|
|
Line 19: |
Line 19: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:}} | | {{#Wiki_filter:. |
| | SOUTHERN NUCLEAR OPERATING COMPANY, INC. |
| | GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MEAG POWER SPVM, LLC MEAG POWER SPVJ, LLC MEAG POWER SPVP, LLC CITY OF DALTON, GEORGIA VOGTLE ELECTRIC GENERATING PLANT, UNIT 4 DOCKET NO. 52-026 AMENDMENT TO FACILITY COMBINED LICENSE Amendment No. 185 License No. NPF-92 |
| | : 1. The Nuclear Regulatory Commission (the Commission) has found that: |
| | A. The application for amendment by Southern Nuclear Operating Company (SNC), |
| | dated June 30, 2020, as supplemented by letters dated August 11, 2020, November 20, 2020, and April 27, 2021, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's regulations set forth in 10 CFR Chapter I; B. The facility will be constructed and will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations, and all applicable requirements have been satisfied. |
| | : 2. Accordingly, by Amendment No. 185, facility Combined License No. NPF-92 is hereby amended to authorize revision to the Emergency Plan as set forth in SNCs application dated June 30, 2020, as supplemented by letters dated August 11, 2020, November 20, 2020, and April 27, 2021. |
| | : 3. This license amendment is effective as of the date of its issuance and shall be implemented within 180 days of the date of issuance. SNC shall submit the changes authorized by this amendment with the next update of the Updated Final Safety Analysis Report in accordance with 10 CFR 50.71(e). |
| | FOR THE NUCLEAR REGULATORY COMMISSION: |
| | /RA/ |
| | Michael F. King, Deputy Director Office of Nuclear Reactor Regulation Date of Issuance: September 17, 2021 |
| | |
| | ==Attachment:== |
| | |
| | Page 7 of the facility Combined License}} |
Latest revision as of 18:04, 18 January 2022
Letter Sequence Other |
---|
EPID:L-2020-LLA-0151, Southern Nuclear Operating Co., Inc. - License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions (Approved, Closed) |
|
MONTHYEARML20192A1402020-06-30030 June 2020 Southern Nuclear Operating Co., Inc. - License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions Project stage: Request ML20202A0172020-07-23023 July 2020 Non-Acceptance of Requested Licensing Action License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Pos Project stage: Acceptance Review ML20224A4642020-08-11011 August 2020 Southern Nuclear Operating Co, Inc - Supplement to License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions Project stage: Supplement ML20217L4312020-08-13013 August 2020 Edwin I Hatch, Units 1 and 2; and Vogtle Electric Plant, Units 1, 2, 3, and 4 - Meeting Slides a License Amendment Request for the Emergency Plan (EPID Nos L-2020-LLA-0150 and L-2020-LLA-051 Project stage: Meeting ML20217L3692020-08-13013 August 2020 Summary of Meeting Joseph M. Farley Nuclear Plant, Units 1 and 2; Edwin I. Hatch, Units 1 and 2; and Vogtle Electric Generating Plant, Units 1, 2, 3, and 4 a LAR for the Emergency Plan (EPID Nos. L-2020-LLA0150 and L-2020-LLA-015 Project stage: Meeting ML20245E2842020-09-0101 September 2020 NRR E-mail Capture - Acceptance Review - SNC Fleet EP LAR (L-2020-LLA-0150 and L-220-LLA-151) Project stage: Acceptance Review ML20293A0752020-10-14014 October 2020 NRR E-mail Capture - RAIs for SNC Fleet EP LAR (L-2020-LLA-0150 and L-2020-LLA-0151) Project stage: RAI PMNS20201237, Notice of Meeting with Southern Nuclear Operating Company, Inc. to Discuss Fleet Emergency Plan License Amendment Request2020-10-21021 October 2020 Notice of Meeting with Southern Nuclear Operating Company, Inc. to Discuss Fleet Emergency Plan License Amendment Request Project stage: Meeting ML20318A0742020-10-21021 October 2020, 12 November 2020, 16 November 2020 MTS - Meeting Summary - SNC Fleet EP LAR - November 12 2020 Project stage: Request ML20318A1032020-11-12012 November 2020 SNC ERO Staffing LAR RAI Responses Project stage: Other ML20318A0752020-11-16016 November 2020 Summary of November 12, 2020, Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a License Amendment Request for the Emergency Plan Project stage: Meeting NL-20-1273, Response to NRC Requests for Information License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for2020-11-20020 November 2020 Response to NRC Requests for Information