{{#Wiki_filter:Appendix C                           Job Performance Measure                       Form ES-C-1 Worksheet   SA.1JPM Page 1 Facility: Columbia Generating Station Task No:
{{#Wiki_filter:Appendix C                   Job Performance Measure               Form ES-C-1 Worksheet SA.1JPM Facility: Columbia Generating Station       Task No:
Task Title: Determine Jet Pump Operability Job Performance Measure No: SA.1JPM K/A  
Task Title: Determine Jet Pump             Job Performance Measure No: SA.1JPM Operability K/A  


==Reference:==
==Reference:==
2.1.7 3.7/4.4 Examinee: NRC Examiner:
2.1.7 3.7/4.4 Examinee:                                   NRC Examiner:
Facility Evaluator:
Facility Evaluator:                         Date: 02/22/01 Method of testing:
Date: 02/22/01 Method of testing:
Admin - Simulate Page 1
Admin - Simulate Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.1JPM Page 2 JPM SETUP INFORMATION Initial Conditions:   


The plant is operating at 100% power. The Jet Pump Operability surveillance is due.
Appendix C                Job Performance Measure                    Form ES-C-1 Worksheet SA.1JPM JPM SETUP INFORMATION Initial Conditions: The plant is operating at 100% power. The Jet Pump Operability surveillance is due.
Task Standard:
Task Standard:     Perform a manual calculation for Jet Pump Operability per OSP-RRC-D701.
Perform a manual calculation for Jet Pump Operability per OSP-RRC-D701.
Required Materials: N/A General  
Required Materials:
N/A General  


==References:==
==References:==
OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1 Initiating Cue:    The plant is operating at 100% power. The Jet Pump Operability surveillance is due.
: 1. Determine if Jet Pumps JP1 through JP10 are operable.
: 2. Perform OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1, using panel indications for these jet pumps.
: 3. A Histogram is not available.
Time Critical Task: NO Validation Time:    15 min.
Simulator ICs:      14 in freeze Malfunctions/Remote N/A Triggers:
Overrides:          N/A Special Setup      N/A Instructions:
Page 2


OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1 Initiating Cue:
Appendix C               Job Performance Measure                   Form ES-C-1 Worksheet SA.1JPM PERFORMANCE INFORMATION START TIME:
The plant is operating at 100% power. The Jet Pump Operability surveillance is due.
Critical Step: YES Performance Step: 1 Using the supplied OSP-RRC-D701 rev 5, step 7.2.3.a and 7.2.3.b and Attachment 10.1; perform the jet pump operability for JP1 through JP10.
1.Determine if Jet Pumps JP1 through JP10 are operable.
CUE:
2.Perform OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1, using panel indications for these jet pumps.
Standard:           1. Jet pump panel readings are recorded within 10% of panel indications - See attached copy of 10.1.
3.A Histogram is not available.
: 2. All Jet pumps are determined to be operable - The YES box is checked for step 7.2.3.b.
Time Critical Task:
NO Validation Time:
15 min.Simulator ICs:
14 in freeze Malfunctions/Remote Triggers: N/A Overrides:
N/A Special Setup Instructions:
N/A Appendix C                           Job Performance Measure                       Form ES-C-1 Worksheet   SA.1JPM Page 3 PERFORMANCE INFORMATION START TIME:
Critical Step: YES Performance Step:  1 Using the supplied OSP-RRC-D701 rev 5, step 7.2.3.a and 7.2.3.b and Attachment 10.1; perform the jet pump operability for JP1 through JP10.
CUE: Standard: 1.Jet pump panel readings are recorded within 10% of panel indications - See attached copy of 10.1.
2.All Jet pumps are determined to be operable - The YES box is checked for step 7.2.3.b.
Comment:
Comment:
SAT / UNSAT THE EXAMINEE SHOULD ANNOUNCE THE TERMINATION POINT OF THE JPM AT THIS POINT.
SAT / UNSAT THE EXAMINEE SHOULD ANNOUNCE THE TERMINATION POINT OF THE JPM AT THIS POINT.
JPM TERMINATION TIME:
JPM TERMINATION TIME:
JPM START TIME:         -
JPM START TIME:     -
 
JPM COMPLETION TIME:
JPM COMPLETION
Page 3
 
TIME:
Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.1JPM Page 4 VERIFICATION OF COMPLETION JPM Number:
SA.1JPM Examinee's Name:
Examiner's Name:


Appendix C              Job Performance Measure Form ES-C-1 Worksheet SA.1JPM VERIFICATION OF COMPLETION JPM Number:        SA.1JPM Examinees Name:
Examiners Name:
Date Performed:
Date Performed:
Facility Evaluator:
Facility Evaluator:
Number of Attempts:
Number of Attempts:
Time to Complete:
Time to Complete:
Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.1JPM Page 5 JPM INFORMATION CARD HAND THE STUDENT INFORMATION CARD TO THE EXAMINEE READ TO THE EXAMINEE:
Page 4
I will explain the initial conditions, which steps to simulate or discuss, and provide


initiation cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Appendix C                        Job Performance Measure                  Form ES-C-1 Worksheet SA.1JPM JPM INFORMATION CARD HAND THE STUDENT INFORMATION CARD TO THE EXAMINEE READ TO THE EXAMINEE:
Task Standard:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiation cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Perform a manual calculation for Jet Pump Operability per OSP-RRC-D701.
Task Standard:             Perform a manual calculation for Jet Pump Operability per OSP-RRC-D701.
Required Materials:
Required Materials:         N/A Safety Equipment:           N/A General  
N/A Safety Equipment:
N/A General  


==References:==
==References:==
 
OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1 Time Critical Task:         NO Initial Conditions:         The plant is operating at 100% power. The Jet Pump Operability surveillance is due.
OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1 Time Critical Task:
NO Initial Conditions:  
 
The plant is operating at 100% power. The Jet Pump Operability surveillance is due.
INITIATING CUE The plant is operating at 100% power. The Jet Pump Operability surveillance is due.
INITIATING CUE The plant is operating at 100% power. The Jet Pump Operability surveillance is due.
1.Determine if Jet Pumps JP1 through JP10 are operable.
: 1. Determine if Jet Pumps JP1 through JP10 are operable.
2.Perform OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1, using panel indications for these jet pumps.
: 2. Perform OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1, using panel indications for these jet pumps.
3.A Histogram is not available.
: 3. A Histogram is not available.
INFORMATION BELOW THIS LINE NOT SHARED WITH EXAMINEE Task Number:
INFORMATION BELOW THIS LINE NOT SHARED WITH EXAMINEE Task Number:                                     Validation Time: 15 min.
Validation Time: 15 min.
NUREG 1123  
NUREG 1123  


==Reference:==
==Reference:==
2.1.7 3.7/4.4 Time Critical: NO Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.1JPM Page 6 Location: Simulator Performance Method:  Perform - Admin Prepared/Revised by:  S Hutchison Revision Date:  1/11/01 Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.1JPM Page 7 STUDENT INFORMATION Initial Conditions:   
2.1.7 3.7/4.4               Time Critical: NO Page 5


The plant is operating at 100% power. The Jet Pump Operability surveillance is due.
Appendix C                  Job Performance Measure              Form ES-C-1 Worksheet SA.1JPM Location: Simulator                        Performance Method: Perform - Admin Prepared/Revised by: S Hutchison          Revision Date: 1/11/01 Page 6
 
Appendix C                  Job Performance Measure          Form ES-C-1 Worksheet SA.1JPM STUDENT INFORMATION Initial Conditions:    The plant is operating at 100% power. The Jet Pump Operability surveillance is due.
INITIATING CUE The plant is operating at 100% power. The Jet Pump Operability surveillance is due.
INITIATING CUE The plant is operating at 100% power. The Jet Pump Operability surveillance is due.
1.Determine if Jet Pumps JP1 through JP10 are operable.
: 1. Determine if Jet Pumps JP1 through JP10 are operable.
2.Perform OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1, using panel indications for these jet pumps.
: 2. Perform OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1, using panel indications for these jet pumps.
3.A Histogram is not available.
: 3. A Histogram is not available.
Appendix C                           Job Performance Measure                       Form ES-C-1 Worksheet   SA.2JPM Page 1 Facility: Columbia Generating Station Task No:
Page 7
Task Title: Interrupt EWDs Job Performance Measure No: SA.2JM K/A  
 
Appendix C                   Job Performance Measure               Form ES-C-1 Worksheet SA.2JPM Facility: Columbia Generating Station     Task No:
Task Title: Interrupt EWDs                 Job Performance Measure No: SA.2JM K/A  


==Reference:==
==Reference:==
2.1.24 2.8/3.1 Examinee: NRC Examiner:
2.1.24 2.8/3.1 Examinee:                                 NRC Examiner:
Facility Evaluator:
Facility Evaluator:                       Date: 02/22/01 Method of testing:
Date: 02/22/01 Method of testing:
Admin - Simulate Page 1
Admin - Simulate Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.2JPM Page 2 JPM SETUP INFORMATION Initial Conditions:   


The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability.
Appendix C                Job Performance Measure                      Form ES-C-1 Worksheet SA.2JPM JPM SETUP INFORMATION Initial Conditions: The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability.
Task Standard:
Task Standard:     Indications for the start of ROA-FN-1A are explained correctly using EWD 80E001.
Indications for the start of ROA-FN-1A are explained correctly using EWD 80E001.
Required Materials: N/A General  
Required Materials:
N/A General  


==References:==
==References:==
 
EWD 80E001 Initiating Cue:     The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability. The following scenario occurs:
EWD 80E001 Initiating Cue:
: 1. The breaker for the fan has been racked in and the EO has notified the control room he is ready for a start.
The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability. The following scenario occurs: 1.The breaker for the fan has been racked in and the EO has notified the control room he is ready for a start.
: 2. The CRO notices that the green STOP/OFF indication at the control switch is off. Thinking the light bulb is burned out; the CRO places the control switch for ROA-FN-1A to start.
2.The CRO notices that the green STOP/OFF indication at the control switch is off. Thinking the light bulb is burned out; the CRO places the control switch for ROA-FN-1A to start.
: 3. The EO reports the breaker closes by sound and the manual indicators but there is no closed indication on the lights on the breaker door.
3.The EO reports the breaker closes by sound and the manual indicators but there is no closed indication on the lights on the breaker door.
: 4. The CRO also notes there is no closed/running indication in the control room.
4.The CRO also notes there is no closed/running indication in the control room.
: 5. The CRO places the control switch in the TRIP position.
5.The CRO places the control switch in the TRIP position.
Nothing happens, the fan continues to run.
Nothing happens, the fan continues to run.
6.All light bulbs have been verified as good.
: 6. All light bulbs have been verified as good.
Using EWD 80E001, explain why there are no indicating lights for ROA-FN-1A and why it cannot be tripped.
Using EWD 80E001, explain why there are no indicating lights for ROA-FN-1A and why it cannot be tripped.
Time Critical Task:
Time Critical Task: NO Validation Time:   10 min.
NO Validation Time:
Simulator ICs:     N/A Malfunctions/Remote N/A Triggers:
10 min.Simulator ICs:
Overrides:         N/A Special Setup       N/A Page 2
N/A Malfunctions/Remote Triggers: N/A Overrides:
 
N/A Special Setup N/A Appendix C                           Job Performance Measure                       Form ES-C-1 Worksheet   SA.2JPM Page 3 Instructions:
Appendix C               Job Performance Measure                     Form ES-C-1 Worksheet SA.2JPM Instructions:
PERFORMANCE INFORMATION START TIME:
PERFORMANCE INFORMATION START TIME:
Critical Step: YES Performance Step:  1 Demonstrate on EWD 80E001 the reason for the indications in the Initiating Cue.
Critical Step: YES Performance Step: 1 Demonstrate on EWD 80E001 the reason for the indications in the Initiating Cue.
Standard: Using EWD 80E001, demonstrate the following :
Standard:           Using EWD 80E001, demonstrate the following :
1.For the fan to start, the close fuses, FO3-1, FO3-2, F10-1, and F10-2 have to be installed and operable.
: 1. For the fan to start, the close fuses, FO3-1, FO3-2, F10-1, and F10-2 have to be installed and operable.
2.All light indications for the fan are in the trip circuit.
: 2. All light indications for the fan are in the trip circuit.
3.For the fan to trip, the trip fuses FO4-1 and FO4-2 have to be installed and operable.
: 3. For the fan to trip, the trip fuses FO4-1 and FO4-2 have to be installed and operable.
4.Since the fan started the close fuses were good.
: 4. Since the fan started the close fuses were good.
5.Since there was no breaker indication locally or in the control room and the fan would not trip with the control switch the trip fuses FO4-1 and FO4-2 (either or both) are blown or not installed correctly.
: 5. Since there was no breaker indication locally or in the control room and the fan would not trip with the control switch the trip fuses FO4-1 and FO4-2 (either or both) are blown or not installed correctly.
FOR FULL CREDIT
FOR FULL CREDIT - It must be indicated that bad/blown trip fuses prevent both light indication and the trip of the fan.
- It must be indicated that bad/blown trip fuses prevent both light indication and the trip of the fan.
Comment:
Comment:
SAT / UNSAT THE EXAMINEE SHOULD ANNOUNCE THE TERMINATION POINT OF THE JPM AT THIS POINT.
SAT / UNSAT THE EXAMINEE SHOULD ANNOUNCE THE TERMINATION POINT OF THE JPM AT THIS POINT.
JPM TERMINATION TIME: JPM START TIME:         -
JPM TERMINATION TIME:
JPM START TIME:     -
JPM COMPLETION TIME:
JPM COMPLETION TIME:
Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.2JPM Page 4 VERIFICATION OF COMPLETION JPM Number:
Page 3
SA.2JPM Examinee's Name:
Examiner's Name:


Appendix C              Job Performance Measure Form ES-C-1 Worksheet SA.2JPM VERIFICATION OF COMPLETION JPM Number:        SA.2JPM Examinees Name:
Examiners Name:
Date Performed:
Date Performed:
Facility Evaluator:
Facility Evaluator:
Number of Attempts:
Number of Attempts:
Time to Complete:
Time to Complete:
Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.2JPM Page 5 JPM INFORMATION CARD HAND THE STUDENT INFORMATION CARD TO THE EXAMINEE READ TO THE EXAMINEE:
Page 4
I will explain the initial conditions, which steps to simulate or discuss, and provide


initiation cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Appendix C                        Job Performance Measure                  Form ES-C-1 Worksheet SA.2JPM JPM INFORMATION CARD HAND THE STUDENT INFORMATION CARD TO THE EXAMINEE READ TO THE EXAMINEE:
Task Standard:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiation cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Indications for the start of ROA-FN-1A are explained correctly using EWD 80E001.
Task Standard:             Indications for the start of ROA-FN-1A are explained correctly using EWD 80E001.
Required Materials:
Required Materials:         N/A Safety Equipment:           N/A General  
N/A Safety Equipment:
N/A General  


==References:==
==References:==
 
EWD 80E001 Time Critical Task:         N/A Initial Conditions:         The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability.
EWD 80E001 Time Critical Task:
N/A Initial Conditions:  
 
The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability.
INITIATING CUE The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability. The following scenario occurs:
INITIATING CUE The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability. The following scenario occurs:
1.The breaker for the fan has been racked in and the EO has notified the control room he is ready for a start.
: 1. The breaker for the fan has been racked in and the EO has notified the control room he is ready for a start.
2.The CRO notices that the green STOP/OFF indication at the control switch is off.
: 2. The CRO notices that the green STOP/OFF indication at the control switch is off.
Thinking the light bulb is burned out; the CRO places the control switch for ROA-
Thinking the light bulb is burned out; the CRO places the control switch for ROA-FN-1A to start.
: 3. The EO reports the breaker closes by sound and the manual indicators but there is no closed indication on the lights on the breaker door.
: 4. The CRO also notes there is no closed/running indication in the control room.
: 5. The CRO places the control switch in the TRIP position. Nothing happens, the fan continues to run.
: 6. All light bulbs have been verified as good.
Page 5


FN-1A to start.
Appendix C                 Job Performance Measure                 Form ES-C-1 Worksheet SA.2JPM Using EWD 80E001, explain why there are no indicating lights for ROA-FN-1A and why it cannot be tripped.
3.The EO reports the breaker closes by sound and the manual indicators but there is no closed indication on the lights on the breaker door.
INFORMATION BELOW THIS LINE NOT SHARED WITH EXAMINEE Task Number:                               Validation Time: 10 min.
4.The CRO also notes there is no closed/running indication in the control room.
5.The CRO places the control switch in the TRIP position. Nothing happens, the fan continues to run.
6.All light bulbs have been verified as good.
Appendix C                           Job Performance Measure                       Form ES-C-1 Worksheet   SA.2JPM Page 6 Using EWD 80E001, explain why there are no indicating lights for ROA-FN-1A and why it cannot be tripped.
INFORMATION BELOW THIS LINE NOT SHARED WITH EXAMINEE Task Number:
Validation Time: 10 min.
NUREG 1123  
NUREG 1123  


==Reference:==
==Reference:==
2.1.24 2.8/3.1 Time Critical: NO Location: Simulator Performance Method: Simulate - Admin Prepared/Revised by: S Hutchison Revision Date: 1/11/01 Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.2JPM Page 7 STUDENT INFORMATION Initial Conditions:   
2.1.24 2.8/3.1       Time Critical: NO Location: Simulator                       Performance Method: Simulate - Admin Prepared/Revised by: S Hutchison           Revision Date: 1/11/01 Page 6


The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability.
Appendix C                  Job Performance Measure              Form ES-C-1 Worksheet SA.2JPM STUDENT INFORMATION Initial Conditions:    The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability.
INITIATING CUE The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability. The following scenario occurs:
INITIATING CUE The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability. The following scenario occurs:
1.The breaker for the fan has been racked in and the EO has notified the control room he is ready for a start.
: 1. The breaker for the fan has been racked in and the EO has notified the control room he is ready for a start.
2.The CRO notices that the green STOP/OFF indication at the control switch is off. Thinking the light bulb is burned out; the CRO places the
: 2. The CRO notices that the green STOP/OFF indication at the control switch is off. Thinking the light bulb is burned out; the CRO places the control switch for ROA-FN-1A to start.
 
: 3. The EO reports the breaker closes by sound and the manual indicators but there is no closed indication on the lights on the breaker door.
control switch for ROA-FN-1A to start.
: 4. The CRO also notes there is no closed/running indication in the control room.
3.The EO reports the breaker closes by sound and the manual indicators but there is no closed indication on the lights on the breaker door.
: 5. The CRO places the control switch in the TRIP position. Nothing happens, the fan continues to run.
4.The CRO also notes there is no closed/running indication in the control room. 5.The CRO places the control switch in the TRIP position. Nothing happens, the fan continues to run.
: 6. All light bulbs have been verified as good.
6.All light bulbs have been verified as good.
Using EWD 80E001, explain why there are no indicating lights for ROA-FN-1A and why it cannot be tripped.
Using EWD 80E001, explain why there are no indicating lights for ROA-FN-1A and why it cannot be tripped.
Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.3JPM Page 1                                               
Page 7


Sa3jpmr0 Facility: Columbia Generating Station Task No: SRO-0026 Task Title: Complete Planned Special Exposure Job Performance Measure No: SA.3JPM K/A  
Appendix C                Job Performance Measure                Form ES-C-1 Worksheet SA.3JPM Facility: Columbia Generating Station       Task No: SRO-0026 Task Title: Complete Planned Special       Job Performance Measure No: SA.3JPM Exposure K/A  


==Reference:==
==Reference:==
2.3.4 2.5/3.1 Examinee: NRC Examiner:
2.3.4 2.5/3.1 Examinee:                                   NRC Examiner:
Facility Evaluator:
Facility Evaluator:                         Date: 02/22/01 Method of testing:
Date: 02/22/01 Method of testing:
Admin - Simulate Page 1 Sa3jpmr0
Admin - Simulate Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.3JPM Page 2                                               


Sa3jpmr0 JPM SETUP INFORMATION Initial Conditions:  
Appendix C                Job Performance Measure                    Form ES-C-1 Worksheet SA.3JPM JPM SETUP INFORMATION Initial Conditions: The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is expected to receive a total of 350 mrem to perform the task. An Increased Exposure Request is required for the task.
 
Task Standard:     The paperwork for the Increased Exposure Request is completed in accordance with GEN-RPP-07.
The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is expected to receive a total of
Required Materials: N/A General  
 
350 mrem to perform the task. An Increased Exposure Request is required for the task.
Task Standard:
The paperwork for the Increased Exposure Request is completed in accordance with GEN-RPP-07.
Required Materials:
N/A General  


==References:==
==References:==
GEN-RPP-07.
GEN-RPP-07.
Initiating Cue:
Initiating Cue:     The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is 30 years old and has been employed by Energy Northwest for 5 years. He is expected to receive a total of 350 mrem to perform the task. The following information applies to the operator.
The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is 30 years old and has been employed by Energy Northwest for 5 years. He is expected to receive a total of 350 mrem to perform the task. The following
: 1. John Q Operator
: 2. SS # - 555-55-5555
: 3. DOB - 01/01/71
: 4. 1.8 rem TEDE year to date.
: 5. 6.875 rem TEDE lifetime.
: 6. All dose is from Energy Northwest exposure.
As the operators supervisor, complete the Increased Exposure Request per GEN-RPP-07.
Time Critical Task: NO Validation Time:    10 min.
Simulator ICs:      N/A Malfunctions/Remote N/A Triggers:
Overrides:          N/A Special Setup      N/A Instructions:
Page 2 Sa3jpmr0


information applies to the operator.
Appendix C             Job Performance Measure                   Form ES-C-1 Worksheet SA.3JPM PERFORMANCE INFORMATION START TIME:
1.John Q Operator 2.SS # - 555-55-5555 3.DOB - 01/01/71 4.1.8 rem TEDE year to date.
Critical Step: YES Performance Step: 1 Complete the first 3 sections of the Increased Exposure Request as the Supervisor of the designated operator.
5.6.875 rem TEDE lifetime.
Standard:           Increased Exposure Request form is completed in accordance with GEN-RPP-07.
6.All dose is from Energy Northwest exposure.
Grading Standard - compare candidates completed form with the attached form. Passing Criteria = each required section must match the attached form. The reason and justification must match the intent.
As the operator's supervisor, complete the Increased Exposure Request per GEN-RPP-07.
Time Critical Task:
NO Validation Time:
10 min.Simulator ICs:
N/A Malfunctions/Remote Triggers: N/A Overrides:
N/A Special Setup Instructions:
N/A Appendix C                           Job Performance Measure                       Form ES-C-1 Worksheet   SA.3JPM Page 3                                               
 
