|
|
Line 3: |
Line 3: |
| | issue date = 05/15/2007 | | | issue date = 05/15/2007 |
| | title = Second Round of Draft RAI on the 9/15/07 Amendment Request | | | title = Second Round of Draft RAI on the 9/15/07 Amendment Request |
| | author name = Tam P S | | | author name = Tam P |
| | author affiliation = NRC/NRR/ADRO/DORL/LPLIII-1 | | | author affiliation = NRC/NRR/ADRO/DORL/LPLIII-1 |
| | addressee name = Scarpello M K, Simpson S D, Vasey R G | | | addressee name = Scarpello M, Simpson S, Vasey R |
| | addressee affiliation = American Electric Power Co, Indiana Michigan Power Co | | | addressee affiliation = American Electric Power Co, Indiana Michigan Power Co |
| | docket = 05000316 | | | docket = 05000316 |
| | license number = DPR-074 | | | license number = DPR-074 |
| | contact person = tam P S, NRR/ADRO/DORL, 415-1451 | | | contact person = tam P, NRR/ADRO/DORL, 415-1451 |
| | case reference number = TAC MD3161 | | | case reference number = TAC MD3161 |
| | document type = E-Mail | | | document type = E-Mail |
Revision as of 00:11, 13 July 2019
Letter Sequence Draft RAI |
---|
|
|
MONTHYEARML0726900832001-09-21021 September 2001 Tech Spec Page for Amendment 281 Regarding Reactor Trip on Low Turbine Oil Pressure Project stage: Other ML0626905002006-09-15015 September 2006 Technical Specification Change for Reactor Trip on Low Turbine Oil Pressure Project stage: Other ML0633504122006-12-0101 December 2006 Draft RAI on Amendment Re Turbine Control System Fluid Oil Pressure Project stage: Draft RAI ML0700401882007-01-0303 January 2007 Request for Conference Call Re. Proposed Amendment Project stage: Other ML0701104412007-01-11011 January 2007 Additional Draft RAI Re. Proposed Amendment Project stage: Draft RAI ML0712200812007-04-20020 April 2007 Response to Request for Additional Information Regarding Technical Specification Change for Reactor Trip on Low Turbine Oil Pressure Project stage: Response to RAI ML0710705942007-04-20020 April 2007 Request for Additional Information Regarding Proposed Amendment Regarding Turbine Control Fluid Oil System Modification Project stage: RAI ML0713506602007-05-15015 May 2007 Second Round of Draft RAI on the 9/15/07 Amendment Request Project stage: Draft RAI ML0717202192007-06-28028 June 2007 Request for Additional Information for Proposed Amendment Re. Reactor Trip on Turbine Oil Pressure Project stage: RAI ML0719803932007-07-0606 July 2007 Technical Specification Change for Reactor Trip on Low Turbine Oil Pressure Request for Additional Information Project stage: Request ML0722002522007-07-25025 July 2007 Technical Specification Change for Reactor Trip on Low Turbine Oil Pressure Request for Additional Information Project stage: Request ML0721806392007-09-21021 September 2007 Issuance of License Amendment 281 Regarding Reactor Trip on Low Turbine Oil Pressure Project stage: Approval 2007-04-20
[Table View] |
Similar Documents at Cook |
---|
Category:E-Mail
MONTHYEARML24221A4172024-08-0101 August 2024 DC Cook 2024 PI&R Inspection Request for Information ML24178A0432024-06-26026 June 2024 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - License Amendment Request Regarding Neutron Flux Instrumentation ML24156A0072024-05-30030 May 2024 NRR E-mail Capture - Final RAI - D.C. Cook Nuclear Plant, Unit Nos. 1 and 2 - License Amendment Request Regarding Reserve Feed Enclosure ML24156A0052024-05-22022 May 2024 NRR E-mail Capture - D.C. Cook Nuclear Plant, Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Reserve Feed Enclosure ML24103A1392024-04-12012 April 2024 NRR E-mail Capture - D.C. Cook Nuclear Plant, Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Adoption of 10 CFR 50.69 ML24096A1132024-04-0505 April 2024 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Delay in Issuance of License Amendment Regarding Neutron Flux Instrumentation ML24093A0582024-04-0202 April 2024 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 1 - Acceptance of License Amendment Request Regarding Technical Specification 3.4.12, Low Temperature Overpressure Protection (LTOP) System, ML23361A1022023-12-21021 December 2023 Security Rule Exemption Request - ISFSI Docket No. Reference ML23321A1222023-11-17017 November 2023 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - License Amendment Request Regarding Neutron Flux Instrumentation ML23052A1502023-02-21021 February 2023 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Neutron Flux Instrumentation ML22307A2532022-11-0303 November 2022 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Verbal