IR 05000280/2017403: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 21: | Line 21: | ||
[[Issue date::August 2, 2017]] | [[Issue date::August 2, 2017]] | ||
Mr. | Mr. Daniel Senior Vice President and Chief Nuclear Officer Virginia Electric and Power Company Dominion Nuclear Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 | ||
SUBJECT: | SUBJECT: SURRY POWER STATION - U.S. NUCLEAR REGULATORY COMMISSION SECURITY INSPECTION REPORT 05000280/2017403 AND 05000281/2017403 | ||
==Dear Mr. Stoddard:== | ==Dear Mr. Stoddard:== | ||
On July 20, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Surry Power Station, Units 1 and 2 and discussed the results of this inspection with Mr. F. Mladen and other members of your staff. The results of this inspection are documented in the enclosed report. | On July 20, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Surry Power Station, Units 1 and 2 and discussed the results of this inspection with Mr. F. Mladen and other members of your staff. The results of this inspection are documented in the enclosed report. | ||
No NRC-identified or self-revealing findings were identified during the inspection. However, the inspector documented one licensee-identified violation, which was determined to be of very low security significance in this report. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy. If you contest the violation or the significance of the NCV, you should provide a response within 30 days of the date of this inspection report with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response and the NRC Resident Inspector at Surry Power Station.This letter will be made available for public inspection and copying at https://www.nrc.gov/reading-rm/adams.html. and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding." | No NRC-identified or self-revealing findings were identified during the inspection. However, the inspector documented one licensee-identified violation, which was determined to be of very low security significance in this report. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy. If you contest the violation or the significance of the NCV, you should provide a response within 30 days of the date of this inspection report with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response and the NRC Resident Inspector at Surry Power Station. This letter will be made available for public inspection and copying at https://www.nrc.gov/reading-rm/adams.html. and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding." However, the enclosed report contains Security-Related Information, so the enclosed report will not be made publicly available in accordance with 10 CFR 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response "Security-Related Information-Withhold from public disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii). | ||
Sincerely,/RA/ | Sincerely,/RA/ | ||
Jon Wallo, Acting Chief Plant Support Branch 2 | Jon Wallo, Acting Chief Plant Support Branch 2 Division of Reactor Safety Docket Nos. 50-280 and 50-281 License Nos. DPR-32 and DPR-37 | ||
===Enclosure:=== | ===Enclosure:=== |
Revision as of 18:20, 18 February 2018
ML17215A946 | |
Person / Time | |
---|---|
Site: | Surry ![]() |
Issue date: | 08/02/2017 |
From: | Wallo J H NRC/RGN-II/DRS/PSB2 |
To: | Stoddard D G Dominion Nuclear, Virginia Electric & Power Co (VEPCO) |
References | |
IR 2017403 | |
Download: ML17215A946 (4) | |
Text
August 2, 2017
Mr. Daniel Senior Vice President and Chief Nuclear Officer Virginia Electric and Power Company Dominion Nuclear Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT: SURRY POWER STATION - U.S. NUCLEAR REGULATORY COMMISSION SECURITY INSPECTION REPORT 05000280/2017403 AND 05000281/2017403
Dear Mr. Stoddard:
On July 20, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Surry Power Station, Units 1 and 2 and discussed the results of this inspection with Mr. F. Mladen and other members of your staff. The results of this inspection are documented in the enclosed report.
No NRC-identified or self-revealing findings were identified during the inspection. However, the inspector documented one licensee-identified violation, which was determined to be of very low security significance in this report. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy. If you contest the violation or the significance of the NCV, you should provide a response within 30 days of the date of this inspection report with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response and the NRC Resident Inspector at Surry Power Station. This letter will be made available for public inspection and copying at https://www.nrc.gov/reading-rm/adams.html. and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding." However, the enclosed report contains Security-Related Information, so the enclosed report will not be made publicly available in accordance with 10 CFR 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response "Security-Related Information-Withhold from public disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
Sincerely,/RA/
Jon Wallo, Acting Chief Plant Support Branch 2 Division of Reactor Safety Docket Nos. 50-280 and 50-281 License Nos. DPR-32 and DPR-37
Enclosure:
NRC IR 05000280/2017403 and 05000281/2017403,
w/Attachment:
Supplemental Information (OUO)