{{#Wiki_filter:Inspection / Activity Plan Page 1 of 2 03/03/2010 07:10:38 Report 22 03/01/2010
-06/30/2011 Unit Number Planned Dates Start          End Inspection Activity Title No. of Staff on Site Vogtle OL EXAM-INITIAL EXAM WEEK 4
PSB1-RP-RP OCCUPATIONAL BASELINE WEEK1 2
EB3ISI-UNIT 2 INSERVICE INSPECTION 2
EB3TI172-TI-172 RCS DM BUTT WELDS 2
EB3SGISI-UNIT 2 SGISI 1
PSB1-RP-RP OCCUPATIONAL BASELINE WEEK 2 2
PSB1EP-EMERGENCY PREPAREDNESS EXERCISE 3
EB1-CDBI-COMPONENT DESIGN BASES INSPECTION 7
FP-TFPI 6 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 4
Inspection / Activity Plan Page 2 of 2 03/03/2010 07:10:38 Report 22 03/01/2010
-06/30/2011 Unit Number Planned Dates Start          End Inspection Activity Title No. of Staff on Site Vogtle OL EXAM-INIITIAL EXAM PREP 2
OL EXAM-INITIAL EXAM - WEEK 1 3
OL EXAM-INITIAL EXAM - WEEK 2 3
EB3ISI-UNIT 1 INSERVICE INSPECTION 1
PSB1-RP-RP RADIOLOGICAL HAZARD ASSESSMENT 1
PSB1EP-EMERGENCY PREPAREDNESS INSPECTION 1
MODS-MODIFICATION/50.59 INSPECTION 3
EB3HS-HEAT SINK 1}}

Revision as of 15:59, 19 September 2018

Vogtle, Inspection/Activity Plan, 03/01/2010 - 06/30/2010, Enclosure - Report 22
ML100620892
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 03/03/2010
From:
Division Reactor Projects II
To:
Southern Nuclear Operating Co
Shared Package
ML100620889 List:
References
IR-10-001
Download: ML100620892 (2)


Text

Inspection / Activity Plan Page 1 of 2 03/03/2010 07:10:38 Report 22 03/01/2010

-06/30/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Vogtle OL EXAM-INITIAL EXAM WEEK 4

PSB1-RP-RP OCCUPATIONAL BASELINE WEEK1 2

EB3ISI-UNIT 2 INSERVICE INSPECTION 2

EB3TI172-TI-172 RCS DM BUTT WELDS 2

EB3SGISI-UNIT 2 SGISI 1

PSB1-RP-RP OCCUPATIONAL BASELINE WEEK 2 2

PSB1EP-EMERGENCY PREPAREDNESS EXERCISE 3

EB1-CDBI-COMPONENT DESIGN BASES INSPECTION 7

FP-TFPI 6 PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 4

Inspection / Activity Plan Page 2 of 2 03/03/2010 07:10:38 Report 22 03/01/2010

-06/30/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Vogtle OL EXAM-INIITIAL EXAM PREP 2

OL EXAM-INITIAL EXAM - WEEK 1 3

OL EXAM-INITIAL EXAM - WEEK 2 3

EB3ISI-UNIT 1 INSERVICE INSPECTION 1

PSB1-RP-RP RADIOLOGICAL HAZARD ASSESSMENT 1

PSB1EP-EMERGENCY PREPAREDNESS INSPECTION 1

MODS-MODIFICATION/50.59 INSPECTION 3

EB3HS-HEAT SINK 1