| | number = ML102780190 | | | number = ML102780190 |
| | issue date = 10/04/2010 | | | issue date = 10/04/2010 |
| | title = Fort Calhoun Unit 1 - Draft Request for Additional Information, Relief Request RR-12, from Requirements of ASME Code Case N-722 for Fourth 10-Year Inservice Inspection Interval (ME4541) | | | title = Draft Request for Additional Information, Relief Request RR-12, from Requirements of ASME Code Case N-722 for Fourth 10-Year Inservice Inspection Interval (ME4541) |
| | author name = Wilkins L E | | | author name = Wilkins L |
| | author affiliation = NRC/NRR/DORL/LPLIV | | | author affiliation = NRC/NRR/DORL/LPLIV |
| | addressee name = Hansher B R | | | addressee name = Hansher B |
| | addressee affiliation = Omaha Public Power District | | | addressee affiliation = Omaha Public Power District |
| | docket = 05000285 | | | docket = 05000285 |
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:ENCLOSURE REQUEST FOR ADDITIONAL INFORMATION REQUEST FOR RELIEF FROM ASME CODE CASE N-722 REQUIREMENTS FOR VISUAL EXAMINATION OF REACTOR VESSEL HOT LEG NOZZLE TO SAFE END WELDS OMAHA PUBLIC POWER DISTRICT, FORT CALHOUN STATION, UNIT NO. 1, DOCKET NO. 50-285 By letter dated August 16, 2010, Omaha Public Power District (the licensee), proposed an alternative to 10 CFR 50.55a(g)(6)(ii)(E) for Fort Calhoun Station, Unit 1. This requirement defines the inservice inspection frequency of visual examination of the reactor vessel hot leg nozzle to safe end welds in accordance with American Society of Mechanical Engineer's Boiler and Pressure Vessel Code Case N-722, "Additional Examinations for PWR Pressure Retaining Welds in Class 1 Components Fabricated With Alloy 600/82/182 Materials," and with NRC conditions. The duration of request is for the fourth 10-year ISI interval which ends on September 25, 2013. | | {{#Wiki_filter:REQUEST FOR ADDITIONAL INFORMATION REQUEST FOR RELIEF FROM ASME CODE CASE N-722 REQUIREMENTS FOR VISUAL EXAMINATION OF REACTOR VESSEL HOT LEG NOZZLE TO SAFE END WELDS OMAHA PUBLIC POWER DISTRICT, FORT CALHOUN STATION, UNIT NO. 1, DOCKET NO. 50-285 By letter dated August 16, 2010, Omaha Public Power District (the licensee), proposed an alternative to 10 CFR 50.55a(g)(6)(ii)(E) for Fort Calhoun Station, Unit 1. This requirement defines the inservice inspection frequency of visual examination of the reactor vessel hot leg nozzle to safe end welds in accordance with American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-722, Additional Examinations for PWR Pressure Retaining Welds in Class 1 Components Fabricated With Alloy 600/82/182 Materials, and with NRC conditions. The duration of request is for the fourth 10-year ISI interval which ends on September 25, 2013. |
| The NRC staff has reviewed and evaluated the information provided by the licensee and has determined that the following information is needed in order to complete its review of the relief request. 1. The NRC staff requests the licensee's basis for not performing a visual, volumetric or inside surface examination of each weld necessary to meet the inspection requirements of 10 CFR 50.55a(g)(6)(ii)(E). If visual, volumetric or inside surface examinations could be performed on each penetration nozzle to meet the current inspection requirements, the NRC staff finds insufficient basis to grant relief under 10 CFR 50.55a(a)(3)(i), as not performing the examination does not provide the same level of assurance as the current inspection requirements. However if there is a hardship, NRC staff requests the licensee's basis for relief to not perform the inspection under 10 CFR 50.55a(a)(3)(ii). 2. NRC staff requests the following references used in the Westinghouse calculation; numbers 3, 5, 6, 8, 9, 10 and 11. NRC staff will need these references quickly to have sufficient time to perform verification calculations and support the licensee's schedule. 3. NRC staff requests the 2003, 2008, and 2009 inspection data of welds designated Items 1 and 2 in Table 1 of the August 16, 2010 relief request. NRC staff requests the inspector's summary reports to verify previous inspection results, and verify basis for initial starting flaw size in flaw analysis calculations. For example, reports documentation the inspection stating "No Reportable" or "No Recordable" indications are requested. 4. In order to support the licensee's use of zinc as a mitigation method, NRC staff requires supporting technical basis documents for review. Specifically, NRC staff requests those documents that address the mitigation effectiveness of the zinc addition history at Fort Calhoun Station, Unit 1, at the current levels at 300 ppb-months, and the rate of addition of 6ppb/month. Also, provide projected rates of addition during the period of requested relief and projected accumulated concentration-time levels over the period of requested relief.}} | | The NRC staff has reviewed and evaluated the information provided by the licensee and has determined that the following information is needed in order to complete its review of the relief request. |
