CNL-14-016, Response to Request for Additional Information Regarding Response to Bulletin 2012-01, Design Vulnerability in Electrical Power System: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(One intermediate revision by the same user not shown)
Line 3: Line 3:
| issue date = 02/03/2014
| issue date = 02/03/2014
| title = Response to Request for Additional Information Regarding Response to Bulletin 2012-01, Design Vulnerability in Electrical Power System
| title = Response to Request for Additional Information Regarding Response to Bulletin 2012-01, Design Vulnerability in Electrical Power System
| author name = Shea J W
| author name = Shea J
| author affiliation = Tennessee Valley Authority
| author affiliation = Tennessee Valley Authority
| addressee name =  
| addressee name =  
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:L44 140203 003 Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-14-016 February 3, 2014 10 CFR 50.4 10 CFR 50.54(f) ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391  
{{#Wiki_filter:L44 140203 003 Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-14-016 February 3, 2014 10 CFR 50.4 10 CFR 50.54(f)
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391


==Subject:==
==Subject:==
Response to Request for Additional Information Regarding Response to Bulletin 2012-01, "Design Vulnerability in Electrical Power System"  
Response to Request for Additional Information Regarding Response to Bulletin 2012-01, "Design Vulnerability in Electrical Power System"


==References:==
==References:==
: 1. NRC Bulletin 2012-01, "Design Vulnerability in Electrical Power System," dated July 27, 2012 Printed on recycled paper 2. TVA Letter to NRC, "90-Day Response to NRC Bulletin 2012-01 ,'Design Vulnerability in Electrical Power System,"'
: 1. NRC Bulletin 2012-01, "Design Vulnerability in Electrical Power System,"
dated October 25, 2012 3. NRC Letter to Those on the Enclosed List, ."Request for Additional Information Regarding Response to Bulletin 2012-01, 'Design Vulnerability in Electrical Power System,"'
dated July 27, 2012
dated December 20, 2013 U.S. Nuclear Regulatory Comm i ssion Page 2 February 3, 2014 In Reference 1 , NRC requested that information be provided describing how the protection scheme for Engineered Safety F eature (ESF) buses is designed to detect and automatically respond to single-phase open c i rcuit conditions or high impedance ground fault condi t ions , including a description of the operating configuration of the ESF buses. In Reference 2, the Tennessee Valley Authority (TVA) provided the information requested in Reference 1 for the Browns Ferry , Sequoyah, and Watts Bar Nuclear Plants. In Reference 3 , NRC requested that additional information be provided regarding the completion of interim actions and compensatory measures and the status of long-term corrective actions. This letter provides the requested information for the Browns Ferry , Sequoyah , and Watts Bar Nuclear Plants in Enclosures 1 , 2 , and 3 , respectively. There are no new regulatory commitments contained in this letter. If you have questions regarding this matter, please contact Beth Wetzel at (423) 751-2403. I declare under penalty of perjury that the foregoing i s true and correct. Executed on the 3rd day of February 2014. Enclosures
: 2. TVA Letter to NRC, "90-Day Response to NRC Bulletin 2012-01 ,'Design Vulnerability in Electrical Power System,"' dated October 25, 2012
: 1. Browns Ferry Nuclear Plant , Units 1 , 2 , and 3 Response to NRC Bulletin 2012-01 , " Design Vulnerability i n Electric Power System ," Request for Additional Information
: 3. NRC Letter to Those on the Enclosed List, ."Request for Additional Information Regarding Response to Bulletin 2012-01, 'Design Vulnerability in Electrical Power System,"' dated December 20, 2013 Printed on recycled paper
: 2. Sequoyah Nuclear Plant , Units 1 and 2 Response to NRC Bulletin 2012-01 , " Design Vulnerability in Electric Power System ," Request for Additional Information
: 3. Watts Bar Nuclear Plan t, Units 1 and 2 Response t o NRC Bulletin 2012-01 , " Design Vulnerability in Electric Power System ," Request for Additional Information cc: See page 3 U.S. Nuclear Regulatory Commission Page 3 February 3, 2014 cc: (Enclosure s):  NRC Regional Administrator
- Region II  NRR Director
- NRC Headquarters NRR Project Manager
- Browns Ferry Nuclear Plant NRC Senior Resident Inspector
- Browns Ferry Nuclear Plant NRR Project Manager
- Sequoyah Nuclear Plant NRC Senior Resident Inspector
- Sequoyah Nuclear Plant NRR Project Manager
- Watts Bar Nuclear Plant, Unit 1  NRR Project Manager
- Watts Bar Nuclear Plant, Unit 2  NRC Senior Resident Inspector
- Watts Bar Nuclear Plant


ENCLOSURE 1 Browns Ferry Nuclear Plant, Units 1 , 2, and 3 Response to NRC Bulletin 2012
U.S. Nuclear Regulatory Comm ission Page 2 February 3, 2014 In Reference 1, NRC requested that information be provided describing how the protection scheme for Engineered Safety Feature (ESF) buses is designed to detect and automatically respond to single-phase open circuit conditions or high impedance ground fault conditions, including a description of the operating configuration of the ESF buses.
-01, "Design Vulnerability in Electric Power System" Request for Additional Information
In Reference 2, the Tennessee Valley Authority (TVA) provided the information requested in Reference 1 for the Browns Ferry, Sequoyah, and Watts Bar Nuclear Plants.
In Reference 3, NRC requested that additional information be provided regarding the completion of interim actions and compensatory measures and the status of long-term corrective actions.
This letter provides the requested information for the Browns Ferry, Sequoyah, and Watts Bar Nuclear Plants in Enclosures 1, 2, and 3, respectively .
There are no new regulatory commitments contained in this letter. If you have questions regarding this matter, please contact Beth Wetzel at (423) 751-2403.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 3rd day of February 2014.
Enclosures :
: 1. Browns Ferry Nuclear Plant, Units 1, 2, and 3 Response to NRC Bulletin 2012-01 , "Design Vulnerability in Electric Power System ," Request for Additional Information
: 2. Sequoyah Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01 ,
              "Design Vulnerability in Electric Power System ," Request for Additional Information
: 3. Watts Bar Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01 ,
              "Design Vulnerability in Electric Power System ," Request for Additional Information cc: See page 3


NRC Request for Additional Information NRC letter dated December 20, 2013 request ed the following:
U.S. Nuclear Regulatory Commission Page 3 February 3, 2014 cc: (Enclosures):
  "In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:
NRC Regional Administrator - Region II NRR Director - NRC Headquarters NRR Project Manager - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRR Project Manager - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRR Project Manager - Watts Bar Nuclear Plant, Unit 1 NRR Project Manager - Watts Bar Nuclear Plant, Unit 2 NRC Senior Resident Inspector - Watts Bar Nuclear Plant
: 1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class
-1E vital buses until permanent corrective actions are completed.
: 2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power."
Response 1
- Summary of All Interim Corrective Actions


Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Browns Ferry Nuclear Plant (BFN). Based on the plant's offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):
ENCLOSURE 1 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Response to NRC Bulletin 2012-01, "Design Vulnerability in Electric Power System" Request for Additional Information
A walk-down of the BFN switchyards was performed to identify OPC vulnerabilities.
The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers.
This would most likely be a grounded open phase condition since the distance between most poles/structures was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground.
The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e. stingers).
While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi
-bolt connection and are inspected by thermography during routine PM inspections of the switchyard.
Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of o ff-normal conditions by Operations personnel.
The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
The Byron OPC event was reviewed in Operations training during BFN Licensed Operator Requalification training during the Cycle 13
-1 sessions which incorporated industry lessons learned and BFN system specifics.
E1  1 of 2


Response 2  
NRC Request for Additional Information NRC letter dated December 20, 2013 requested the following:
- Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and i s in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off
In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:
-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.
: 1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class-1E vital buses until permanent corrective actions are completed.
: 2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power.
Response 1 - Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Browns Ferry Nuclear Plant (BFN).
Based on the plants offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):
* A walk-down of the BFN switchyards was performed to identify OPC vulnerabilities.
The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers. This would most likely be a grounded open phase condition since the distance between most poles/structures was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground. The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e. stingers). While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi-bolt connection and are inspected by thermography during routine PM inspections of the switchyard.
* Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
* Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
* The Byron OPC event was reviewed in Operations training during BFN Licensed Operator Requalification training during the Cycle 13-1 sessions which incorporated industry lessons learned and BFN system specifics.
E1 1 of 2
 
Response 2 - Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and is in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.
TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.
TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.
With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.
With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.
Vulnerability studies of the OPC faults are in progress for BFN and additional operator meetings are being scheduled to communicate the results.
Vulnerability studies of the OPC faults are in progress for BFN and additional operator meetings are being scheduled to communicate the results.
The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.
The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.
It is BFN's intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturer's delivery capabilities, licensing delays, etc.
It is BFNs intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturers delivery capabilities, licensing delays, etc.
Any deviation from the Industry OPC Initiative schedule will be documented through t he deviation/exemption process addressed in the NEI OPC Guidance Document.
Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.
E1 2 of 2


E1  2 of 2
ENCLOSURE 2 Sequoyah Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01, "Design Vulnerability in Electric Power System" Request for Additional Information


ENCLOSURE 2 Sequoyah Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012
NRC letter dated December 20, 2013 requested the following:
-01, "Design Vulnerability in Electric Power System" Request for Additional Information
In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:
: 1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class-1E vital buses until permanent corrective actions are completed.
: 2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power.
Response 1 - Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Sequoyah Nuclear Plant (SQN).
Based upon the plants offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):
* A walk-down of the SQN switchyards was performed to identify OPC vulnerabilities.
The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers. This would most likely be a grounded open phase condition since the distance between most poles/structures was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground. The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e. stingers). While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi-bolt connection and are inspected by thermography during routine PM inspections of the switchyard.
* Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
* Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
* A Training Needs Analysis was performed relative to Operations procedures and training curriculum associated with OPC. This led to the inclusion of additional Operations training during SQN Licensed Operator Requalification training during the Cycle 13-2 sessions which incorporated industry lessons learned and SQN system specifics.
E2 1 of 2


NRC letter dated December 20, 2013 request ed the following:
Response 2 - Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and is in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.
  "In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:
: 1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class
-1E vital buses until permanent corrective actions are completed.
: 2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power."
Response 1
- Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Sequoyah Nuclear Plant (SQN). Based upon the plant's offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):
A walk-down of the SQN switchyards was performed to identify OPC vulnerabilities.
The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers.
This would most likely be a grounded open phase condition since the distance between most poles/structures was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground.
The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e. stingers).
While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi
-bolt connection and are inspected by thermography during routine PM inspections of the switchyard.
Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
A Training Needs Analysis was performed relative to Operations procedures and training curriculum associated with OPC. This led to the inclusion of additional Operations training during SQN Licensed Operator Requalification training during the Cycle 13-2 sessions which incorporated industry lessons learned and SQN system specifics.
E 2  1 of 2 Response 2  
- Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and i s in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off
-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.
TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.
TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.
With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.
With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.
Vulnerability studies of the OPC faults have been completed for SQN and additional operator meetings are being scheduled to communicate the results.
Vulnerability studies of the OPC faults have been completed for SQN and additional operator meetings are being scheduled to communicate the results. For the analyzed configurations, the vulnerability studies showed existing protection automatically actuates and provides protection to the Class-1E system for grounded open phase conditions.
For the analyzed configurations, the vulnerability studies showed existing protection automatically actuates and provides protection to the Class
Vulnerability to an ungrounded open phase condition has been identified for some analyzed configurations.
-1E system for grounded open phase conditions. Vulnerability to an ungrounded open phase condition has been identified for some analyzed configurations.
The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.
The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.
It is SQN's intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturer's delivery capabilities, licensing delays, etc.
It is SQNs intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturers delivery capabilities, licensing delays, etc.
Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.
Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.
E 2 2 of 2
E 2 2 of 2
 