Sa3jpmr0 PERFORMANCE INFORMATION START TIME:
Critical Step: YES Performance Step:  1 Complete the first 3 sections of the Increased Exposure Request as the Supervisor of the designated operator.
Standard: Increased Exposure Request form is completed in accordance with GEN-RPP-07.
Grading Standard - compare candidates completed form with the attached form. Passing Criteria = each required section must match the attached form. The reason and justification
 
must match the intent.
Comment:
Comment:
SAT / UNSAT THE EXAMINEE SHOULD ANNOUNCE THE TERMINATION POINT OF THE JPM AT THIS POINT.
SAT / UNSAT THE EXAMINEE SHOULD ANNOUNCE THE TERMINATION POINT OF THE JPM AT THIS POINT.
JPM TERMINATION TIME: JPM START TIME:         -
JPM TERMINATION TIME:
JPM START TIME:     -
JPM COMPLETION TIME:
JPM COMPLETION TIME:
Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.3JPM Page 4                                               
Page 3 Sa3jpmr0
 
Sa3jpmr0 VERIFICATION OF COMPLETION JPM Number:
SA.3JPM Examinee's Name:
Examiner's Name:


Appendix C              Job Performance Measure Form ES-C-1 Worksheet SA.3JPM VERIFICATION OF COMPLETION JPM Number:        SA.3JPM Examinees Name:
Examiners Name:
Date Performed:
Date Performed:
Facility Evaluator:
Facility Evaluator:
Number of Attempts:
Number of Attempts:
Time to Complete:
Time to Complete:
Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.3JPM Page 5                                               
Page 4 Sa3jpmr0


Sa3jpmr0 JPM INFORMATION CARD HAND THE STUDENT INFORMATION CARD TO THE EXAMINEE READ TO THE EXAMINEE:
Appendix C                      Job Performance Measure                    Form ES-C-1 Worksheet SA.3JPM JPM INFORMATION CARD HAND THE STUDENT INFORMATION CARD TO THE EXAMINEE READ TO THE EXAMINEE:
I will explain the initial conditions, which steps to simulate or discuss, and provide
I will explain the initial conditions, which steps to simulate or discuss, and provide initiation cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
 
Task Standard:             The paperwork for the Increased Exposure Request is completed in accordance with GEN-RPP-07.
initiation cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Required Materials:         N/A Safety Equipment:           N/A General  
Task Standard:
The paperwork for the Increased Exposure Request is completed in accordance with GEN-RPP-07.
Required Materials:
N/A Safety Equipment:
N/A General  


==References:==
==References:==
GEN-RPP-07.
GEN-RPP-07.
Time Critical Task:
Time Critical Task:         NO Initial Conditions:         The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is expected to receive a total of 350 mrem to perform the task. An Increased Exposure Request is required for the task.
NO Initial Conditions:  
 
The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is expected to receive a total of 350 mrem to perform the task. An Increased Exposure Request is required for the task.
INITIATING CUE The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is 30 years old and has been employed by Energy Northwest for 5 years. He is expected to receive a total of 350 mrem to perform the task. The following information applies to the operator.
INITIATING CUE The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is 30 years old and has been employed by Energy Northwest for 5 years. He is expected to receive a total of 350 mrem to perform the task. The following information applies to the operator.
1.John Q Operator 2.SS # - 555-55-5555 3.DOB - 01/01/71 4.1.8 rem TEDE year to date.
: 1. John Q Operator
5.6.875 rem TEDE lifetime.
: 2. SS # - 555-55-5555
Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.3JPM Page 6                                               
: 3. DOB - 01/01/71
: 4. 1.8 rem TEDE year to date.
: 5. 6.875 rem TEDE lifetime.
Page 5 Sa3jpmr0


Sa3jpmr0 6.All dose is from Energy Northwest exposure.
Appendix C                  Job Performance Measure                Form ES-C-1 Worksheet SA.3JPM
As the operator's supervisor, complete the Increased Exposure Request per GEN-RPP-
: 6. All dose is from Energy Northwest exposure.
: 07. INFORMATION BELOW THIS LINE NOT SHARED WITH EXAMINEE Task Number: SRO-0026 Validation Time: 10 min.
As the operators supervisor, complete the Increased Exposure Request per GEN-RPP-07.
INFORMATION BELOW THIS LINE NOT SHARED WITH EXAMINEE Task Number: SRO-0026                         Validation Time: 10 min.
NUREG 1123  
NUREG 1123  


==Reference:==
==Reference:==
2.3.4 2.5/3.1 Time Critical: NO Location: Admin Performance Method: Simulate Prepared/Revised by: S Hutchison Revision Date: 1/10/01 Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.3JPM Page 7                                               
2.3.4 2.5/3.1           Time Critical: NO Location: Admin                               Performance Method: Simulate Prepared/Revised by: S Hutchison             Revision Date: 1/10/01 Page 6 Sa3jpmr0


Sa3jpmr0 STUDENT INFORMATION Initial Conditions:     
Appendix C                Job Performance Measure              Form ES-C-1 Worksheet SA.3JPM STUDENT INFORMATION Initial Conditions:    The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is expected to receive a total of 350 mrem to perform the task. An Increased Exposure Request is required for the task.
INITIATING CUE The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is 30 years old and has been employed by Energy Northwest for 5 years. He is expected to receive a total of 350 mrem to perform the task. The following information applies to the operator.
: 1. John Q Operator
: 2. SS # - 555-55-5555
: 3. DOB - 01/01/71
: 4. 1.8 rem TEDE year to date.
: 5. 6.875 rem TEDE lifetime.
: 6. All dose is from Energy Northwest exposure.
As the operators supervisor, complete the Increased Exposure Request per GEN-RPP-07.
Page 7 Sa3jpmr0


The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot
Appendix C                   Job Performance Measure               Form ES-C-1 Worksheet SA.4JPM Facility: Columbia Generating Station       Task No: SRO-0233 Task Title: Classify the Event             Job Performance Measure No: SA.4JPM K/A  
 
spot from a trap in the drywell. The operator selected is expected to receive a total of 350 mrem to perform the task. An Increased Exposure Request is required for the task.
INITIATING CUE The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is 30 years old and has been employed by Energy Northwest for 5 years. He is expected to receive a total of 350 mrem to perform the task. The following information applies to the operator.
1.John Q Operator 2.SS # - 555-55-5555 3.DOB - 01/01/71 4.1.8 rem TEDE year to date.
5.6.875 rem TEDE lifetime.
6.All dose is from Energy Northwest exposure.
As the operator's supervisor, complete the Increased Exposure Request per GEN-RPP-07.
Appendix C                           Job Performance Measure                       Form ES-C-1 Worksheet   SA.4JPM Page 1 Facility: Columbia Generating Station Task No: SRO-0233 Task Title: Classify the Event Job Performance Measure No: SA.4JPM K/A  


==Reference:==
==Reference:==
2.4.41 2.3/4.1 Examinee: NRC Examiner:
2.4.41 2.3/4.1 Examinee:                                   NRC Examiner:
Facility Evaluator:
Facility Evaluator:                         Date: 02/22/01 Method of testing:
Date: 02/22/01 Method of testing:
Admin - Simulate Page 1
Admin - Simulate Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.4JPM Page 2 JPM SETUP INFORMATION Initial Conditions:   


The plant is in Mode 3.
Appendix C                Job Performance Measure                    Form ES-C-1 Worksheet SA.4JPM JPM SETUP INFORMATION Initial Conditions: The plant is in Mode 3.
Task Standard:
Task Standard:     Classify the event correctly per PPM 13.1.1 Classifying the Emergency.
Classify the event correctly per PPM 13.1.1 Classifying the Emergency.
Required Materials: N/A General  
Required Materials:
N/A General  