| | : 1. The NRC staff requests the licensees basis for not performing a visual, volumetric or inside surface examination of each weld necessary to meet the inspection requirements of 10 CFR 50.55a(g)(6)(ii)(E). If visual, volumetric or inside surface examinations could be performed on each penetration nozzle to meet the current inspection requirements, the NRC staff finds insufficient basis to grant relief under 10 CFR 50.55a(a)(3)(i), as not performing the examination does not provide the same level of assurance as the current inspection requirements. However if there is a hardship, NRC staff requests the licensees basis for relief to not perform the inspection under 10 CFR 50.55a(a)(3)(ii). |
| | : 2. NRC staff requests the following references used in the Westinghouse calculation; numbers 3, 5, 6, 8, 9, 10 and 11. NRC staff will need these references quickly to have sufficient time to perform verification calculations and support the licensees schedule. |
| | : 3. NRC staff requests the 2003, 2008, and 2009 inspection data of welds designated Items 1 and 2 in Table 1 of the August 16, 2010 relief request. NRC staff requests the inspectors summary reports to verify previous inspection results, and verify basis for initial starting flaw size in flaw analysis calculations. For example, reports documentation the inspection stating No Reportable or No Recordable indications are requested. |
| | : 4. In order to support the licensees use of zinc as a mitigation method, NRC staff requires supporting technical basis documents for review. Specifically, NRC staff requests those documents that address the mitigation effectiveness of the zinc addition history at Fort Calhoun Station, Unit 1, at the current levels at 300 ppb-months, and the rate of addition of 6ppb/month. Also, provide projected rates of addition during the period of requested relief and projected accumulated concentration-time levels over the period of requested relief. |
| | ENCLOSURE}} |
Letter Sequence Draft RAI |
---|
|
|
MONTHYEARML1023006412010-08-16016 August 2010 10 CFR 50.55a Request Number RR-12, Request for Relief from Code Case N-722 Visual Examination of the Reactor Vessel Hot Leg Nozzle to Safe End Dissimilar Metal Welds Project stage: Request ML1026500132010-09-21021 September 2010 Acceptance Review E-mail, Relief Request RR-12, from Requirements of ASME Code Case N-722 Visual Examination of Reactor Vessel Hot-Leg Nozzle to Safe End Dissimilar Metal Welds for 4th 10-Year Inservice Inspection Interval (ME4541) Project stage: Acceptance Review ML1027801882010-10-0404 October 2010 Email, Draft Request for Additional Information, Relief Request RR-12, from Requirements of ASME Code Case N-722 for Fourth 10-Year Inservice Inspection Interval (ME4541) Project stage: Draft RAI ML1027801902010-10-0404 October 2010 Draft Request for Additional Information, Relief Request RR-12, from Requirements of ASME Code Case N-722 for Fourth 10-Year Inservice Inspection Interval (ME4541) Project stage: Draft RAI ML1028600872010-10-25025 October 2010 Request for Additional Information, Relief Request RR-12 from ASME Code Case N-722 Visual Examination Requirements for 4th 10-Year Inservice Inspection Interval Project stage: RAI ML1029101312010-10-25025 October 2010 Request for Withholding Information from Public Disclosure, 7/30/10 Affidavit Executed by J. Gresham, Westinghouse Project stage: Withholding Request Acceptance LIC-10-0095, Response to Request for Additional Information (RAI) Regarding Relief from ASME Code Case N-722 Requirements for Visual Examination of Reactor Vessel Hot Leg Nozzle to Safe End Welds2010-11-0404 November 2010 Response to Request for Additional Information (RAI) Regarding Relief from ASME Code Case N-722 Requirements for Visual Examination of Reactor Vessel Hot Leg Nozzle to Safe End Welds Project stage: Response to RAI ML1102001932011-01-14014 January 2011 Withdrawal of Response to Request for Additional Information (RAI) Regarding Request for Relief from ASME Code Case N-722 Requirements for Visual Examination of Reactor Vessel Hot Leg Nozzle-to-Safe End Dissimilar Metal Butt Welds Project stage: Withdrawal ML1104705872011-02-16016 February 2011 Request for Additional Information LAR to Revise Technical Specification to Relocate Operating and Surveillance Requirements for the Power Operated Relief Valve Project stage: RAI ML1104705882011-02-16016 February 2011 Request for Additional Information