26, 2009
Mr. Biff Bradley, Director Risk Assessment Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708
SUBJECT:
FINAL SAFETY EVALUATION FOR NUCLEAR ENERGY INSTITUTE (NEI) TOPICAL REPORT (TR) WCAP-16308-NP, REVISION 0, "PRESSURIZED WATER REACTOR OWNERS GROUP [(PWROG)] 10 CFR [TITLE 10 OF THE CODE OF FEDERAL REGULATIONS] 50.69 PILOT PROGRAM -
CATEGORIZATION PROCESS - WOLF CREEK GENERATING STATION" (TAC NO. MD4229)
Dear Mr. Bradley:
By letter dated September 25, 2006, as supplemented by letters dated October 22, 2007, and July 15, 2008, the NEI submitted Topical Report (TR) WCAP-16308-NP, Revision 0, "Pressurized Water Reactor Owners Group 10 CFR 50.69 Pilot Program - Categorization Process- Wolf Creek Generating Station," to the U.S. Nuclear Regulatory Commission (NRC) staff for review on behalf of the PWROG. By letter dated September 16, 2008, an NRC draft safety evaluation (SE) regarding our approval of TR WCAP-16308-NP was provided for your review and comments. By letter dated October 14, 2008, NEI commented on the draft SE. The NRC staff's disposition of NEI
=s comments on the draft SE are discussed in Attachment 2 to the final SE enclosed with this letter.
The NRC staff has found that TR WCAP-16308-NP is acceptable for referencing in licensing applications to the extent specified and under the limitations delineated in the TR and in the enclosed final SE. The final SE defines the basis for our acceptance of the TR.
The categorization process described in TR WCAP-16308-NP and evaluated in the enclosed final SE supports license amendment applications by licensees voluntarily choosing to implement 10 CFR 50.69, "Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors." As described in the statement of considerations for 10 CFR 50.69, the treatment processes for structures, systems, and components (SSC) are not subject to NRC review and approval as part of the license amendment process, but rather will be subject to sample inspections at nuclear power plants implementing 10 CFR 50.69.
Therefore, the SE does not approve nor endorse any specific treatment process. The NRC recognizes the need for an effective, stable and predictable inspection process regarding treatment requirements and looks forward to a continuing dialogue with NEI to ensure these goals are achieved.
Our acceptance applies only to material provided in the subject TR. We do not intend to repeat our review of the acceptable material described in the TR. When the TR appears as a reference
in license applications, our review will ensure that the materi al presented applies to the specific plant involved. License amendment requests that deviate from this TR will be s ubject to a plant-specific review in accordance with applicable review standards. In accordance with the guidance provided on the NRC website, we request that NEI publish an accepted version of this TR within three months of receipt of this letter. The accepted version shall incorporate this letter and the enclosed final SE after the title page. In addition, the accepted version should be modified to incorporate the changes identified in Table 1 of the enclosed SE. Also, they must contain historical review information, including NRC requests for additional information and your responses. The accepted versions shall include an "-A" (designating accepted) following the TR identification symbol.
If future changes to the NRC's regulatory requirements affect the acceptability of this TR, NEI and/or licensees referencing it will be expected to revise the TR appropriately, or justify its continued applicability for subsequent refe rencing. Sincerely,
/RA/
Thomas B. Blount, Deputy Director Division of Policy and Rulemaking Office of Nuclear Reactor Regulation
Project No. 689
Enclosure:
Final SE
cc w/encl: See next page
ML090280265 (Package); ML090260632 (Cover Letter); ML082140868 (Draft SE); ML090260674 (Final SE) *No major changes to SE input. NRR-043 OFFICE PSPB/PM PSPB/LA DCI/CPTB* DCI/CPNB* DE/EMCB DRA/APLA* PSPB/BC DPR/DD NAME TMensah DBaxley JMcHale TChan KManoly MRubin SRosenberg TBlount DATE 02 /09 /09 02/05 /09 07/08/08 07/08/08 08/22/08 07/22/08 03 /12 /09 03/26/09 Nuclear Energy Institute Project No. 689
cc:
Mr. Anthony Pietrangelo, Vice President Regulatory Affairs Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 arp@nei.org
Mr. Jack Roe, Director Security Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 jwr@nei.org
Mr. Charles B. Brinkman Washington Operations ABB-Combustion Engineering, Inc.
12300 Twinbrook Parkway, Suite 330 Rockville, MD 20852 brinkmcb@westinghouse.com
Mr. James Gresham, Manager Regulatory Compliance and Plant Licensing Westinghouse Electric Company P.O. Box 355 Pittsburgh, PA 15230-0355 greshaja@westinghouse.com
Ms. Barbara Lewis Assistant Editor Platts, Principal Editorial Office 1200 G St., N.W., Suite 1100 Washington, DC 20005 Barbara_lewis@platts.com
Mr. Alexander Marion, Acting Vice President for Nuclear Operations Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 am@nei.org
Mr. John Butler, Director Operations Support Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 jcb@nei.org
Mike Melton, Senior Project Manager 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 man@nei.org
Dennis Buschbaum PWROG Chairman Comanche Peak Steam Electric Station 6322 North Farm to Marked Rd 56 Mail Code E15 Glen Rose, TX 76043 Dennis.Buschbaum@luminant.com
Mr. James H. Riley, Director Engineering Nuclear Energy Institute 1776 I Street, NW Washington, DC 20006-3708 jhr@nei.org