ENCLOSURE 3 Watts Bar Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012
-01, "Design Vulnerability in Electric Power System" Request for Additional Information
 
NRC letter dated December 20, 2013 request ed the following:
  "In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:
: 1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class
-1E vital buses until permanent corrective actions are completed.
: 2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power."


Response 1
ENCLOSURE 3 Watts Bar Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01, "Design Vulnerability in Electric Power System" Request for Additional Information
- Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Watts Bar Nuclear Plant (WBN). Based upon the plant's offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):
A walk-down of the WBN switchyards was performed to identify OPC vulnerabilities.
The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers.
This would most likely be a grounded open phase condition since the distance between most poles was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground.
The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e.
, stingers).
While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi
-bolt connection, are not in tension, and are inspected by thermography during routine PM inspections of the switchyard.
Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off
-normal conditions by Operations personnel.
The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
NRC Bulletin 2012
-01 was presented to all licensed operators during Cycle 2013
-02 Licensed Operator Requalification (LOR) training.


E 3 1 of 2
NRC letter dated December 20, 2013 requested the following:
In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:
: 1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class-1E vital buses until permanent corrective actions are completed.
: 2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power.
Response 1 - Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Watts Bar Nuclear Plant (WBN).
Based upon the plants offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):
* A walk-down of the WBN switchyards was performed to identify OPC vulnerabilities.
The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers. This would most likely be a grounded open phase condition since the distance between most poles was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground. The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e., stingers). While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi-bolt connection, are not in tension, and are inspected by thermography during routine PM inspections of the switchyard.
* Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
* Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
* NRC Bulletin 2012-01 was presented to all licensed operators during Cycle 2013-02 Licensed Operator Requalification (LOR) training.
E 3 1 of 2


Response 2  
Response 2 - Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and is in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.
- Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and i s in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off
-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.
TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.
TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.
With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.
With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.
Vulnerability studies of the OPC faults have been completed for WBN and additional operator meetings are being scheduled to communicate the results.
Vulnerability studies of the OPC faults have been completed for WBN and additional operator meetings are being scheduled to communicate the results. For the analyzed configurations, the vulnerability studies showed existing protection automatically actuates and provides protection to the Class-1E system for grounded open phase conditions.
For the analyzed configurations, the vulnerability studies showed existing protection automatically actuates and provides protection to the Class
Vulnerability to an ungrounded open phase condition has been identified for some analyzed configurations.
-1E system for grounded open phase conditions. Vulnerability to an ungrounded open phase condition has been identified for some analyzed configurations.
The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.
The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.
It is WB N's intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturer's delivery capabilities, licensing delays, etc.
It is WBNs intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturers delivery capabilities, licensing delays, etc.
Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.
Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.
E 3 2 of 2}}
E 3 2 of 2}}


=Text=
=Text=
{{#Wiki_filter:L44 140203 003 Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-14-016 February 3, 2014 10 CFR 50.4 10 CFR 50.54(f) ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391  
{{#Wiki_filter:L44 140203 003 Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-14-016 February 3, 2014 10 CFR 50.4 10 CFR 50.54(f)
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391


==Subject:==
==Subject:==
Response to Request for Additional Information Regarding Response to Bulletin 2012-01, "Design Vulnerability in Electrical Power System"  
Response to Request for Additional Information Regarding Response to Bulletin 2012-01, "Design Vulnerability in Electrical Power System"


==References:==
==References:==
: 1. NRC Bulletin 2012-01, "Design Vulnerability in Electrical Power System," dated July 27, 2012 Printed on recycled paper 2. TVA Letter to NRC, "90-Day Response to NRC Bulletin 2012-01 ,'Design Vulnerability in Electrical Power System,"'
: 1. NRC Bulletin 2012-01, "Design Vulnerability in Electrical Power System,"
dated October 25, 2012 3. NRC Letter to Those on the Enclosed List, ."Request for Additional Information Regarding Response to Bulletin 2012-01, 'Design Vulnerability in Electrical Power System,"'
dated July 27, 2012
dated December 20, 2013 U.S. Nuclear Regulatory Comm i ssion Page 2 February 3, 2014 In Reference 1 , NRC requested that information be provided describing how the protection scheme for Engineered Safety F eature (ESF) buses is designed to detect and automatically respond to single-phase open c i rcuit conditions or high impedance ground fault condi t ions , including a description of the operating configuration of the ESF buses. In Reference 2, the Tennessee Valley Authority (TVA) provided the information requested in Reference 1 for the Browns Ferry , Sequoyah, and Watts Bar Nuclear Plants. In Reference 3 , NRC requested that additional information be provided regarding the completion of interim actions and compensatory measures and the status of long-term corrective actions. This letter provides the requested information for the Browns Ferry , Sequoyah , and Watts Bar Nuclear Plants in Enclosures 1 , 2 , and 3 , respectively. There are no new regulatory commitments contained in this letter. If you have questions regarding this matter, please contact Beth Wetzel at (423) 751-2403. I declare under penalty of perjury that the foregoing i s true and correct. Executed on the 3rd day of February 2014. Enclosures
: 2. TVA Letter to NRC, "90-Day Response to NRC Bulletin 2012-01 ,'Design Vulnerability in Electrical Power System,"' dated October 25, 2012
: 1. Browns Ferry Nuclear Plant , Units 1 , 2 , and 3 Response to NRC Bulletin 2012-01 , " Design Vulnerability i n Electric Power System ," Request for Additional Information
: 3. NRC Letter to Those on the Enclosed List, ."Request for Additional Information Regarding Response to Bulletin 2012-01, 'Design Vulnerability in Electrical Power System,"' dated December 20, 2013 Printed on recycled paper
: 2. Sequoyah Nuclear Plant , Units 1 and 2 Response to NRC Bulletin 2012-01 , " Design Vulnerability in Electric Power System ," Request for Additional Information
 