Project stage: RAI ML1105404412011-02-23023 February 2011 Request for Additional Information, Round 2, Relief Request RR-12 from ASME Code Case N-722 Visual Examination Requirements for 4th 10-Year Inservice Inspection Interval Project stage: RAI ML1105404492011-02-23023 February 2011 Request for Additional Information, Round 2, Relief Request RR-12 from ASME Code Case N-722 Visual Examination Requirements for 4th 10-Year Inservice Inspection Interval Project stage: RAI ML1106102172011-03-0303 March 2011 Request for Additional Information, Round 2, Relief Request RR-12 from ASME Code Case N-722 Visual Examination Requirements for 4th 10-Year Inservice Inspection Interval Project stage: RAI LIC-11-0016, Response to Second NRC Request for Additional Information (RAI) Regarding Request for Relief from ASME Code Case N-722 Requirements for Visual Examination of Reactor Vessel Hot Leg Nozzle-to-Safe End Dissimilar Metal Butt Welds2011-03-0404 March 2011 Response to Second NRC Request for Additional Information (RAI) Regarding Request for Relief from ASME Code Case N-722 Requirements for Visual Examination of Reactor Vessel Hot Leg Nozzle-to-Safe End Dissimilar Metal Butt Welds Project stage: Request ML1109103272011-04-0505 April 2011 Verbal Authorization, Request for Relief from Code Case N-722 Visual Examination of the Reactor Vessel Hot-Leg Nozzle-to-Safe-End Dissimilar Metal Welds, 4th 10-Year Inservice Inspection Interval Project stage: Other ML1108309472011-05-17017 May 2011 Request for Withholding Information from Public Disclosure, Affidavit Dated 7/30/10, Executed by J. Gresham, Westinghouse, Report LTR-PAFM-10-123-P, Revision 0 Project stage: Withholding Request Acceptance ML1122702902011-08-18018 August 2011 Relief Request RR-12 from Code Case N-722, Additional Examinations for PWR Pressure Retaining Welds in Class 1 Components Fabricated with Alloy 600/82/182 Materials, Fourth 10-Year Inservice Inspection Interval Project stage: Other LIC-12-0004, Delay 2012 Refueling Outage and Extend In-service Inspection (ISI) and In-service Test (IST) Intervals2012-01-17017 January 2012 Delay 2012 Refueling Outage and Extend In-service Inspection (ISI) and In-service Test (IST) Intervals Project stage: Other 2011-02-16
[Table View] |
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML24243A1042024-09-12012 September 2024 Proposed Revision to the OPPD FCS DQAP - Request for Additional Information (License No. DPR-40, Docket Nos. 50-285, 72-054, and 71-0256) ML24180A2062024-07-0808 July 2024 Phase 1 Final Status Survey Reports Request for Additional Information ML23151A0042023-06-0606 June 2023 Second Set RAIs Rev 4 ML22357A0672022-12-30030 December 2022 Enclosure RAI Re Approval of License Termination Plan ML22119A2472022-05-0303 May 2022 Review of Amendment Request to Add a LC to Include LTP Requirements, RAI for Environmental Review ML20111A2162020-05-20020 May 2020 Revised PSDAR Request for Additional Information - RAI ML19241A1812019-08-21021 August 2019 Request for Additional Information on Proposed Changes to the FCS Emergency Plan and Emergency Action Level Scheme to Reflect an ISFSI-only Status ML18067A1432018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to M. J. Fisher Request for Additional Information Regarding Omaha Public Power District'S Decommissioning Funding Plan Update for Fort Calhoun Station ISFSI) ML17236A3462017-08-24024 August 2017 NRR E-mail Capture - Final RAI for Fort Calhoun LAR Regarding Permanently Defueled TS (MF9567) ML17236A3442017-08-24024 August 2017 NRR E-mail Capture - Final RAI for Fort Calhoun Exemption from 10 CFR 140.11(a)(4), Off-site Primary and Secondary Liability Insurance (MF9664) ML17234A4692017-08-22022 August 2017 NRR E-mail Capture - Final RAI for Fort Calhoun LAR Regarding Removal of Dry Cask Loading Limits (MF9831) ML17194A9732017-07-13013 July 2017 NRR E-mail Capture - Final RAI for Fort Calhoun Ultimate Strength Design for Aux. Bldg LAR (MF8525) ML17112A0362017-04-20020 April 2017 NRR E-mail Capture - Fort Calhoun Station - Final RAI Regarding Permanently Defueled EP and EAL Scheme Change LAR ML17090A3942017-03-31031 March 2017 NRR E-mail Capture - Fort Calhoun - Final RAI Regarding Administrative Control TS Change LAR (MF8437) ML17082A0022017-03-22022 March 2017 NRR E-mail Capture - Fort Calhoun Station - Final Nsir/Dpr RAI Regarding Proposed Emergency Planning Exemption ML17081A0192017-03-21021 March 2017 NRR E-mail Capture - Fort Calhoun Station - Final RAI Regarding Proposed Emergency Planning Exemption ML17067A3862017-03-15015 March 2017 Request for Additional Information, Request for Approval of Certified Fuel Handler Training and Retraining Program to Facilitate Activities Associated with Decommissioning and Irradiated Fuel Handling