Authorization of Relief Request ISIR-5-06 Regarding Alternative to N-729-6 for RPV Head Visual Examination ML22122A0902022-04-29029 April 2022 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-554, Revision 1 ML22250A6712022-02-16016 February 2022 Outline Submittal Notification Email DC-Cook 2022 ML21341A6252021-12-0707 December 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-577, Revision 1 ML21307A3352021-11-0303 November 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Final RAI - License Amendment Request Regarding Containment Water Level Instrumentation ML21236A0262021-08-23023 August 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance of License Amendment Regarding Changes to Reactor Vessel Heatup and Cooldown Curves and Low Temperature Overpressure Protection System Requirements ML21140A3052021-05-20020 May 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request ISIR-4-11, Impractical Examinations for the Fourth 10-Year ISI Interval ML21113A2812021-04-23023 April 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request Regarding Containment Water Level Instrumentation ML21089A0222021-03-24024 March 2021 DC Cook Power Operated Valves (POV) Preliminary Request for Information ML21082A0262021-03-22022 March 2021 Acceptance of Relief Request ISIR-4-11, Impractical Examinations for the Fourth 10-Year ISI Interval ML21049A2682021-02-16016 February 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Final RAI - License Amendment Request for One-Time Extension Containment Type a ILRT ML21026A3472021-01-26026 January 2021 NRR E-mail Capture - Final RAI - D.C. Cook 1 & 2 - Relief Request REL-PP2 for Pump and Valve IST Fifth 10-year Interval ML21008A4742021-01-0808 January 2021 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance of License Amendment Request for One-Time Extension Containment Type a ILRT ML20366A1012020-12-31031 December 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance of License Amendment Request for One-Time Deferral of Steam Generator Inspection ML20316A0152020-11-0606 November 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of Relief Request REL-PP2 for Pump and Valve IST Fifth 10-year Interval ML20318A0202020-10-16016 October 2020 NRR E-mail Capture - Regarding Public Comment on D.C. Cook, Unit 1 Request for Relief from Nozzle Inspections, Code Case N-729 ML20289A7122020-10-15015 October 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 1 - Verbal Authorization of Relief Request ISIR-5-04 Regarding Alternative to N-729-6 for RPV Head Visual Examination ML20290A4252020-10-15015 October 2020 Verbal Authorization of Relief Request ISIR-5-04 Regarding Alternative to N-729-6 for RPV Head Visual Examination ML20318A0192020-10-15015 October 2020 NRR E-mail Capture - (External_Sender) Supplemental Public Comment on D.C. Cook, Unit 1 Request for Relief from Nozzle Inspections, Code Case N-729 ML20289A1192020-10-0909 October 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of Relief Request for Alternative to N-729-4 for RPV Head Visual Examination ML20318A0182020-10-0909 October 2020 NRR E-mail Capture - (External_Sender) Public Comment on D.C. Cook, Unit 1 Request for Relief from Nozzle Inspections, Code Case N-729 ML20181A4122020-06-29029 June 2020 NRR E-mail Capture - Final RAI - D.C. Cook 1 - One-Time Extension, Containment Type a ILRT Frequency ML20149K6272020-05-28028 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment and Exemptions Regarding UFSAR 10 CFR 50.71(e)(4) Update Schedule (Epids: L-2020-LLA-0100, L-2020-LLE-0052, L-2020-LLE-0053) ML20149K4332020-05-26026 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-567, Revision 1 ML20141L6062020-05-20020 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-541, Revision 2 ML20141L8112020-05-20020 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of Relief Request Regarding Impracticality for Inservice Inspection for Certain Welds ML20136A5162020-05-15015 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-412, Revision 3 ML20133J9662020-05-11011 May 2020 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 1 - Acceptance of License Amendment Regarding Changes to Reactor Vessel Heatup and Cooldown Curves and Low Temperature Overpressure Protection System Requirements ML20232B4562020-04-27027 April 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Fragility Questions ML20232B4432020-03-25025 March 2020 Request for Supporting Information for the D.C. Cook SPRA Audit Review - Plant Response Model Questions ML19345F9382019-12-0909 December 2019 