==References:==
==References:==
PPM 13.1.1 rev 28, page 13 Initiating Cue:    The plant is in Mode 3. The following conditions exist:
: 1. Reactor Pressure is 687 psig and down slow
: 2. Reactor Level is -62 inches and stable
: 3. Drywell temperature is 251°F and up slow
: 4. Drywell pressure is 8 psig and up slow
: 5. Drywell unidentified leakage on EDR-FRS-623 went offscale high for a short period of time and returned to 0.
: 6. Wind direction 300°
: 7. Wind speed 8 mph
: 8. Stability Classification E
: 9. No precipitation Based on these conditions, determine the Emergency Classification, and complete a CNF form.
Time Critical Task: NO Validation Time:    15 min Simulator ICs:      N/A Malfunctions/Remote N/A Triggers:
Overrides:          N/A Special Setup      N/A Instructions:
Page 2


PPM 13.1.1 rev 28, page 13 Initiating Cue:
Appendix C             Job Performance Measure                 Form ES-C-1 Worksheet SA.4JPM PERFORMANCE INFORMATION START TIME:
The plant is in Mode 3. The following conditions exist:
Critical Step: Yes Performance Step: 1 Review plant data and complete CNF form.
1.Reactor Pressure is 687 psig and down slow 2.Reactor Level is -62 inches and stable 3.Drywell temperature is 251°F  and up slow 4.Drywell pressure is 8 psig and up slow 5.Drywell unidentified leakage on EDR-FRS-623 went offscale high for a short period of time and returned to 0.
CUE:
6.Wind direction 300° 7.Wind speed 8 mph 8.Stability Classification E 9.No precipitation Based on these conditions, determine the Emergency Classification, and complete a CNF form.
Standard:           1. Review data and complete CNF form as attached.
Time Critical Task:
: 2. EAL is ALERT based on either 2.1.a.1 or 3.1.a.1 of PPM 13.1.1.
NO Validation Time:
Comment:
15 min Simulator ICs:
N/A Malfunctions/Remote Triggers: N/A Overrides:
N/A Special Setup Instructions:
N/A Appendix C                           Job Performance Measure                       Form ES-C-1 Worksheet   SA.4JPM Page 3 PERFORMANCE INFORMATION START TIME:
Critical Step: Yes Performance Step:  1 Review plant data and complete CNF form.
CUE: Standard: 1.Review data and complete CNF form as attached.
2.EAL is ALERT based on either 2.1.a.1 or 3.1.a.1 of PPM 13.1.1.Comment:
SAT / UNSAT THE EXAMINEE SHOULD ANNOUNCE THE TERMINATION POINT OF THE JPM AT THIS POINT.
SAT / UNSAT THE EXAMINEE SHOULD ANNOUNCE THE TERMINATION POINT OF THE JPM AT THIS POINT.
JPM TERMINATION TIME: JPM START TIME:         -
JPM TERMINATION TIME:
JPM START TIME:     -
JPM COMPLETION TIME:
JPM COMPLETION TIME:
Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.4JPM Page 4 VERIFICATION OF COMPLETION JPM Number:
Page 3
SA.4JPM Examinee's Name:
Examiner's Name:


Appendix C              Job Performance Measure Form ES-C-1 Worksheet SA.4JPM VERIFICATION OF COMPLETION JPM Number:        SA.4JPM Examinees Name:
Examiners Name:
Date Performed:
Date Performed:
Facility Evaluator:
Facility Evaluator:
Number of Attempts:
Number of Attempts:
Time to Complete:
Time to Complete:
Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.4JPM Page 5 JPM INFORMATION CARD HAND THE STUDENT INFORMATION CARD TO THE EXAMINEE READ TO THE EXAMINEE:
Page 4
I will explain the initial conditions, which steps to simulate or discuss, and provide


initiation cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Appendix C                      Job Performance Measure                  Form ES-C-1 Worksheet SA.4JPM JPM INFORMATION CARD HAND THE STUDENT INFORMATION CARD TO THE EXAMINEE READ TO THE EXAMINEE:
Task Standard:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiation cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Classify the event correctly per PPM 13.1.1 Classifying the Emergency.
Task Standard:             Classify the event correctly per PPM 13.1.1 Classifying the Emergency.
Required Materials:
Required Materials:         N/A Safety Equipment:           N/A General  
N/A Safety Equipment:
N/A General  


==References:==
==References:==
PPM 13.1.1 rev 28, page 13 Time Critical Task:        NO Initial Conditions:        The plant is in Mode 3.
INITIATING CUE The plant is in Mode 3. The following conditions exist:
: 1. Reactor Pressure is 687 psig and down slow
: 2. Reactor Level is -62 inches and stable
: 3. Drywell temperature is 251°F and up slow
: 4. Drywell pressure is 8 psig and up slow
: 5. Drywell unidentified leakage on EDR-FRS-623 went offscale high for a short period of time and returned to 0.
: 6. Wind direction 300°
: 7. Wind speed 8 mph
: 8. Stability Classification E
: 9. No precipitation Page 5


PPM 13.1.1 rev 28, page 13 Time Critical Task:
Appendix C                    Job Performance Measure                  Form ES-C-1 Worksheet SA.4JPM Based on these conditions, determine the Emergency Classification, and complete a CNF form.
NO Initial Conditions:   
Page 6


The plant is in Mode 3.
Appendix C                 Job Performance Measure             Form ES-C-1 Worksheet SA.4JPM INFORMATION BELOW THIS LINE NOT SHARED WITH EXAMINEE Task Number: SRO-0233                     Validation Time: 15 NUREG 1123  
INITIATING CUE The plant is in Mode 3. The following conditions exist:
1.Reactor Pressure is 687 psig and down slow 2.Reactor Level is -62 inches and stable 3.Drywell temperature is 251°F  and up slow 4.Drywell pressure is 8 psig and up slow 5.Drywell unidentified leakage on EDR-FRS-623 went offscale high for a short period of time and returned to 0.
6.Wind direction 300° 7.Wind speed 8 mph 8.Stability Classification E 9.No precipitation Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.4JPM Page 6 Based on these conditions, determine the Emergency Classification, and complete a CNF form.
Appendix C                           Job Performance Measure                       Form ES-C-1 Worksheet   SA.4JPM Page 7 INFORMATION BELOW THIS LINE NOT SHARED WITH EXAMINEE Task Number: SRO-0233 Validation Time: 15 NUREG 1123  


==Reference:==
==Reference:==
2.4.41 2.3/4.1 Time Critical: NO Location: Admin Performance Method: Admin Prepared/Revised by: S Hutchison Revision Date: 1/10/01 Appendix C                            Job Performance Measure                      Form ES-C-1 Worksheet  SA.4JPM Page 8 STUDENT INFORMATION Initial Conditions:   
2.4.41 2.3/4.1       Time Critical: NO Location: Admin                           Performance Method: Admin Prepared/Revised by: S Hutchison           Revision Date: 1/10/01 Page 7


The plant is in Mode 3.
Appendix C                  Job Performance Measure        Form ES-C-1 Worksheet SA.4JPM STUDENT INFORMATION Initial Conditions:    The plant is in Mode 3.
INITIATING CUE The plant is in Mode 3. The following conditions exist:
INITIATING CUE The plant is in Mode 3. The following conditions exist:
1.Reactor Pressure is 687 psig and down slow 2.Reactor Level is -62 inches and stable 3.Drywell temperature is 251°F and up slow 4.Drywell pressure is 8 psig and up slow 5.Drywell unidentified leakage on EDR-FRS-623 went offscale high for a short period of time and returned to 0.
: 1. Reactor Pressure is 687 psig and down slow
6.Wind direction 300° 7.Wind speed 8 mph 8.Stability Classification E 9.No precipitation Based on these conditions, determine the Emergency Classification, and complete a CNF form.
: 2. Reactor Level is -62 inches and stable
ADMINISTRATIVE TOPICS SECTION A2 COLUMBIA GENERATING STATION   SRO                                     FEB. 22, 2001 page 1 Question No.
: 3. Drywell temperature is 251°F and up slow
SA.1-1 The plant is operating at 99% power. IN-4 has been lost due to equipment failure.
: 4. Drywell pressure is 8 psig and up slow
: 5. Drywell unidentified leakage on EDR-FRS-623 went offscale high for a short period of time and returned to 0.
: 6. Wind direction 300°
: 7. Wind speed 8 mph
: 8. Stability Classification E
: 9. No precipitation Based on these conditions, determine the Emergency Classification, and complete a CNF form.
Page 8
 