: 3. Watts Bar Nuclear Plan t, Units 1 and 2 Response t o NRC Bulletin 2012-01 , " Design Vulnerability in Electric Power System ," Request for Additional Information cc: See page 3 U.S. Nuclear Regulatory Commission Page 3 February 3, 2014 cc: (Enclosure s):  NRC Regional Administrator
U.S. Nuclear Regulatory Comm ission Page 2 February 3, 2014 In Reference 1, NRC requested that information be provided describing how the protection scheme for Engineered Safety Feature (ESF) buses is designed to detect and automatically respond to single-phase open circuit conditions or high impedance ground fault conditions, including a description of the operating configuration of the ESF buses.
- Region II  NRR Director
In Reference 2, the Tennessee Valley Authority (TVA) provided the information requested in Reference 1 for the Browns Ferry, Sequoyah, and Watts Bar Nuclear Plants.
- NRC Headquarters NRR Project Manager
In Reference 3, NRC requested that additional information be provided regarding the completion of interim actions and compensatory measures and the status of long-term corrective actions.
- Browns Ferry Nuclear Plant NRC Senior Resident Inspector
This letter provides the requested information for the Browns Ferry, Sequoyah, and Watts Bar Nuclear Plants in Enclosures 1, 2, and 3, respectively .
- Browns Ferry Nuclear Plant NRR Project Manager
There are no new regulatory commitments contained in this letter. If you have questions regarding this matter, please contact Beth Wetzel at (423) 751-2403.
- Sequoyah Nuclear Plant NRC Senior Resident Inspector
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 3rd day of February 2014.
- Sequoyah Nuclear Plant NRR Project Manager
Enclosures :
- Watts Bar Nuclear Plant, Unit 1  NRR Project Manager
: 1. Browns Ferry Nuclear Plant, Units 1, 2, and 3 Response to NRC Bulletin 2012-01 , "Design Vulnerability in Electric Power System ," Request for Additional Information
- Watts Bar Nuclear Plant, Unit 2  NRC Senior Resident Inspector
: 2. Sequoyah Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01 ,
- Watts Bar Nuclear Plant
              "Design Vulnerability in Electric Power System ," Request for Additional Information
: 3. Watts Bar Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01 ,
              "Design Vulnerability in Electric Power System ," Request for Additional Information cc: See page 3


ENCLOSURE 1 Browns Ferry Nuclear Plant, Units 1 , 2, and 3 Response to NRC Bulletin 2012
U.S. Nuclear Regulatory Commission Page 3 February 3, 2014 cc: (Enclosures):
-01, "Design Vulnerability in Electric Power System" Request for Additional Information
NRC Regional Administrator - Region II NRR Director - NRC Headquarters NRR Project Manager - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRR Project Manager - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRR Project Manager - Watts Bar Nuclear Plant, Unit 1 NRR Project Manager - Watts Bar Nuclear Plant, Unit 2 NRC Senior Resident Inspector - Watts Bar Nuclear Plant


NRC Request for Additional Information NRC letter dated December 20, 2013 request ed the following:
ENCLOSURE 1 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Response to NRC Bulletin 2012-01, "Design Vulnerability in Electric Power System" Request for Additional Information
  "In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:
: 1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class
-1E vital buses until permanent corrective actions are completed.
: 2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power."
Response 1
- Summary of All Interim Corrective Actions


Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Browns Ferry Nuclear Plant (BFN). Based on the plant's offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):
NRC Request for Additional Information NRC letter dated December 20, 2013 requested the following:
A walk-down of the BFN switchyards was performed to identify OPC vulnerabilities.
In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:
The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers.
: 1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class-1E vital buses until permanent corrective actions are completed.
This would most likely be a grounded open phase condition since the distance between most poles/structures was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground.
: 2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power.
The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e. stingers).
Response 1 - Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Browns Ferry Nuclear Plant (BFN).
While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi
Based on the plants offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):
-bolt connection and are inspected by thermography during routine PM inspections of the switchyard.
* A walk-down of the BFN switchyards was performed to identify OPC vulnerabilities.
Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of o ff-normal conditions by Operations personnel.
The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers. This would most likely be a grounded open phase condition since the distance between most poles/structures was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground. The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e. stingers). While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi-bolt connection and are inspected by thermography during routine PM inspections of the switchyard.
The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
* Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
* Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
The Byron OPC event was reviewed in Operations training during BFN Licensed Operator Requalification training during the Cycle 13
* The Byron OPC event was reviewed in Operations training during BFN Licensed Operator Requalification training during the Cycle 13-1 sessions which incorporated industry lessons learned and BFN system specifics.
-1 sessions which incorporated industry lessons learned and BFN system specifics.
E1 1 of 2
E1 1 of 2


