{{#Wiki_filter:SONGS DECOMMISSIONING CONTROL ROOM / COMMAND CENTER FUNCTION OPTIONS September 24, 2014 Meeting Agenda Topic Time Introduction 12:00 pm SONGS Decommissioning Plan/Schedule 12:10 pm Relocation of Main Control Room / Command Center Functions 12:20 pm NRC Feedback/Discussion on Command Center Option 1:10 pm Path Forward 1:30 pm Security Discussion (Closed Meeting) 1:35 pm Summary/Actions/Conclusion 1:55 pm 2 Security Discussion 3
{{#Wiki_filter:SONGS DECOMMISSIONING CONTROL ROOM / COMMAND CENTER FUNCTION OPTIONS September 24, 2014
Control Room Functional Requirement Comparisons 4 Design Requirement Operating Plant Proposed Decommissioning Security - Access Protected Area/Vital Area Access Controls Protected Area
 
- Bullet Resistance 10 CFR 73.55 (protects plant safety controls)
Meeting Agenda Topic                                             Time Introduction                                     12:00 pm SONGS Decommissioning Plan/Schedule             12:10 pm Relocation of Main Control Room / Command Center 12:20 pm Functions NRC Feedback/Discussion on Command Center 1:10 pm Option Path Forward                                     1:30 pm Security Discussion (Closed Meeting)             1:35 pm Summary/Actions/Conclusion                       1:55 pm 2
Not required (no plant controls in control room)
 
- Cyber Security 10 CFR 73.54 (as functions require) 10 CFR 73.54 (as functions require)
Security Discussion 3
 
Control Room Functional Requirement Comparisons Design Requirement Operating Plant             Proposed Decommissioning Security
  - Access           Protected Area/Vital Area    Protected Area Access Controls
  - Bullet Resistance 10 CFR 73.55 (protects plant Not required (no plant safety controls)            controls in control room)
  - Cyber Security   10 CFR 73.54 (as functions   10 CFR 73.54 (as require)                    functions require) 4


Summary Actions/Conclusions 5}}
Summary Actions/Conclusions 5}}

Latest revision as of 00:53, 4 November 2019

SONGS Public Meeting Slides (Non-Public Portion) - Public Meeting September 24, 2014
ML14272A465
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 09/24/2014
From:
Southern California Edison Co
To:
Office of Nuclear Reactor Regulation
Wengert T
References
Download: ML14272A465 (5)


Text

SONGS DECOMMISSIONING CONTROL ROOM / COMMAND CENTER FUNCTION OPTIONS September 24, 2014

Meeting Agenda Topic Time Introduction 12:00 pm SONGS Decommissioning Plan/Schedule 12:10 pm Relocation of Main Control Room / Command Center 12:20 pm Functions NRC Feedback/Discussion on Command Center 1:10 pm Option Path Forward 1:30 pm Security Discussion (Closed Meeting) 1:35 pm Summary/Actions/Conclusion 1:55 pm 2

Security Discussion 3

Control Room Functional Requirement Comparisons Design Requirement Operating Plant Proposed Decommissioning Security

- Access Protected Area/Vital Area Protected Area Access Controls

- Bullet Resistance 10 CFR 73.55 (protects plant Not required (no plant safety controls) controls in control room)

- Cyber Security 10 CFR 73.54 (as functions 10 CFR 73.54 (as require) functions require) 4

Summary Actions/Conclusions 5