ADMINISTRATIVE TOPICS SECTION A2 COLUMBIA GENERATING STATION SRO                                   FEB. 22, 2001 Question No. The plant is operating at 99% power. IN-4 has been lost due to equipment SA.1-1        failure.
Which plant department is the most affected by a loss of IN-4?
Which plant department is the most affected by a loss of IN-4?
CLOSED REFERENCE ANSWER: Security Response: SAT / UNSAT LO 5897 2.1.27 2.8/2.9 82-RSY-1200-T5 Question No.
CLOSED REFERENCE ANSWER:         Security
SA.1-2 The plant is shutdown in Mode 4. Maintenance is underway in the Primary Access Point. A laborer calls the control room and notifies you that an unknown/unbadged person has wondered into the Yakima Building (GSB) asking for directions to FFTF.
 
===Response===
SAT / UNSAT LO 5897       2.1.27 2.8/2.9                           82-RSY-1200-T5 Question No. The plant is shutdown in Mode 4. Maintenance is underway in the Primary SA.1-2        Access Point. A laborer calls the control room and notifies you that an unknown/unbadged person has wondered into the Yakima Building (GSB) asking for directions to FFTF.
What are the required NRC notifications for this event?
What are the required NRC notifications for this event?
OPEN REFERENCE ANSWER: 1 Hour notification to the NRC.
OPEN REFERENCE ANSWER:         1 Hour notification to the NRC.
Response: SAT / UNSAT LO 6011 2.1.13 2.1/2.9 PPM 1.10.1 rev 19, page 9 ADMINISTRATIVE TOPICS SECTION A2 COLUMBIA GENERATING STATION   SRO                                     FEB. 22, 2001 page 2 Question No.
 
SA.1-2 The plant is shutdown in Mode 4. Maintenance is underway in the Primary Access Point. A laborer calls the control room and notifies you that an unknown/unbadged person has wondered into the Yakima Building (GSB) asking for directions to FFTF.
===Response===
SAT / UNSAT LO 6011                   2.1.13 2.1/2.9                   PPM 1.10.1 rev 19, page 9 page 1
 
ADMINISTRATIVE TOPICS SECTION A2 COLUMBIA GENERATING STATION SRO                                   FEB. 22, 2001 Question No. The plant is shutdown in Mode 4. Maintenance is underway in the Primary SA.1-2        Access Point. A laborer calls the control room and notifies you that an unknown/unbadged person has wondered into the Yakima Building (GSB) asking for directions to FFTF.
What are the required NRC notifications for this event?
What are the required NRC notifications for this event?
OPEN REFERENCE ADMINISTRATIVE TOPICS SECTION A2 COLUMBIA GENERATING STATION   SRO                                     FEB. 22, 2001 page 3 Question No.
OPEN REFERENCE page 2
SA.1-1 The plant is operating at 99% power. IN-4 has been lost due to equipment failure.
 
ADMINISTRATIVE TOPICS SECTION A2 COLUMBIA GENERATING STATION SRO                                   FEB. 22, 2001 Question No. The plant is operating at 99% power. IN-4 has been lost due to equipment SA.1-1        failure.
Which plant department is the most affected by a loss of IN-4?
Which plant department is the most affected by a loss of IN-4?
CLOSED REFERENCE}}
CLOSED REFERENCE page 3}}

Revision as of 05:57, 24 November 2019

CGS-Retake Exam-2/2001-Final Operating Exam
ML010680329
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 02/22/2001
From:
NRC Region 4
To:
References
-RFPFR
Download: ML010680329 (32)


Text

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.1JPM Facility: Columbia Generating Station Task No:

Task Title: Determine Jet Pump Job Performance Measure No: SA.1JPM Operability K/A

Reference:

2.1.7 3.7/4.4 Examinee: NRC Examiner:

Facility Evaluator: Date: 02/22/01 Method of testing:

Admin - Simulate Page 1

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.1JPM JPM SETUP INFORMATION Initial Conditions: The plant is operating at 100% power. The Jet Pump Operability surveillance is due.

Task Standard: Perform a manual calculation for Jet Pump Operability per OSP-RRC-D701.

Required Materials: N/A General

References:

OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1 Initiating Cue: The plant is operating at 100% power. The Jet Pump Operability surveillance is due.

1. Determine if Jet Pumps JP1 through JP10 are operable.
2. Perform OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1, using panel indications for these jet pumps.
3. A Histogram is not available.

Time Critical Task: NO Validation Time: 15 min.

Simulator ICs: 14 in freeze Malfunctions/Remote N/A Triggers:

Overrides: N/A Special Setup N/A Instructions:

Page 2

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.1JPM PERFORMANCE INFORMATION START TIME:

Critical Step: YES Performance Step: 1 Using the supplied OSP-RRC-D701 rev 5, step 7.2.3.a and 7.2.3.b and Attachment 10.1; perform the jet pump operability for JP1 through JP10.

CUE:

Standard: 1. Jet pump panel readings are recorded within 10% of panel indications - See attached copy of 10.1.

2. All Jet pumps are determined to be operable - The YES box is checked for step 7.2.3.b.

Comment:

SAT / UNSAT THE EXAMINEE SHOULD ANNOUNCE THE TERMINATION POINT OF THE JPM AT THIS POINT.

JPM TERMINATION TIME:

JPM START TIME: -

JPM COMPLETION TIME:

Page 3

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.1JPM VERIFICATION OF COMPLETION JPM Number: SA.1JPM Examinees Name:

Examiners Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Page 4

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.1JPM JPM INFORMATION CARD HAND THE STUDENT INFORMATION CARD TO THE EXAMINEE READ TO THE EXAMINEE:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiation cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

Task Standard: Perform a manual calculation for Jet Pump Operability per OSP-RRC-D701.

Required Materials: N/A Safety Equipment: N/A General

References:

OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1 Time Critical Task: NO Initial Conditions: The plant is operating at 100% power. The Jet Pump Operability surveillance is due.

INITIATING CUE The plant is operating at 100% power. The Jet Pump Operability surveillance is due.

1. Determine if Jet Pumps JP1 through JP10 are operable.
2. Perform OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1, using panel indications for these jet pumps.
3. A Histogram is not available.

INFORMATION BELOW THIS LINE NOT SHARED WITH EXAMINEE Task Number: Validation Time: 15 min.

NUREG 1123

Reference:

2.1.7 3.7/4.4 Time Critical: NO Page 5

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.1JPM Location: Simulator Performance Method: Perform - Admin Prepared/Revised by: S Hutchison Revision Date: 1/11/01 Page 6

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.1JPM STUDENT INFORMATION Initial Conditions: The plant is operating at 100% power. The Jet Pump Operability surveillance is due.

INITIATING CUE The plant is operating at 100% power. The Jet Pump Operability surveillance is due.

1. Determine if Jet Pumps JP1 through JP10 are operable.
2. Perform OSP-RRC-D701 rev 5, step 7.2.3.a, 7.2.3.b, and ATT. 10.1, using panel indications for these jet pumps.
3. A Histogram is not available.