Management ML17033A9692017-02-0202 February 2017 NRR E-mail Capture - Fort Calhoun Station - Final Request for Additional Information Concerning Post-Shutdown Eplan Amendment ML16263A0492016-09-20020 September 2016 Request for Additional Information, Request for Approval of Certified Fuel Handler Training and Retraining Program to Facilitate Activities Associated with Decommissioning and Irradiated Fuel Handling Management ML16174A1502016-06-27027 June 2016 Request for Additional Information, Relief Request, Use of Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1 ML16146A1782016-05-27027 May 2016 Request for Additional Information, Round 2, Request to Revise Current Licensing Basis as Described in the Final Safety Analysis Report to Allow Equipment Classification Methodology from ANSI/ANS-58.14-2011 ML16106A0232016-04-29029 April 2016 Request for Additional Information, Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors ML16104A2872016-04-25025 April 2016 Request for Additional Information, License Amendment Request to Revise Current Licensing Basis to Use American Concrete Institute (Aci) Ultimate Strength Requirements ML16048A1542016-02-23023 February 2016 Request for Additional Information, License Amendment Request, Revise Current Licensing Basis as Described in the Final Safety Analysis Report to Allow Equipment Classification Methodology from ANSI/ANS-58.14-2011 ML16048A0242016-02-23023 February 2016 Request for Additional Information, License Amendment Request to Adopt Technical Specification Task Force (TSTF)-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML15343A1082015-12-15015 December 2015 Request for Additional Information, License Amendment Request to Make Administrative Changes to the Technical Specifications to Update Titles, Delete Obsolete Actions in Appendix B, and Relocate a Definition ML15323A0362015-11-24024 November 2015 Request for Additional Information, Relief Requests P-1 - LPSI and CS Pumps and P-2 - Adjusting Hydraulic Parameters Consistent W/Code Case OMN-21, Fifth 10-Year Inservice Testing Interval ML15194A2722015-07-14014 July 2015 Request for Additional Information, Adopt Emergency Action Level Scheme Pursuant to Nuclear Energy Institute (NEI) 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors ML15057A0152015-03-0303 March 2015 Request for Additional Information, Materials Reliability Program (MRP)-227-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guidelines, Implementation Review ML15043A0612015-02-25025 February 2015 Request for Additional Information, Round 2, License Amendment Request to Revise Updated Safety Analysis Report to Allow Pipe Stress Analysis to Be Performed in Accordance with ASME Code Section III ML14353A0512014-12-22022 December 2014 Request for Additional Information, Request to Revise Updated Safety Analysis Report, Design and Evaluation of Seismic Class I Structures Using Ascm (Alternate Seismic Criteria and Methodologies) Developed Floor Response Spectra ML14259A3652014-09-24024 September 2014 Request for Additional Information, License Amendment Request to Revise Updated Safety Analysis Report to Allow Pipe Stress Analysis to Be Performed in Accordance with ASME Code Section III ML14195A0862014-07-16016 July 2014 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Hazard and Screening Report ML13317A5832013-11-25025 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13290A0022013-10-0909 October 2013 Request for Additional Information Email, License Amendment Request to Revise Current Licensing Basis of Pipe Break Criteria for High Energy Line Breaks ML13282A5362013-10-0909 October 2013 Request for Additional Information Email, Round 2, Exemption Request, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) ML13270A2872013-09-27027 September 2013 Email, Request for Additional Information Round 4 (Apla), Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light-Water Reactor Generating Plants (2001 Edition) ML13261A2122013-09-18018 September 2013 Request for Additional Information Email, Exemption Request, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) ML13233A2482013-08-26026 August 2013 Supplemental Information Needed for Acceptance of Requested Licensing Action; Request for Exemption, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage in Lieu of 10 CFR 26.205(d)(7) ML13235A1682013-08-23023 August 2013 Draft Request for Additional Information Email, Overall Integrated Plan in Response to 3/12/2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) ML13234A4352013-08-22022 August 2013 Request for Additional Information Email, Round 2, Request to Revise TS 2.0.1, General Requirements, and TS 2.7, Electrical Systems, for Inoperable System, Subsystem. or Component Due to Inoperable Power