D.C. Cook 50.54(f) SPRA Submittal - Completeness Review Done and Path Forward ML19333B8042019-11-29029 November 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Adopt TSTF-569 (L-2019-LLA-0248) ML19309F9212019-11-0505 November 2019 Request for Eportal Access for Audit Review of the DC Cook SPRA Supporting Documents ML19270E7372019-09-26026 September 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Adopt TSTF-421, Reactor Coolant Pump Flywheel Inspection Program ML19207A4642019-07-26026 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Delete Diesel Generator Load Test Resistor Banks ML19204A0962019-07-23023 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Request for Additional Information Related to Unit 2 Leak Before Break Analysis and Deletion of Containment Humidity Monitors for Unit Nos. 1 and 2 ML19211C3032019-07-0303 July 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 & 2 - Request for Additional Information Related to LAR to Address NSAL-15-1 ML19175A3032019-06-24024 June 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit No. 2 - Acceptance Review for LAR to Revise Battery Monitoring and Maintenance TS ML19092A4802019-04-0202 April 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Adopt TSTF-563 ML19092A4792019-04-0202 April 2019 NRR E-mail Capture - D.C. Cook Nuclear Plant Unit Nos. 1 and 2 - Acceptance Review for LAR to Address Issues Identified in Westinghouse Document NSAL-15-1 2024-08-01
[Table view] |
Text
From: Peter TamTo:Scarpello, Michael; Simpson, Sue; Vasey, BobDate: 05/15/2007 10:14:31 AM
Subject:
D.C. Cook Unit 2 - Second Round of Draft RAI on the 9/15/06 AmendmentRequest (TAC MD3161)
Bob:
We have reviewed your 4/20/07 response and determined that we need additional information(see below) to complete our review. Consistent with our review process set forth in NRR Office Instruction LIC-101, Rev. 3, we would like to first discuss this information need with you in a conference call: (1) The response to Request 2 states that out-of-tolerance is defined as "exceeding theband established around a desired value...." However, the licensee has not defined how thisband is established. Provide the information about what uncertainties are included in the out-of-tolerance band, basis for their inclusion, and how it is calculated.(2)The response to Request 2 states that "An as-found condition that exceeds thecalibration tolerance......." However, the licensee has not defined how the calibration toleranceis determined. Provide the information about the uncertainties included in the calibration tolerance band, basis for their inclusion, and how it is calculated.(3)The response to Request 2, on page 3, first full paragraph provides the example of Unit1 calibration tolerance but did not state that the same value has been used for Unit 2 also and how it was determined. Provide the calibration tolerance band for Unit 2. (4)The response to Request 2, on page 3, first full paragraph states that the"out-of-Tolerance" evaluation may include changes to the acceptance criteria, changes to switch design or calibration method (including the setpoint value), or the replacement of poorly performing components, but did not provide any detail on how it is determined and who makes that determination and how soon this evaluation is completed. Provide the missing information.This e-mail aims solely to prepare you and others for the proposed conference call. Itdoes not formally request for additional information, and does not convey any formal NRC staff position
.Peter S. Tam, Senior Project ManagerPlant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulatione-mail: pst@nrc.gov Tel.: 301-415-1451 CC:Garg, Hukam; Jin-Sien GuoMail Envelope Properties(4649C047.51D : 12 : 35330)
Subject:
D.C. Cook Unit 2 - Second Round of Draft RAI on the 9/15/06Amendment Request (TAC MD3161)Creation Date05/15/2007 10:14:31 AMFrom: Peter TamCreated By:PST@nrc.gov RecipientsActionDate & Timeaep.comTransferred05/15/2007 10:15:14
AM mkscarpello (Michael Scarpello) rgvasey (Bob Vasey) sdsimpson (Sue Simpson)nrc.gov OWGWPO02.HQGWDO01Delivered05/15/2007 10:14:40
AM HCG CC (Hukam Garg)Opened05/15/2007 10:21:02
AM JSG CC (Jin-Sien Guo)Post Office DeliveredRouteaep.com OWGWPO02.HQGWDO0105/15/2007 10:14:40 AMnrc.govFilesSizeDate & Time MESSAGE314805/15/2007 10:14:31 AMOptions Auto Delete:
No Expiration Date:
None Notify Recipients:
Yes Priority:Standard ReplyRequested:
No Return Notification:
None Concealed
Subject:
No Security:Standard To Be Delivered:Immediate Status Tracking:Delivered & Opened