Page 7

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.2JPM Facility: Columbia Generating Station Task No:

Task Title: Interrupt EWDs Job Performance Measure No: SA.2JM K/A

Reference:

2.1.24 2.8/3.1 Examinee: NRC Examiner:

Facility Evaluator: Date: 02/22/01 Method of testing:

Admin - Simulate Page 1

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.2JPM JPM SETUP INFORMATION Initial Conditions: The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability.

Task Standard: Indications for the start of ROA-FN-1A are explained correctly using EWD 80E001.

Required Materials: N/A General

References:

EWD 80E001 Initiating Cue: The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability. The following scenario occurs:

1. The breaker for the fan has been racked in and the EO has notified the control room he is ready for a start.
2. The CRO notices that the green STOP/OFF indication at the control switch is off. Thinking the light bulb is burned out; the CRO places the control switch for ROA-FN-1A to start.
3. The EO reports the breaker closes by sound and the manual indicators but there is no closed indication on the lights on the breaker door.
4. The CRO also notes there is no closed/running indication in the control room.
5. The CRO places the control switch in the TRIP position.

Nothing happens, the fan continues to run.

6. All light bulbs have been verified as good.

Using EWD 80E001, explain why there are no indicating lights for ROA-FN-1A and why it cannot be tripped.

Time Critical Task: NO Validation Time: 10 min.

Simulator ICs: N/A Malfunctions/Remote N/A Triggers:

Overrides: N/A Special Setup N/A Page 2

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.2JPM Instructions:

PERFORMANCE INFORMATION START TIME:

Critical Step: YES Performance Step: 1 Demonstrate on EWD 80E001 the reason for the indications in the Initiating Cue.

Standard: Using EWD 80E001, demonstrate the following :

1. For the fan to start, the close fuses, FO3-1, FO3-2, F10-1, and F10-2 have to be installed and operable.
2. All light indications for the fan are in the trip circuit.
3. For the fan to trip, the trip fuses FO4-1 and FO4-2 have to be installed and operable.
4. Since the fan started the close fuses were good.
5. Since there was no breaker indication locally or in the control room and the fan would not trip with the control switch the trip fuses FO4-1 and FO4-2 (either or both) are blown or not installed correctly.

FOR FULL CREDIT - It must be indicated that bad/blown trip fuses prevent both light indication and the trip of the fan.

Comment:

SAT / UNSAT THE EXAMINEE SHOULD ANNOUNCE THE TERMINATION POINT OF THE JPM AT THIS POINT.

JPM TERMINATION TIME:

JPM START TIME: -

JPM COMPLETION TIME:

Page 3

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.2JPM VERIFICATION OF COMPLETION JPM Number: SA.2JPM Examinees Name:

Examiners Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Page 4

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.2JPM JPM INFORMATION CARD HAND THE STUDENT INFORMATION CARD TO THE EXAMINEE READ TO THE EXAMINEE:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiation cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

Task Standard: Indications for the start of ROA-FN-1A are explained correctly using EWD 80E001.

Required Materials: N/A Safety Equipment: N/A General

References:

EWD 80E001 Time Critical Task: N/A Initial Conditions: The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability.

INITIATING CUE The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability. The following scenario occurs:

1. The breaker for the fan has been racked in and the EO has notified the control room he is ready for a start.
2. The CRO notices that the green STOP/OFF indication at the control switch is off.

Thinking the light bulb is burned out; the CRO places the control switch for ROA-FN-1A to start.

3. The EO reports the breaker closes by sound and the manual indicators but there is no closed indication on the lights on the breaker door.
4. The CRO also notes there is no closed/running indication in the control room.
5. The CRO places the control switch in the TRIP position. Nothing happens, the fan continues to run.
6. All light bulbs have been verified as good.

Page 5

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.2JPM Using EWD 80E001, explain why there are no indicating lights for ROA-FN-1A and why it cannot be tripped.

INFORMATION BELOW THIS LINE NOT SHARED WITH EXAMINEE Task Number: Validation Time: 10 min.

NUREG 1123

Reference:

2.1.24 2.8/3.1 Time Critical: NO Location: Simulator Performance Method: Simulate - Admin Prepared/Revised by: S Hutchison Revision Date: 1/11/01 Page 6

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.2JPM STUDENT INFORMATION Initial Conditions: The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability.

INITIATING CUE The plant is operating at power. ROA-FN-1A has to be started following maintenance for operability. The following scenario occurs:

1. The breaker for the fan has been racked in and the EO has notified the control room he is ready for a start.
2. The CRO notices that the green STOP/OFF indication at the control switch is off. Thinking the light bulb is burned out; the CRO places the control switch for ROA-FN-1A to start.
3. The EO reports the breaker closes by sound and the manual indicators but there is no closed indication on the lights on the breaker door.
4. The CRO also notes there is no closed/running indication in the control room.
5. The CRO places the control switch in the TRIP position. Nothing happens, the fan continues to run.
6. All light bulbs have been verified as good.

Using EWD 80E001, explain why there are no indicating lights for ROA-FN-1A and why it cannot be tripped.

Page 7

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.3JPM Facility: Columbia Generating Station Task No: SRO-0026 Task Title: Complete Planned Special Job Performance Measure No: SA.3JPM Exposure K/A

Reference:

2.3.4 2.5/3.1 Examinee: NRC Examiner:

Facility Evaluator: Date: 02/22/01 Method of testing:

Admin - Simulate Page 1 Sa3jpmr0

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.3JPM JPM SETUP INFORMATION Initial Conditions: The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is expected to receive a total of 350 mrem to perform the task. An Increased Exposure Request is required for the task.

Task Standard: The paperwork for the Increased Exposure Request is completed in accordance with GEN-RPP-07.

Required Materials: N/A General

References:

GEN-RPP-07.

Initiating Cue: The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is 30 years old and has been employed by Energy Northwest for 5 years. He is expected to receive a total of 350 mrem to perform the task. The following information applies to the operator.

1. John Q Operator
2. SS # - 555-55-5555
3. DOB - 01/01/71
4. 1.8 rem TEDE year to date.
5. 6.875 rem TEDE lifetime.
6. All dose is from Energy Northwest exposure.

As the operators supervisor, complete the Increased Exposure Request per GEN-RPP-07.

Time Critical Task: NO Validation Time: 10 min.

Simulator ICs: N/A Malfunctions/Remote N/A Triggers:

Overrides: N/A Special Setup N/A Instructions:

Page 2 Sa3jpmr0

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.3JPM PERFORMANCE INFORMATION START TIME:

Critical Step: YES Performance Step: 1 Complete the first 3 sections of the Increased Exposure Request as the Supervisor of the designated operator.

Standard: Increased Exposure Request form is completed in accordance with GEN-RPP-07.

Grading Standard - compare candidates completed form with the attached form. Passing Criteria = each required section must match the attached form. The reason and justification must match the intent.

Comment:

SAT / UNSAT THE EXAMINEE SHOULD ANNOUNCE THE TERMINATION POINT OF THE JPM AT THIS POINT.

JPM TERMINATION TIME:

JPM START TIME: -

JPM COMPLETION TIME:

Page 3 Sa3jpmr0

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.3JPM VERIFICATION OF COMPLETION JPM Number: SA.3JPM Examinees Name:

Examiners Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Page 4 Sa3jpmr0

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.3JPM JPM INFORMATION CARD HAND THE STUDENT INFORMATION CARD TO THE EXAMINEE READ TO THE EXAMINEE:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiation cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

Task Standard: The paperwork for the Increased Exposure Request is completed in accordance with GEN-RPP-07.

Required Materials: N/A Safety Equipment: N/A General

References:

GEN-RPP-07.