Source ML13226A1222013-08-14014 August 2013 Email, Request for Additional Information Round 3 (Apla), Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light-Water Reactor Generating Plants (2001 Edition) ML13212A0092013-07-30030 July 2013 Request for Additional Information Email, Request to Revise Technical Specification (TS) 2.0.1, General Requirements, and TS 2.7, Electrical Systems, for Inoperable System, Subsystem, or Component Due to Inoperable Power Source ML13205A1252013-07-24024 July 2013 Request for Additional Information Email Round 2, Exigent Amendment Request to Revise Current Licensing Basis to Adopt Revised Design Basis/Methodology for Addressing Design-Basis Tornado/Tornado Missile Impact ML13205A0182013-07-23023 July 2013 Request for Additional Information Email, Exigent License Amendment Request to Revise Current Licensing Basis to Adopt Revised Design Basis/Methodology for Addressing Design-Basis Tornado/Tornado Missile Impact ML13144A4822013-05-23023 May 2013 Request for Additional Information Email, Decommissioning Funding Status Report ML13100A1752013-04-10010 April 2013 Request for Additional Information Email, Request for One-Time Exemption from Requirements of 10 CFR 26.205(d)(7) to Allow Less Restrictive Working Hour Limitations to Support Activities for Plant Startup ML13086A4732013-03-27027 March 2013 Request for Additional Information Email, Request to Revise Technical Specification 2.16, River Level, and Establish EAL Classification Criteria for External Flooding Events Under Radiological Emergency Response Plan ML13120A0842013-03-22022 March 2013 Request for Additional Information Email Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 20 (TAC No. D91660) 2024-09-12
[Table view] |
Text
REQUEST FOR ADDITIONAL INFORMATION REQUEST FOR RELIEF FROM ASME CODE CASE N-722 REQUIREMENTS FOR VISUAL EXAMINATION OF REACTOR VESSEL HOT LEG NOZZLE TO SAFE END WELDS OMAHA PUBLIC POWER DISTRICT, FORT CALHOUN STATION, UNIT NO. 1, DOCKET NO. 50-285 By letter dated August 16, 2010, Omaha Public Power District (the licensee), proposed an alternative to 10 CFR 50.55a(g)(6)(ii)(E) for Fort Calhoun Station, Unit 1. This requirement defines the inservice inspection frequency of visual examination of the reactor vessel hot leg nozzle to safe end welds in accordance with American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-722, Additional Examinations for PWR Pressure Retaining Welds in Class 1 Components Fabricated With Alloy 600/82/182 Materials, and with NRC conditions. The duration of request is for the fourth 10-year ISI interval which ends on September 25, 2013.
The NRC staff has reviewed and evaluated the information provided by the licensee and has determined that the following information is needed in order to complete its review of the relief request.
- 1. The NRC staff requests the licensees basis for not performing a visual, volumetric or inside surface examination of each weld necessary to meet the inspection requirements of 10 CFR 50.55a(g)(6)(ii)(E). If visual, volumetric or inside surface examinations could be performed on each penetration nozzle to meet the current inspection requirements, the NRC staff finds insufficient basis to grant relief under 10 CFR 50.55a(a)(3)(i), as not performing the examination does not provide the same level of assurance as the current inspection requirements. However if there is a hardship, NRC staff requests the licensees basis for relief to not perform the inspection under 10 CFR 50.55a(a)(3)(ii).
- 2. NRC staff requests the following references used in the Westinghouse calculation; numbers 3, 5, 6, 8, 9, 10 and 11. NRC staff will need these references quickly to have sufficient time to perform verification calculations and support the licensees schedule.
- 3. NRC staff requests the 2003, 2008, and 2009 inspection data of welds designated Items 1 and 2 in Table 1 of the August 16, 2010 relief request. NRC staff requests the inspectors summary reports to verify previous inspection results, and verify basis for initial starting flaw size in flaw analysis calculations. For example, reports documentation the inspection stating No Reportable or No Recordable indications are requested.
- 4. In order to support the licensees use of zinc as a mitigation method, NRC staff requires supporting technical basis documents for review. Specifically, NRC staff requests those documents that address the mitigation effectiveness of the zinc addition history at Fort Calhoun Station, Unit 1, at the current levels at 300 ppb-months, and the rate of addition of 6ppb/month. Also, provide projected rates of addition during the period of requested relief and projected accumulated concentration-time levels over the period of requested relief.
ENCLOSURE