Response 2  
Response 2 - Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and is in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.
- Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and i s in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off
-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.
TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.
TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.
With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.
With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.
Vulnerability studies of the OPC faults are in progress for BFN and additional operator meetings are being scheduled to communicate the results.
Vulnerability studies of the OPC faults are in progress for BFN and additional operator meetings are being scheduled to communicate the results.
The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.
The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.
It is BFN's intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturer's delivery capabilities, licensing delays, etc.
It is BFNs intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturers delivery capabilities, licensing delays, etc.
Any deviation from the Industry OPC Initiative schedule will be documented through t he deviation/exemption process addressed in the NEI OPC Guidance Document.
Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.
E1 2 of 2


E1  2 of 2
ENCLOSURE 2 Sequoyah Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01, "Design Vulnerability in Electric Power System" Request for Additional Information


ENCLOSURE 2 Sequoyah Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012
NRC letter dated December 20, 2013 requested the following:
-01, "Design Vulnerability in Electric Power System" Request for Additional Information
In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:
: 1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class-1E vital buses until permanent corrective actions are completed.
: 2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power.
Response 1 - Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Sequoyah Nuclear Plant (SQN).
Based upon the plants offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):
* A walk-down of the SQN switchyards was performed to identify OPC vulnerabilities.
The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers. This would most likely be a grounded open phase condition since the distance between most poles/structures was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground. The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e. stingers). While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi-bolt connection and are inspected by thermography during routine PM inspections of the switchyard.
* Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
* Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
* A Training Needs Analysis was performed relative to Operations procedures and training curriculum associated with OPC. This led to the inclusion of additional Operations training during SQN Licensed Operator Requalification training during the Cycle 13-2 sessions which incorporated industry lessons learned and SQN system specifics.
E2 1 of 2


NRC letter dated December 20, 2013 request ed the following:
Response 2 - Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and is in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.
  "In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:
: 1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class
-1E vital buses until permanent corrective actions are completed.
: 2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power."
Response 1
- Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Sequoyah Nuclear Plant (SQN). Based upon the plant's offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):
A walk-down of the SQN switchyards was performed to identify OPC vulnerabilities.
The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers.
This would most likely be a grounded open phase condition since the distance between most poles/structures was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground.
The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e. stingers).
While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi
-bolt connection and are inspected by thermography during routine PM inspections of the switchyard.
Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
A Training Needs Analysis was performed relative to Operations procedures and training curriculum associated with OPC. This led to the inclusion of additional Operations training during SQN Licensed Operator Requalification training during the Cycle 13-2 sessions which incorporated industry lessons learned and SQN system specifics.
E 2  1 of 2 Response 2  
- Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and i s in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off
-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.
TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.
TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.
With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.
With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.
Vulnerability studies of the OPC faults have been completed for SQN and additional operator meetings are being scheduled to communicate the results.
Vulnerability studies of the OPC faults have been completed for SQN and additional operator meetings are being scheduled to communicate the results. For the analyzed configurations, the vulnerability studies showed existing protection automatically actuates and provides protection to the Class-1E system for grounded open phase conditions.
For the analyzed configurations, the vulnerability studies showed existing protection automatically actuates and provides protection to the Class
Vulnerability to an ungrounded open phase condition has been identified for some analyzed configurations.
-1E system for grounded open phase conditions. Vulnerability to an ungrounded open phase condition has been identified for some analyzed configurations.
The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.
The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.
It is SQN's intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturer's delivery capabilities, licensing delays, etc.
It is SQNs intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturers delivery capabilities, licensing delays, etc.
Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.
Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.
E 2 2 of 2
E 2 2 of 2
 
ENCLOSURE 3 Watts Bar Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012
-01, "Design Vulnerability in Electric Power System" Request for Additional Information
 
NRC letter dated December 20, 2013 request ed the following:
  "In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:
: 1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class
-1E vital buses until permanent corrective actions are completed.
: 2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power."


Response 1
ENCLOSURE 3 Watts Bar Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01, "Design Vulnerability in Electric Power System" Request for Additional Information
- Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Watts Bar Nuclear Plant (WBN). Based upon the plant's offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):
A walk-down of the WBN switchyards was performed to identify OPC vulnerabilities.
The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers.
This would most likely be a grounded open phase condition since the distance between most poles was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground.
The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e.
, stingers).
While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi
-bolt connection, are not in tension, and are inspected by thermography during routine PM inspections of the switchyard.
Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off
-normal conditions by Operations personnel.
The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
NRC Bulletin 2012
-01 was presented to all licensed operators during Cycle 2013
-02 Licensed Operator Requalification (LOR) training.