Time Critical Task: NO Initial Conditions: The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is expected to receive a total of 350 mrem to perform the task. An Increased Exposure Request is required for the task.

INITIATING CUE The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is 30 years old and has been employed by Energy Northwest for 5 years. He is expected to receive a total of 350 mrem to perform the task. The following information applies to the operator.

1. John Q Operator
2. SS # - 555-55-5555
3. DOB - 01/01/71
4. 1.8 rem TEDE year to date.
5. 6.875 rem TEDE lifetime.

Page 5 Sa3jpmr0

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.3JPM

6. All dose is from Energy Northwest exposure.

As the operators supervisor, complete the Increased Exposure Request per GEN-RPP-07.

INFORMATION BELOW THIS LINE NOT SHARED WITH EXAMINEE Task Number: SRO-0026 Validation Time: 10 min.

NUREG 1123

Reference:

2.3.4 2.5/3.1 Time Critical: NO Location: Admin Performance Method: Simulate Prepared/Revised by: S Hutchison Revision Date: 1/10/01 Page 6 Sa3jpmr0

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.3JPM STUDENT INFORMATION Initial Conditions: The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is expected to receive a total of 350 mrem to perform the task. An Increased Exposure Request is required for the task.

INITIATING CUE The plant is in a refueling outage with the drywell open. A valve manipulation is required to flush a hot spot from a trap in the drywell. The operator selected is 30 years old and has been employed by Energy Northwest for 5 years. He is expected to receive a total of 350 mrem to perform the task. The following information applies to the operator.

1. John Q Operator
2. SS # - 555-55-5555
3. DOB - 01/01/71
4. 1.8 rem TEDE year to date.
5. 6.875 rem TEDE lifetime.
6. All dose is from Energy Northwest exposure.

As the operators supervisor, complete the Increased Exposure Request per GEN-RPP-07.

Page 7 Sa3jpmr0

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.4JPM Facility: Columbia Generating Station Task No: SRO-0233 Task Title: Classify the Event Job Performance Measure No: SA.4JPM K/A

Reference:

2.4.41 2.3/4.1 Examinee: NRC Examiner:

Facility Evaluator: Date: 02/22/01 Method of testing:

Admin - Simulate Page 1

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.4JPM JPM SETUP INFORMATION Initial Conditions: The plant is in Mode 3.

Task Standard: Classify the event correctly per PPM 13.1.1 Classifying the Emergency.

Required Materials: N/A General

References:

PPM 13.1.1 rev 28, page 13 Initiating Cue: The plant is in Mode 3. The following conditions exist:

1. Reactor Pressure is 687 psig and down slow
2. Reactor Level is -62 inches and stable
3. Drywell temperature is 251°F and up slow
4. Drywell pressure is 8 psig and up slow
5. Drywell unidentified leakage on EDR-FRS-623 went offscale high for a short period of time and returned to 0.
6. Wind direction 300°
7. Wind speed 8 mph
8. Stability Classification E
9. No precipitation Based on these conditions, determine the Emergency Classification, and complete a CNF form.

Time Critical Task: NO Validation Time: 15 min Simulator ICs: N/A Malfunctions/Remote N/A Triggers:

Overrides: N/A Special Setup N/A Instructions:

Page 2

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.4JPM PERFORMANCE INFORMATION START TIME:

Critical Step: Yes Performance Step: 1 Review plant data and complete CNF form.

CUE:

Standard: 1. Review data and complete CNF form as attached.

2. EAL is ALERT based on either 2.1.a.1 or 3.1.a.1 of PPM 13.1.1.

Comment:

SAT / UNSAT THE EXAMINEE SHOULD ANNOUNCE THE TERMINATION POINT OF THE JPM AT THIS POINT.

JPM TERMINATION TIME:

JPM START TIME: -

JPM COMPLETION TIME:

Page 3

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.4JPM VERIFICATION OF COMPLETION JPM Number: SA.4JPM Examinees Name:

Examiners Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Page 4

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.4JPM JPM INFORMATION CARD HAND THE STUDENT INFORMATION CARD TO THE EXAMINEE READ TO THE EXAMINEE:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiation cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

Task Standard: Classify the event correctly per PPM 13.1.1 Classifying the Emergency.

Required Materials: N/A Safety Equipment: N/A General

References:

PPM 13.1.1 rev 28, page 13 Time Critical Task: NO Initial Conditions: The plant is in Mode 3.

INITIATING CUE The plant is in Mode 3. The following conditions exist:

1. Reactor Pressure is 687 psig and down slow
2. Reactor Level is -62 inches and stable
3. Drywell temperature is 251°F and up slow
4. Drywell pressure is 8 psig and up slow
5. Drywell unidentified leakage on EDR-FRS-623 went offscale high for a short period of time and returned to 0.
6. Wind direction 300°
7. Wind speed 8 mph
8. Stability Classification E
9. No precipitation Page 5

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.4JPM Based on these conditions, determine the Emergency Classification, and complete a CNF form.

Page 6

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.4JPM INFORMATION BELOW THIS LINE NOT SHARED WITH EXAMINEE Task Number: SRO-0233 Validation Time: 15 NUREG 1123

Reference:

2.4.41 2.3/4.1 Time Critical: NO Location: Admin Performance Method: Admin Prepared/Revised by: S Hutchison Revision Date: 1/10/01 Page 7

Appendix C Job Performance Measure Form ES-C-1 Worksheet SA.4JPM STUDENT INFORMATION Initial Conditions: The plant is in Mode 3.

INITIATING CUE The plant is in Mode 3. The following conditions exist:

1. Reactor Pressure is 687 psig and down slow
2. Reactor Level is -62 inches and stable
3. Drywell temperature is 251°F and up slow
4. Drywell pressure is 8 psig and up slow
5. Drywell unidentified leakage on EDR-FRS-623 went offscale high for a short period of time and returned to 0.
6. Wind direction 300°
7. Wind speed 8 mph
8. Stability Classification E
9. No precipitation Based on these conditions, determine the Emergency Classification, and complete a CNF form.

Page 8

ADMINISTRATIVE TOPICS SECTION A2 COLUMBIA GENERATING STATION SRO FEB. 22, 2001 Question No. The plant is operating at 99% power. IN-4 has been lost due to equipment SA.1-1 failure.

Which plant department is the most affected by a loss of IN-4?

CLOSED REFERENCE ANSWER: Security

Response

SAT / UNSAT LO 5897 2.1.27 2.8/2.9 82-RSY-1200-T5 Question No. The plant is shutdown in Mode 4. Maintenance is underway in the Primary SA.1-2 Access Point. A laborer calls the control room and notifies you that an unknown/unbadged person has wondered into the Yakima Building (GSB) asking for directions to FFTF.

What are the required NRC notifications for this event?

OPEN REFERENCE ANSWER: 1 Hour notification to the NRC.

Response

SAT / UNSAT LO 6011 2.1.13 2.1/2.9 PPM 1.10.1 rev 19, page 9 page 1

ADMINISTRATIVE TOPICS SECTION A2 COLUMBIA GENERATING STATION SRO FEB. 22, 2001 Question No. The plant is shutdown in Mode 4. Maintenance is underway in the Primary SA.1-2 Access Point. A laborer calls the control room and notifies you that an unknown/unbadged person has wondered into the Yakima Building (GSB) asking for directions to FFTF.

What are the required NRC notifications for this event?

OPEN REFERENCE page 2

ADMINISTRATIVE TOPICS SECTION A2 COLUMBIA GENERATING STATION SRO FEB. 22, 2001 Question No. The plant is operating at 99% power. IN-4 has been lost due to equipment SA.1-1 failure.

Which plant department is the most affected by a loss of IN-4?

CLOSED REFERENCE page 3