License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Project stage: Response to RAI ML20342A0182021-02-24024 February 2021 Audit Plan for Revision to Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions Project stage: Other ND-21-0277, ITAAC Closure Notification on Completion of ITAAC 2.5.06.02 (Index Number 574)2021-04-26026 April 2021 ITAAC Closure Notification on Completion of ITAAC 2.5.06.02 (Index Number 574) Project stage: Request ML21117A2882021-04-27027 April 2021 ITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number 2.5.06.02 (Index No. 574) for Vogtle Unit 3 Combined License (VOG3) Project stage: Request ML21060B4322021-05-19019 May 2021 Audit Report for Revision to Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions Project stage: Other ML21217A0282021-09-17017 September 2021 Safety Evaluation for Vogtle Electric Generating Plant Units 3 and 4 Regarding Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions Project stage: Approval ML21217A0262021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment No. 187 Project stage: Other ML21217A0272021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment No. 185 Project stage: Other ML21217A0252021-09-17017 September 2021 Amendment No. 185 - Vogtle Electric Generating Plant Unit 4 Project stage: Other ML21217A0242021-09-17017 September 2021 Amendment No. 187 - Vogtle Electric Generating Plant Unit 3 Project stage: Other ML21217A0232021-09-17017 September 2021 Cover Letter for Vogtle Electric Generating Plant Units 3 and 4 Amendment Nos. 187 and 185 Regarding Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions Project stage: Other 2020-08-11
[Table View] |
|
---|
Category:License-Combined License (COL) (New/Renewal/Amendments) DKT 52
MONTHYEARML23243B0542023-12-19019 December 2023 VEGP Unit 4 Amendment No. 193 - Enclosure 2 ML23243A9682023-12-19019 December 2023 VEGP Unit 3 Amendment No. 197 - Enclosure 1 ML23310A2922023-12-0707 December 2023 Issuance of Amendment for Exception to Regulatory Guide 1.163, LAR 23 007 ML23339A1812023-12-0707 December 2023 Correction Letter Regarding License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 ML23289A1632023-11-28028 November 2023 Letter and Amendment 195 and 192 LAR-23-006R1 TS 3.1.9 More Restrictive Action ML23159A0972023-07-31031 July 2023 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 23-001) ML23072A2722023-05-0101 May 2023 Enclosure 1 - LAR 22-005 Amendment No. 191 Vogtle Unit 3 ML23072A2732023-05-0101 May 2023 Enclosure 2 - LAR 22-005 Amendment No. 188 Vogtle, Unit 4 ML23072A2762023-05-0101 May 2023 Attachment to Enclosure 2 - VEGP U4 Amendment 188 LAR-22-005 ML23037A0892023-02-0808 February 2023 Amendment - Vogtle Unit 3 Amendment No. 190, Tech Spec Exceptions for In-Containment Refueling Water Storage Tank Operability Prior to Initial Criticality (Exigent Circumstances) ML20290A2822022-08-0303 August 2022 Finding That Acceptance Criteria in the Combined License Are Met (10 CFR 103g - Finding) ML21237A2342021-10-15015 October 2021 Amendment Unit 3 - Vogtle Electric Generating Plant LAR 21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2352021-10-15015 October 2021 Attachment Unit 3 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2372021-10-15015 October 2021 Attachment Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2362021-10-15015 October 2021 Amendment Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21217A0242021-09-17017 September 2021 Amendment No. 187 - Vogtle Electric Generating Plant Unit 3 ML21217A0252021-09-17017 September 2021 Amendment No. 185 - Vogtle Electric Generating Plant Unit 4 ML21217A0272021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment No. 185 ML21217A0262021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment No. 187 ML20314A0132020-12-0707 December 2020 License Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 20-005) ML20314A0142020-12-0707 December 2020 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment 184 (LAR-20-005) ML20314A0102020-12-0707 December 2020 License Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 20-005) ML20314A0112020-12-0707 December 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 186 (LAR-20-005) ML20247J4612020-10-14014 October 2020 Amendment 183 - Vogtle Electric Generating Plant Unit 4 (LAR 20-004) ML20247J4592020-10-14014 October 2020 Amendment 185 - Vogtle Electric Generating Plant Unit 3 (LAR 20-004) ML20237F4922020-09-24024 September 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 184 (LAR-20-003) ML20237F4942020-09-24024 September 2020 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment 182 (LAR-20-003) ML20237F4932020-09-24024 September 2020 Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 20-003) ML20237F4912020-09-24024 September 2020 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 20-003) ML20196L6772020-08-11011 August 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 183 for LAR-20-002 ML20196L6782020-08-11011 August 2020 Amendment 181 - Vogtle Electric Generating Plant Unit 4 for LAR 20-002 ML20196L6792020-08-11011 August 2020 Attachment - Vogtle Electric Generating Plant Unit 4 for Amendment 181 for LAR-20-002 ML20132A0762020-08-0404 August 2020 Attachment - Vogtle Electric Generating Plant Unit 3 (LAR 20-001) ML20059N7792020-05-12012 May 2020 Amendment 181 - LAR-19-010: Auxiliary Building Room Heatup ML20059N7822020-05-12012 May 2020 Amendment 180 - LAR-19-010: Auxiliary Building Room Heatup ML20106F1632020-05-12012 May 2020 Attachment to Amendment 180 - LAR-19-010: Auxiliary Building Room Heatup ML20106F1622020-05-12012 May 2020 Attachment to Amendment 181 - LAR-19-010: Auxiliary Building Room Heatup ML20120A0072020-04-30030 April 2020 Attachment for Amendment 178 Cyber Security Plan Changes (LAR-19-020) ML20106F1592020-04-30030 April 2020 Attachment for Amendment 179 Cyber Security Plan Changes (LAR-19-020) ML20057E1172020-04-30030 April 2020 Amendment 178 - Issuance of Amendments for Cyber Security Plan Changes (LAR-19-020) ML20057E1062020-04-30030 April 2020 Amendment 179 - Issuance of Amendments for Cyber Security Plan Changes (LAR-19-020) ML20064E6682020-03-23023 March 2020 Enclosure 4: Supplemental Attachment to License Amendment No. 148 for COL No. NPF-91 ML20064E6802020-03-23023 March 2020 Enclosure 5: Supplemental Attachment to License Amendment No. 147 for COL No. NPF-92 ML20064E5722020-03-23023 March 2020 Supplemental Attachment to License Amendment No. 36 for COL No. NPF-92 ML20064E6122020-03-23023 March 2020 Enclosure 2: Supplemental Attachment to License Amendment No. 125 for COL No. NPF-91 ML20064E6282020-03-23023 March 2020 Enclosure 3: Supplemental Attachment to License Amendment No. 124 for COL No. NPF-92 ML20013G6882020-02-0303 February 2020 Amendment - Vogtle Electric Generating Plant Unit 4 ML19350C7002020-01-28028 January 2020 Attachment - Vogtle Electric Generating Plant Unit 3 (LAR 19-015).d ML19350C7142020-01-28028 January 2020 Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 19-015) ML19350C6862020-01-28028 January 2020 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 19-015) 2023-07-31
[Table view] |
Text
.
SOUTHERN NUCLEAR OPERATING COMPANY, INC.
GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MEAG POWER SPVM, LLC MEAG POWER SPVJ, LLC MEAG POWER SPVP, LLC CITY OF DALTON, GEORGIA VOGTLE ELECTRIC GENERATING PLANT, UNIT 4 DOCKET NO.52-026 AMENDMENT TO FACILITY COMBINED LICENSE Amendment No. 185 License No. NPF-92
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Southern Nuclear Operating Company (SNC),
dated June 30, 2020, as supplemented by letters dated August 11, 2020, November 20, 2020, and April 27, 2021, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's regulations set forth in 10 CFR Chapter I; B. The facility will be constructed and will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations, and all applicable requirements have been satisfied.
- 2. Accordingly, by Amendment No. 185, facility Combined License No. NPF-92 is hereby amended to authorize revision to the Emergency Plan as set forth in SNCs application dated June 30, 2020, as supplemented by letters dated August 11, 2020, November 20, 2020, and April 27, 2021.
- 3. This license amendment is effective as of the date of its issuance and shall be implemented within 180 days of the date of issuance. SNC shall submit the changes authorized by this amendment with the next update of the Updated Final Safety Analysis Report in accordance with 10 CFR 50.71(e).
FOR THE NUCLEAR REGULATORY COMMISSION:
/RA/
Michael F. King, Deputy Director Office of Nuclear Reactor Regulation Date of Issuance: September 17, 2021
Attachment:
Page 7 of the facility Combined License