E 3 1 of 2
NRC letter dated December 20, 2013 requested the following:
In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:
: 1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class-1E vital buses until permanent corrective actions are completed.
: 2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power.
Response 1 - Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Watts Bar Nuclear Plant (WBN).
Based upon the plants offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):
* A walk-down of the WBN switchyards was performed to identify OPC vulnerabilities.
The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers. This would most likely be a grounded open phase condition since the distance between most poles was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground. The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e., stingers). While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi-bolt connection, are not in tension, and are inspected by thermography during routine PM inspections of the switchyard.
* Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
* Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
* NRC Bulletin 2012-01 was presented to all licensed operators during Cycle 2013-02 Licensed Operator Requalification (LOR) training.
E 3 1 of 2


Response 2  
Response 2 - Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and is in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.
- Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and i s in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off
-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.
TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.
TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.
With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.
With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.
Vulnerability studies of the OPC faults have been completed for WBN and additional operator meetings are being scheduled to communicate the results.
Vulnerability studies of the OPC faults have been completed for WBN and additional operator meetings are being scheduled to communicate the results. For the analyzed configurations, the vulnerability studies showed existing protection automatically actuates and provides protection to the Class-1E system for grounded open phase conditions.
For the analyzed configurations, the vulnerability studies showed existing protection automatically actuates and provides protection to the Class
Vulnerability to an ungrounded open phase condition has been identified for some analyzed configurations.
-1E system for grounded open phase conditions. Vulnerability to an ungrounded open phase condition has been identified for some analyzed configurations.
The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.
The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.
It is WB N's intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturer's delivery capabilities, licensing delays, etc.
It is WBNs intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturers delivery capabilities, licensing delays, etc.
Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.
Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.
E 3 2 of 2}}
E 3 2 of 2}}

Latest revision as of 09:36, 4 November 2019

Response to Request for Additional Information Regarding Response to Bulletin 2012-01, Design Vulnerability in Electrical Power System
ML14038A075
Person / Time
Site: Browns Ferry, Watts Bar, Sequoyah  Tennessee Valley Authority icon.png
Issue date: 02/03/2014
From: James Shea
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
BL-12-001, CNL-14-016, L44 140203 003
Download: ML14038A075 (12)


Text

L44 140203 003 Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-14-016 February 3, 2014 10 CFR 50.4 10 CFR 50.54(f)

ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391

Subject:

Response to Request for Additional Information Regarding Response to Bulletin 2012-01, "Design Vulnerability in Electrical Power System"

References:

1. NRC Bulletin 2012-01, "Design Vulnerability in Electrical Power System,"

dated July 27, 2012

2. TVA Letter to NRC, "90-Day Response to NRC Bulletin 2012-01 ,'Design Vulnerability in Electrical Power System,"' dated October 25, 2012
3. NRC Letter to Those on the Enclosed List, ."Request for Additional Information Regarding Response to Bulletin 2012-01, 'Design Vulnerability in Electrical Power System,"' dated December 20, 2013 Printed on recycled paper

U.S. Nuclear Regulatory Comm ission Page 2 February 3, 2014 In Reference 1, NRC requested that information be provided describing how the protection scheme for Engineered Safety Feature (ESF) buses is designed to detect and automatically respond to single-phase open circuit conditions or high impedance ground fault conditions, including a description of the operating configuration of the ESF buses.

In Reference 2, the Tennessee Valley Authority (TVA) provided the information requested in Reference 1 for the Browns Ferry, Sequoyah, and Watts Bar Nuclear Plants.

In Reference 3, NRC requested that additional information be provided regarding the completion of interim actions and compensatory measures and the status of long-term corrective actions.

This letter provides the requested information for the Browns Ferry, Sequoyah, and Watts Bar Nuclear Plants in Enclosures 1, 2, and 3, respectively .

There are no new regulatory commitments contained in this letter. If you have questions regarding this matter, please contact Beth Wetzel at (423) 751-2403.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 3rd day of February 2014.

Enclosures :

1. Browns Ferry Nuclear Plant, Units 1, 2, and 3 Response to NRC Bulletin 2012-01 , "Design Vulnerability in Electric Power System ," Request for Additional Information
2. Sequoyah Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01 ,

"Design Vulnerability in Electric Power System ," Request for Additional Information

3. Watts Bar Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01 ,

"Design Vulnerability in Electric Power System ," Request for Additional Information cc: See page 3

U.S. Nuclear Regulatory Commission Page 3 February 3, 2014 cc: (Enclosures):

NRC Regional Administrator - Region II NRR Director - NRC Headquarters NRR Project Manager - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRR Project Manager - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRR Project Manager - Watts Bar Nuclear Plant, Unit 1 NRR Project Manager - Watts Bar Nuclear Plant, Unit 2 NRC Senior Resident Inspector - Watts Bar Nuclear Plant

ENCLOSURE 1 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Response to NRC Bulletin 2012-01, "Design Vulnerability in Electric Power System" Request for Additional Information

NRC Request for Additional Information NRC letter dated December 20, 2013 requested the following:

In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:

1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class-1E vital buses until permanent corrective actions are completed.
2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power.

Response 1 - Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Browns Ferry Nuclear Plant (BFN).

Based on the plants offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):

The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers. This would most likely be a grounded open phase condition since the distance between most poles/structures was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground. The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e. stingers). While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi-bolt connection and are inspected by thermography during routine PM inspections of the switchyard.

  • Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
  • Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
  • The Byron OPC event was reviewed in Operations training during BFN Licensed Operator Requalification training during the Cycle 13-1 sessions which incorporated industry lessons learned and BFN system specifics.

E1 1 of 2

Response 2 - Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and is in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.

TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.

With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.

Vulnerability studies of the OPC faults are in progress for BFN and additional operator meetings are being scheduled to communicate the results.

The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.

It is BFNs intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturers delivery capabilities, licensing delays, etc.

Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.

E1 2 of 2

ENCLOSURE 2 Sequoyah Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01, "Design Vulnerability in Electric Power System" Request for Additional Information

NRC letter dated December 20, 2013 requested the following:

In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:

1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class-1E vital buses until permanent corrective actions are completed.
2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power.

Response 1 - Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Sequoyah Nuclear Plant (SQN).

Based upon the plants offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):

The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers. This would most likely be a grounded open phase condition since the distance between most poles/structures was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground. The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e. stingers). While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi-bolt connection and are inspected by thermography during routine PM inspections of the switchyard.

  • Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
  • Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
  • A Training Needs Analysis was performed relative to Operations procedures and training curriculum associated with OPC. This led to the inclusion of additional Operations training during SQN Licensed Operator Requalification training during the Cycle 13-2 sessions which incorporated industry lessons learned and SQN system specifics.

E2 1 of 2

Response 2 - Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and is in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.

TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.

With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.

Vulnerability studies of the OPC faults have been completed for SQN and additional operator meetings are being scheduled to communicate the results. For the analyzed configurations, the vulnerability studies showed existing protection automatically actuates and provides protection to the Class-1E system for grounded open phase conditions.

Vulnerability to an ungrounded open phase condition has been identified for some analyzed configurations.

The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.

It is SQNs intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturers delivery capabilities, licensing delays, etc.

Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.

E 2 2 of 2

ENCLOSURE 3 Watts Bar Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01, "Design Vulnerability in Electric Power System" Request for Additional Information

NRC letter dated December 20, 2013 requested the following:

In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:

1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class-1E vital buses until permanent corrective actions are completed.
2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power.

Response 1 - Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Watts Bar Nuclear Plant (WBN).

Based upon the plants offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):

The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers. This would most likely be a grounded open phase condition since the distance between most poles was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground. The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e., stingers). While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi-bolt connection, are not in tension, and are inspected by thermography during routine PM inspections of the switchyard.

  • Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
  • Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
  • NRC Bulletin 2012-01 was presented to all licensed operators during Cycle 2013-02 Licensed Operator Requalification (LOR) training.

E 3 1 of 2

Response 2 - Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and is in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.

TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.

With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.

Vulnerability studies of the OPC faults have been completed for WBN and additional operator meetings are being scheduled to communicate the results. For the analyzed configurations, the vulnerability studies showed existing protection automatically actuates and provides protection to the Class-1E system for grounded open phase conditions.

Vulnerability to an ungrounded open phase condition has been identified for some analyzed configurations.

The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.

It is WBNs intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturers delivery capabilities, licensing delays, etc.

Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.

E 3 2 of 2

Text

L44 140203 003 Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-14-016 February 3, 2014 10 CFR 50.4 10 CFR 50.54(f)

ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391

Subject:

Response to Request for Additional Information Regarding Response to Bulletin 2012-01, "Design Vulnerability in Electrical Power System"

References:

1. NRC Bulletin 2012-01, "Design Vulnerability in Electrical Power System,"

dated July 27, 2012

2. TVA Letter to NRC, "90-Day Response to NRC Bulletin 2012-01 ,'Design Vulnerability in Electrical Power System,"' dated October 25, 2012
3. NRC Letter to Those on the Enclosed List, ."Request for Additional Information Regarding Response to Bulletin 2012-01, 'Design Vulnerability in Electrical Power System,"' dated December 20, 2013 Printed on recycled paper

U.S. Nuclear Regulatory Comm ission Page 2 February 3, 2014 In Reference 1, NRC requested that information be provided describing how the protection scheme for Engineered Safety Feature (ESF) buses is designed to detect and automatically respond to single-phase open circuit conditions or high impedance ground fault conditions, including a description of the operating configuration of the ESF buses.

In Reference 2, the Tennessee Valley Authority (TVA) provided the information requested in Reference 1 for the Browns Ferry, Sequoyah, and Watts Bar Nuclear Plants.

In Reference 3, NRC requested that additional information be provided regarding the completion of interim actions and compensatory measures and the status of long-term corrective actions.

This letter provides the requested information for the Browns Ferry, Sequoyah, and Watts Bar Nuclear Plants in Enclosures 1, 2, and 3, respectively .

There are no new regulatory commitments contained in this letter. If you have questions regarding this matter, please contact Beth Wetzel at (423) 751-2403.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 3rd day of February 2014.

Enclosures :

1. Browns Ferry Nuclear Plant, Units 1, 2, and 3 Response to NRC Bulletin 2012-01 , "Design Vulnerability in Electric Power System ," Request for Additional Information
2. Sequoyah Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01 ,

"Design Vulnerability in Electric Power System ," Request for Additional Information

3. Watts Bar Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01 ,

"Design Vulnerability in Electric Power System ," Request for Additional Information cc: See page 3

U.S. Nuclear Regulatory Commission Page 3 February 3, 2014 cc: (Enclosures):

NRC Regional Administrator - Region II NRR Director - NRC Headquarters NRR Project Manager - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRR Project Manager - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRR Project Manager - Watts Bar Nuclear Plant, Unit 1 NRR Project Manager - Watts Bar Nuclear Plant, Unit 2 NRC Senior Resident Inspector - Watts Bar Nuclear Plant

ENCLOSURE 1 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Response to NRC Bulletin 2012-01, "Design Vulnerability in Electric Power System" Request for Additional Information

NRC Request for Additional Information NRC letter dated December 20, 2013 requested the following:

In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:

1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class-1E vital buses until permanent corrective actions are completed.
2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power.

Response 1 - Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Browns Ferry Nuclear Plant (BFN).

Based on the plants offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):

The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers. This would most likely be a grounded open phase condition since the distance between most poles/structures was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground. The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e. stingers). While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi-bolt connection and are inspected by thermography during routine PM inspections of the switchyard.

  • Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
  • Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
  • The Byron OPC event was reviewed in Operations training during BFN Licensed Operator Requalification training during the Cycle 13-1 sessions which incorporated industry lessons learned and BFN system specifics.

E1 1 of 2

Response 2 - Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and is in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.

TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.

With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.

Vulnerability studies of the OPC faults are in progress for BFN and additional operator meetings are being scheduled to communicate the results.

The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.

It is BFNs intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturers delivery capabilities, licensing delays, etc.

Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.

E1 2 of 2

ENCLOSURE 2 Sequoyah Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01, "Design Vulnerability in Electric Power System" Request for Additional Information

NRC letter dated December 20, 2013 requested the following:

In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:

1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class-1E vital buses until permanent corrective actions are completed.
2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power.

Response 1 - Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Sequoyah Nuclear Plant (SQN).

Based upon the plants offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):

The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers. This would most likely be a grounded open phase condition since the distance between most poles/structures was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground. The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e. stingers). While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi-bolt connection and are inspected by thermography during routine PM inspections of the switchyard.

  • Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
  • Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
  • A Training Needs Analysis was performed relative to Operations procedures and training curriculum associated with OPC. This led to the inclusion of additional Operations training during SQN Licensed Operator Requalification training during the Cycle 13-2 sessions which incorporated industry lessons learned and SQN system specifics.

E2 1 of 2

Response 2 - Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and is in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.

TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.

With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.

Vulnerability studies of the OPC faults have been completed for SQN and additional operator meetings are being scheduled to communicate the results. For the analyzed configurations, the vulnerability studies showed existing protection automatically actuates and provides protection to the Class-1E system for grounded open phase conditions.

Vulnerability to an ungrounded open phase condition has been identified for some analyzed configurations.

The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.

It is SQNs intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturers delivery capabilities, licensing delays, etc.

Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.

E 2 2 of 2

ENCLOSURE 3 Watts Bar Nuclear Plant, Units 1 and 2 Response to NRC Bulletin 2012-01, "Design Vulnerability in Electric Power System" Request for Additional Information

NRC letter dated December 20, 2013 requested the following:

In order for the NRC staff to complete its review of responses to the bulletin, the following additional information is requested:

1. Provide a summary of all interim corrective actions that have been taken since the January 30, 2012, event at Byron Station, Unit 2, to ensure that plant operators can promptly diagnose and respond to open phase conditions on the offsite power circuits for Class-1E vital buses until permanent corrective actions are completed.
2. Provide a status and schedule for completion of plant design changes and modifications to resolve issues with an open phase of electric power.

Response 1 - Summary of All Interim Corrective Actions Lessons learned from the events at Byron station were reviewed and various interim corrective actions evaluated for safety and efficiency at Watts Bar Nuclear Plant (WBN).

Based upon the plants offsite power configuration, electrical design details, and industry lessons learned shared through the Institute of Nuclear Power Operations (INPO) and Nuclear Energy Institute (NEI), the following actions were taken to ensure plant operators can promptly diagnose and respond to open phase conditions (OPCs):

The walk-down determined if an open phase condition were to occur, it would be most likely at the overhead line connection to the offsite power transformers. This would most likely be a grounded open phase condition since the distance between most poles was greater than the height of the lines and a breakpoint in these spans would allow the transmission line to fall to the ground. The walkdown also determined a potential vulnerability of an ungrounded open phase condition in the overhead transmission line connection points (i.e., stingers). While stinger failure provided a conceivable ungrounded open phase condition, it was determined unlikely since most stingers have a multi-bolt connection, are not in tension, and are inspected by thermography during routine PM inspections of the switchyard.

  • Procedures for daily transformer yard inspections were reviewed to ensure the thoroughness and completeness relative to the identification of off-normal conditions by Operations personnel. The procedures for periodic thermography of switchyard components (performed to assist in the early identification of degraded components) were also reviewed.
  • Bus transfer procedures were verified to ensure three phase voltages are checked prior to bus transfers and the bus voltage is checked on the bus voltmeter after the bus transfers.
  • NRC Bulletin 2012-01 was presented to all licensed operators during Cycle 2013-02 Licensed Operator Requalification (LOR) training.

E 3 1 of 2

Response 2 - Status and Schedule for Completion of Plant Design Changes Holders of operating licenses and combined licenses for nuclear power reactors are investigating options being researched by several vendors (PSC2000, EPRI, Schweitzer, etc.) to detect OPC faults. TVA has sent representatives to evaluate the PSC2000 solution, is working with EPRI to provide a possible testing facility for their proposed solution, and is in the process of contracting relay experts to evaluate various proposed protective relay solutions. There is currently no generic, off-the-shelf technology that has been proven to detect all the required open phase fault conditions for all plant and transformer designs.

TVA is fully engaged in the development of the NEI OPC Guidance Document, as well as development of enhancements to software tools being used to analyze OPC faults. TVA has provided technical expertise to participate in the NEI steering committee and are providing technical experts in a leadership capacity to aid in the development of the only nuclear QA software, ETAP.

With the goal of ensuring accurate detection without compromising nuclear safety or increasing plant risk, this new OPC technology is being thoroughly evaluated, will be tested, and will be fully analyzed before installation.

Vulnerability studies of the OPC faults have been completed for WBN and additional operator meetings are being scheduled to communicate the results. For the analyzed configurations, the vulnerability studies showed existing protection automatically actuates and provides protection to the Class-1E system for grounded open phase conditions.

Vulnerability to an ungrounded open phase condition has been identified for some analyzed configurations.

The TVA nuclear fleet has endorsed the generic schedule provided in the Industry OPC Initiative.

It is WBNs intention to meet the milestones of this schedule; however, deviations may be required to accommodate outage schedules, software and hardware availability, manufacturers delivery capabilities, licensing delays, etc.

Any deviation from the Industry OPC Initiative schedule will be documented through the deviation/exemption process addressed in the NEI OPC Guidance Document.

E 3 2 of 2