| title = Browns Ferry, Units 2, 10 CFR 50 Appendix H Status Update
| title = CFR 50 Appendix H Status Update
| author name = Polson K J
| author name = Polson K
| author affiliation = Tennessee Valley Authority
| author affiliation = Tennessee Valley Authority
| addressee name =  
| addressee name =  
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:Tennessee Valley Authority, Post Office Box 2000, Decatur, Alabama 35609-2000 December 27, 2013 10 CFR 50, Appendix H ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Unit 2 Renewed Facility Operating License No. DPR-52 NRC Docket No. 50-260  
{{#Wiki_filter:Tennessee Valley Authority, Post Office Box 2000, Decatur, Alabama 35609-2000 December 27, 2013 10 CFR 50, Appendix H ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Unit 2 Renewed Facility Operating License No. DPR-52 NRC Docket No. 50-260


==Subject:==
==Subject:==
10 CFR 50 Appendix H Status Update for Browns Ferry Nuclear Plant, Unit 2  
10 CFR 50 Appendix H Status Update for Browns Ferry Nuclear Plant, Unit 2


==Reference:==
==Reference:==
Letter from EPRI to NRC, "Project No. 704 - BWRVIP-271 NP: BWR Vessel and Internals Project, Testing and Evaluation of the Browns Ferry Unit 2 1200 Capsule," dated April 17, 2013 On April 17, 2013, the Electric Power Research Institute (EPRI), on behalf of the Boiling Water Reactor Vessel and Internals Project (BWRVIP), submitted "BWRVIP-271 NP: BWR Vessel and Internals Project, Testing and Evaluation of the Browns Ferry Unit 2 1200 Capsule" (Reference), as required by Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Appendix H, Section IV B. The Tennessee Valley Authority (TVA) has reviewed the test results provided in BWRVIP-271 NP (Reference) and determined that the Pressure-Temperature (P-T) Limits Curves contained in the Browns Ferry Nuclear Plant (BFN), Unit 2, Technical Specifications (TS) Figures 3.4.9-1 and 3.4.9-2 are non-conservative. Corrective actions are being managed by TVA's corrective action program under Problem Evaluation Report 816957.
BFN is treating the non-conservative P-T Limits Curves as a degraded condition and has established compensatory measures to ensure that the BFN, Unit 2, Reactor Vessel is maintained within acceptable limits. As part of the BFN, Unit 2, License Renewal Application, TVA committed to submit revised BFN, Unit 2, P-T Limits Curves prior to the period of extended operation. As such, WVA will submit a License Amendment Request to revise the BFN, Unit 2, P-T Limits Curves by June 27, 2014.
The approval and implementation of the revised P-T Limits Curves will resolve the degraded condition.


Letter from EPRI to NRC, "Project No. 704 -BWRVIP-271 NP: BWR Vessel and Internals Project, Testing and Evaluation of the Browns Ferry Unit 2 1200 Capsule," dated April 17, 2013 On April 17, 2013, the Electric Power Research Institute (EPRI), on behalf of the Boiling Water Reactor Vessel and Internals Project (BWRVIP), submitted"BWRVIP-271 NP: BWR Vessel and Internals Project, Testing and Evaluation of the Browns Ferry Unit 2 1200 Capsule" (Reference), as required by Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Appendix H, Section IV B. The Tennessee Valley Authority (TVA) has reviewed the test results provided in BWRVIP-271 NP (Reference) and determined that the Pressure-Temperature (P-T) Limits Curves contained in the Browns Ferry Nuclear Plant (BFN), Unit 2, Technical Specifications (TS) Figures 3.4.9-1 and 3.4.9-2 are non-conservative.
U.S. Nuclear Regulatory Commission Page 2 December 27, 2013 This letter does not include any new regulatory commitments. Please direct any questions concerning this matter to Jamie Paul, Nuclear Site Licensing Manager, at (256) 729-2636.
Corrective actions are being managed by TVA's corrective action program under Problem Evaluation Report 816957.BFN is treating the non-conservative P-T Limits Curves as a degraded condition and has established compensatory measures to ensure that the BFN, Unit 2, Reactor Vessel is maintained within acceptable limits. As part of the BFN, Unit 2, License Renewal Application, TVA committed to submit revised BFN, Unit 2, P-T Limits Curves prior to the period of extended operation.
cc:
As such, WVA will submit a License Amendment Request to revise the BFN, Unit 2, P-T Limits Curves by June 27, 2014.The approval and implementation of the revised P-T Limits Curves will resolve the degraded condition.
NRC Regional Administrator- Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant}}
U.S. Nuclear Regulatory Commission Page 2 December 27, 2013 This letter does not include any new regulatory commitments.
Please direct any questions concerning this matter to Jamie Paul, Nuclear Site Licensing Manager, at (256) 729-2636.cc: NRC Regional Administrator-Region II NRC Senior Resident Inspector  
-Browns Ferry Nuclear Plant}}

Latest revision as of 10:36, 4 November 2019

CFR 50 Appendix H Status Update
ML14008A108
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 12/27/2013
From: Polson K
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML14008A108 (2)


Text

Tennessee Valley Authority, Post Office Box 2000, Decatur, Alabama 35609-2000 December 27, 2013 10 CFR 50, Appendix H ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Unit 2 Renewed Facility Operating License No. DPR-52 NRC Docket No. 50-260

Subject:

10 CFR 50 Appendix H Status Update for Browns Ferry Nuclear Plant, Unit 2

Reference:

Letter from EPRI to NRC, "Project No. 704 - BWRVIP-271 NP: BWR Vessel and Internals Project, Testing and Evaluation of the Browns Ferry Unit 2 1200 Capsule," dated April 17, 2013 On April 17, 2013, the Electric Power Research Institute (EPRI), on behalf of the Boiling Water Reactor Vessel and Internals Project (BWRVIP), submitted "BWRVIP-271 NP: BWR Vessel and Internals Project, Testing and Evaluation of the Browns Ferry Unit 2 1200 Capsule" (Reference), as required by Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Appendix H,Section IV B. The Tennessee Valley Authority (TVA) has reviewed the test results provided in BWRVIP-271 NP (Reference) and determined that the Pressure-Temperature (P-T) Limits Curves contained in the Browns Ferry Nuclear Plant (BFN), Unit 2, Technical Specifications (TS) Figures 3.4.9-1 and 3.4.9-2 are non-conservative. Corrective actions are being managed by TVA's corrective action program under Problem Evaluation Report 816957.

BFN is treating the non-conservative P-T Limits Curves as a degraded condition and has established compensatory measures to ensure that the BFN, Unit 2, Reactor Vessel is maintained within acceptable limits. As part of the BFN, Unit 2, License Renewal Application, TVA committed to submit revised BFN, Unit 2, P-T Limits Curves prior to the period of extended operation. As such, WVA will submit a License Amendment Request to revise the BFN, Unit 2, P-T Limits Curves by June 27, 2014.

The approval and implementation of the revised P-T Limits Curves will resolve the degraded condition.

U.S. Nuclear Regulatory Commission Page 2 December 27, 2013 This letter does not include any new regulatory commitments. Please direct any questions concerning this matter to Jamie Paul, Nuclear Site Licensing Manager, at (256) 729-2636.

cc:

NRC Regional Administrator- Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant